W DOC AIRBUS | AMM A320F

Test of the Air Relief Valves,the Reservoir Pressure Check Valves,the Pressure Gages and the Automatic Drain Valve of the Reservoir Pressurizing System


TASK 29-14-00-280-001-A
Test of the Air Relief Valves,the Reservoir Pressure Check Valves,the Pressure Gages and the Automatic Drain Valve of the Reservoir Pressurizing System


ZONE: 147
ZONE: 195
FIN: 1005GM
FIN: 1383GM
FIN: 1388GM
FIN: 2005GM
FIN: 2383GM
FIN: 2388GM
FIN: 3005GM
FIN: 3383GM
FIN: 3388GM
1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
3
CAP - BLANKING
No specific
1
CONTAINER 3 L(3/4 USGAL)
No specific
AR
PLUG - BLANKING
No specific
AR
SAFETY CLIP - CIRCUIT BREAKER
No specific
2
WARNING NOTICE(S)
No specific
Torque wrench: range to between 1.3 and 1.2 m.daN (115.04 and 106.19 lbf.in ) T
No specific
Torque wrench: range to between 1.7 and 1.5 m.daN (12.54 and 11.06 lbf.ft ) T
No specific
Torque wrench: range to between 4.3 and 3.9 m.daN (31.71 and 28.76 lbf.ft ) T
97A29102035000
1
CONNECTOR-PRESSURIZING,HYDRAULIC TANK
98D29003501000
1
FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR
98D29003501003
1
FILL UNIT - AIR
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
147
MAIN GEAR WELL AND HYDRAULIC COMPARTMENT
195
HYDRAULIC COMPT AND FAIRINGS
195BB
 C. Referenced Information
REFERENCE
DESIGNATION
TASK 12-12-29-611-001-A
Fill the Hydraulic Fluid Reservoir with a Hand Pump
TASK 12-12-29-611-002-A
Fill the Hydraulic Fluid Reservoir with a Hydraulic Service Cart
TASK 29-00-00-864-001-A
Put the Related Hydraulic System in the Depressurized Configuration before Maintenance Action
TASK 29-00-00-910-002-A
Safety Procedures of the Hydraulic System
TASK 29-10-00-680-001-A
Drainage of the Reservoir of the Green Hydraulic System
TASK 29-10-00-680-002-A
Drainage of the Reservoir of the Yellow Hydraulic System
TASK 29-10-00-680-003-A
Drainage of the Reservoir of the Blue Hydraulic System
TASK 29-11-41-000-001-A
Removal of the Green Hydraulic Reservoir
TASK 29-11-41-400-001-A
Installation of the Green Hydraulic Reservoir
TASK 29-12-41-000-001-A
Removal of the Blue Hydraulic Reservoir
TASK 29-12-41-400-001-A
Installation of the Blue Hydraulic Reservoir
TASK 29-13-41-000-002-A
Removal of the Yellow Hydraulic Reservoir
TASK 29-13-41-400-002-A
Installation of the Yellow Hydraulic Reservoir
TASK 29-14-00-614-001-A
Depressurization of the Hydraulic Reservoirs
TASK 29-14-17-000-001-A
Removal of the Air Relief Valve of the Green Hydraulic System
TASK 29-14-17-000-002-A
Removal of the Air Relief Valve of the Blue Hydraulic System
TASK 29-14-17-000-003-A
Removal of the Air Relief Valve of the Yellow Hydraulic System
TASK 29-14-17-400-001-A
Installation of the Air Relief Valve of the Green Hydraulic System
TASK 29-14-17-400-002-A
Installation of the Air Relief Valve of the Blue Hydraulic System
TASK 29-14-17-400-003-A
Installation of the Air Relief Valve of the Yellow Hydraulic System
TASK 29-14-18-000-001-A
Removal of the Reservoir Pressure Check Valves
TASK 29-14-18-400-001-A
Installation of the Reservoir Pressure Check Valves
TASK 36-12-00-710-001-A
Operational Test of the APU Bleed Air Supply and Crossbleed Systems
TASK 49-00-00-860-005-A
APU Start by External Power
TASK 49-00-00-860-005-A-01
APU Start by Batteries
TASK 49-00-00-860-006-A
APU Shutdown by External Power
TASK 49-00-00-860-006-A-01
APU Shutdown by Batteries
TASK 49-00-00-860-008-A
APU Start by External Power
TASK 49-00-00-860-008-A-01
APU Start by Batteries
TASK 49-00-00-860-009-A
APU Shutdown by External Power (131-9(A))
TASK 49-00-00-860-009-A-01
APU Shutdown by Batteries (131-9(A))
3. Job Set-up
Subtask 29-14-00-865-067-A
A. Open, safety and tag this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C ALL
123VUB HYD/ELEC PUMP2701GJAB09
123VUY HYD/ELEC/PUMP3802GXAB06
123VUY HYD/ELEC/ELEC PUMP/NORM3801GXAB03
Subtask 29-14-00-860-060-A
B. Aircraft Maintenance Configuration
WARNING: OBEY THE HYDRAULIC SAFETY PROCEDURES.
   (1) Obey the hydraulic safety procedures (Ref. AMM TASK 29-00-00-910-002).
   (2) Depressurize the Green, Yellow and Blue hydraulic systems and put them in the maintenance configuration (Ref. AMM TASK 29-00-00-864-001).
   (3) Put WARNING NOTICE(S) to tell persons not to pressurize the hydraulic systems:
  • In the flight compartment near the hydraulic section 40VU of the overhead panel.
  • On the ground service panels of the Green, Yellow and Blue hydraulic systems.
   (4) Depressurize the reservoirs of the Green, Yellow and Blue hydraulic systems.
(Ref. AMM TASK 29-14-00-614-001).
   (5) Drain the reservoirs of the Green, Yellow and Blue hydraulic systems:
   (6) Open the access door 195BB.
4. Procedure
Subtask 29-14-00-320-050-A
A. Manufacturing of the Test Manifold
   (1) If not available make a test manifold.
   (2) Connect a flexible hose (2) with a length of approximately 1.0 m (3.28 ft.) to the test manifold (3).
   (3) Connect a calibrated pressure gage (1) with a range to 10.0 bar (145.0377 psi) to the hose (2).
   (4) Install a gas-charging valve (5) with a packing (4) in the test manifold (3).
Subtask 29-14-00-480-050-A
B. Test Preparation
CAUTION: USE A SECOND WRENCH TO APPLY COUNTERTORQUE TO THE UNION WHEN YOU DISCONNECT/CONNECT HYDRAULIC LINES ON UNIONS. IF YOU DO NOT USE THE SECOND WRENCH, THERE IS A RISK THAT YOU WILL LOOSEN OR TIGHTEN THE UNION TOO MUCH.
   (1) Disconnect the air supply line (20) from the reservoir pressurization unit (21).
   (2) Install a blanking cap on the open port at the reservoir pressurization unit (21).
   (3) Put the open end of the air supply line (20) in a CONTAINER 3 L(3/4 USGAL).
   (4) Fill the container with water so that the end of the air supply line (20) is under water.
Subtask 29-14-00-280-050-A
C. Test of the Air Relief Valve (1005GM), the Reservoir Pressure Check Valve (1388GM) and the Reservoir Pressure Gage (1383GM) of the Green Hydraulic Reservoir Pressurizing System
CAUTION: USE A SECOND WRENCH TO APPLY COUNTERTORQUE TO THE UNION WHEN YOU DISCONNECT/CONNECT HYDRAULIC LINES ON UNIONS. IF YOU DO NOT USE THE SECOND WRENCH, THERE IS A RISK THAT YOU WILL LOOSEN OR TIGHTEN THE UNION TOO MUCH.
   (1) Disconnect the line end fittings (12) and (13) from the fitting (15) of the reservoir (16).
   (2) Install a PLUG - BLANKING in the open line end fittings (12) and (13).
   (3) Install an adapter hose (14) at the fitting (15).
   (4) Install a CAP - BLANKING on the open port of the fitting (15).
   (5) Put the open end of the adapter hose (14) in a container.
   (6) Fill the container with water so that end of the adapter hose (14) is under water.
   (7) Install the test manifold (3) to the drain valve (17) of the reservoir (16).
NOTE: Make sure that the gage (1) of the test manifold (3) is correctly calibrated.
   (8) Connect the 98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR or 98D29003501003 FILL UNIT - AIR (10) to the gas-charging valve (5).
NOTE: If the 98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR and 98D29003501003 FILL UNIT - AIR is not available, you can use an alternative air supply. The supply must have a pressure of 7.0 bar (101.5264 psi) and it must have a filter. The rating of the filter must be 5 microns or better.
As alternative to the air source, you can use the nitrogen source with 97A29102035000 CONNECTOR-PRESSURIZING,HYDRAULIC TANK.
   (9) Open the gas-charging valve (5).
   (10) Slowly increase the pressure until you read 4.8 bar (69.6181 psi) on the gage (1).
   (11) Make sure that no air bubbles come out of the adapter hose (14) and the air supply line (20).
     (a) If air bubbles come out of the line end of the air supply line (20) during this test:
   (12) Slowly increase the pressure until air bubbles come out of the adapter hose (14).
   (13) Monitor and record this pressure value. The pressure value must be between 5.1 bar (73.9692 psi) and 5.5 bar (79.7707 psi).
     (a) If the pressure value is not in this range:
   (14) Compare the pressure value on the gage (1) of the test manifold (3) with the pressure value of the reservoir pressure gage (11).
     (a) If the pressure gage of the reservoir shows a different value:
   (15) Close the gas-charging valve (5).
   (16) Monitor and record the pressure value when the air bubbles stop to come out of the line end of the adapter hose (14). The pressure value must be between 5.1 bar (73.9692 psi) and 5.3 bar (76.8700 psi).
     (a) If the pressure value is not in this range:
   (17) Depressurize the 98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR or 98D29003501003 FILL UNIT - AIR (10) or the alternative pressure supply.
   (18) Depressurize the reservoir of the Green hydraulic system
(Ref. AMM TASK 29-14-00-614-001).
   (19) Do the complete test procedure again two times to make sure that the system operates correct.
   (20) Disconnect the 98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR or 98D29003501003 FILL UNIT - AIR (10) or the alternative pressure supply from the gas-charging valve (5).
   (21) Disconnect the test manifold (3) from the drain valve (17) of the reservoir (16).
   (22) Remove the blanking cap from the fitting (15).
   (23) Make sure that the hydraulic line end-fittings are serviceable.
   (24) Loosely install the line end fitting (12) on the fitting (15).
CAUTION: USE A SECOND WRENCH TO APPLY COUNTERTORQUE TO THE UNION WHEN YOU DISCONNECT/CONNECT HYDRAULIC LINES ON UNIONS. IF YOU DO NOT USE THE SECOND WRENCH, THERE IS A RISK THAT YOU WILL LOOSEN OR TIGHTEN THE UNION TOO MUCH.
   (25) TORQUE the line end fitting (12) to between 4.3 and 3.9 m.daN (31.71 and 28.76 lbf.ft ) T.
   (26) Remove the adapter hose (14) from the fitting (15).
   (27) Make sure that the hydraulic line end-fittings are serviceable.
   (28) Loosely install the line end fitting (13) on the fitting (15).
   (29) TORQUE the line end fitting (13) to between 1.3 and 1.2 m.daN (115.04 and 106.19 lbf.in )
T.
Subtask 29-14-00-280-051-A
D. Test of the Air Relief Valve (2005GM), the Reservoir Pressure Check Valve (2388GM) and the Reservoir Pressure Gage (2383GM) of the Blue Hydraulic Reservoir Pressurizing System
CAUTION: USE A SECOND WRENCH TO APPLY COUNTERTORQUE TO THE UNION WHEN YOU DISCONNECT/CONNECT HYDRAULIC LINES ON UNIONS. IF YOU DO NOT USE THE SECOND WRENCH, THERE IS A RISK THAT YOU WILL LOOSEN OR TIGHTEN THE UNION TOO MUCH.
   (1) Disconnect the line end fittings (12) and (13) from the fitting (15) of the reservoir (16).
   (2) Install a PLUG - BLANKING in the open line end fittings (12) and (13).
   (3) Install an adapter hose (14) at the fitting (15).
   (4) Install a CAP - BLANKING on the open port of the fitting (15).
   (5) Put the open end of the adapter hose (14) in a container.
   (6) Fill the container with water so that end of the adapter hose (14) is under water.
   (7) Install the test manifold (3) to the drain valve (17) of the reservoir (16).
NOTE: Make sure that the gage (1) of the test manifold (3) is correctly calibrated.
   (8) Connect the
98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR or 98D29003501003 FILL UNIT - AIR (10) to the gas-charging valve (5).
NOTE: If the 98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR and 98D29003501003 FILL UNIT - AIR is not available, you can use an alternative air supply. The supply must have a pressure of 7.0 bar (101.5264 psi) and it must have a filter. The rating of the filter must be 5 microns or better.
As alternative to the air source, you can use the nitrogen source with 97A29102035000 CONNECTOR-PRESSURIZING,HYDRAULIC TANK.
   (9) Open the gas-charging valve (5).
   (10) Slowly increase the pressure until you read 4.8 bar (69.6181 psi) on the gage (1).
   (11) Make sure that no air bubbles come out of the adapter hose (14) and the air supply line (20).
     (a) If air bubbles come out of the line end of the air supply line (20) during this test:
   (12) Slowly increase the pressure until air bubbles come out of the adapter hose (14).
   (13) Monitor and record this pressure value. The pressure value must be between 5.1 bar (73.9692 psi) and 5.5 bar (79.7707 psi).
     (a) If the pressure value is not in this range:
   (14) Compare the pressure value on the gage (1) of the test manifold (3) with the pressure value of the reservoir pressure gage (11).
     (a) If the pressure gage of the reservoir shows a different value:
   (15) Close the gas-charging valve (5).
   (16) Monitor and record the pressure value when the air bubbles stop to come out of the line end of the adapter hose (14). The pressure value must be between 5.1 bar (73.9692 psi) and 5.3 bar (76.8700 psi).
     (a) If the pressure value is not in this range:
   (17) Depressurize the 98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR or 98D29003501003 FILL UNIT - AIR (10) or the alternative pressure supply.
   (18) Depressurize the reservoir of the Blue hydraulic system.
(Ref. AMM TASK 29-14-00-614-001).
   (19) Do the complete test procedure again two times to make sure that the system operates correct.
   (20) Disconnect the 98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR or 98D29003501003 FILL UNIT - AIR (10) or the alternative pressure supply from the gas-charging valve (5).
   (21) Disconnect the test manifold (3) from the drain valve (17) of the reservoir (16).
   (22) Remove the blanking cap from the fitting (15).
   (23) Make sure that the hydraulic line end-fittings are serviceable.
   (24) Loosely install the line end fitting (12) on the fitting (15).
CAUTION: USE A SECOND WRENCH TO APPLY COUNTERTORQUE TO THE UNION WHEN YOU DISCONNECT/CONNECT HYDRAULIC LINES ON UNIONS. IF YOU DO NOT USE THE SECOND WRENCH, THERE IS A RISK THAT YOU WILL LOOSEN OR TIGHTEN THE UNION TOO MUCH.
   (25) TORQUE the line end fitting (12) to between 4.3 and 3.9 m.daN (31.71 and 28.76 lbf.ft ) T.
   (26) Remove the adapter hose (14) from the fitting (15).
   (27) Make sure that the hydraulic line end-fittings are serviceable.
   (28) Loosely install the line end fitting (13) on the fitting (15).
   (29) TORQUE the line end fitting (13) to between 1.3 and 1.2 m.daN (115.04 and 106.19 lbf.in )
T.
Subtask 29-14-00-280-052-A
E. Test of the Air Relief Valve (3005GM), the Reservoir Pressure Check Valve (3388GM) and the Reservoir Pressure Gage (3383GM) of the Yellow Hydraulic Reservoir Pressurizing System
CAUTION: USE A SECOND WRENCH TO APPLY COUNTERTORQUE TO THE UNION WHEN YOU DISCONNECT/CONNECT HYDRAULIC LINES ON UNIONS. IF YOU DO NOT USE THE SECOND WRENCH, THERE IS A RISK THAT YOU WILL LOOSEN OR TIGHTEN THE UNION TOO MUCH.
   (1) Disconnect the line end fittings (12) and (13) from the fitting (15) of the reservoir (16).
   (2) Install a PLUG - BLANKING in the open line end fittings (12) and (13).
   (3) Install an adapter hose (14) at the fitting (15).
   (4) Install a CAP - BLANKING on the open port of the fitting (15).
   (5) Put the open end of the adapter hose (14) in a container.
   (6) Fill the container with water so that end of the adapter hose (14) is under water.
   (7) Install the test manifold (3) to the drain valve (17) of the reservoir (16).
NOTE: Make sure that the gage (1) of the test manifold (3) is correctly calibrated.
   (8) Connect the
98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR or 98D29003501003 FILL UNIT - AIR (10) to the gas-charging valve (5).
NOTE: If the 98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR and 98D29003501003 FILL UNIT - AIR is not available, you can use an alternative air supply. The supply must have a pressure of 7.0 bar (101.5264 psi) and it must have a filter. The rating of the filter must be 5 microns or better.
As alternative to the air source, you can use the nitrogen source with 97A29102035000 CONNECTOR-PRESSURIZING,HYDRAULIC TANK.
   (9) Open the gas-charging valve (5).
   (10) Slowly increase the pressure until you read 4.8 bar (69.6181 psi) on the gage (1).
   (11) Make sure that no air bubbles come out of the adapter hose (14) and the air supply line (20).
     (a) If air bubbles come out of the line end of the air supply line (20) during this test:
   (12) Slowly increase the pressure until air bubbles come out of the adapter hose (14).
   (13) Monitor and record this pressure value. The pressure value must be between 5.1 bar (73.9692 psi) and 5.5 bar (79.7707 psi).
     (a) If the pressure value is not in this range:
   (14) Compare the pressure value on the gage (1) of the test manifold (3) with the pressure value of the reservoir pressure gage (11).
     (a) If the pressure gage of the reservoir shows a different value:
   (15) Close the gas-charging valve (5).
   (16) Monitor and record the pressure value when the air bubbles stop to come out of the line end of the adapter hose (14). The pressure value must be between 5.1 bar (73.9692 psi) and 5.3 bar (76.8700 psi).
     (a) If the pressure value is not in this range:
   (17) Depressurize the 98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR or 98D29003501003 FILL UNIT - AIR (10) or the alternative pressure supply.
   (18) Depressurize the reservoir of the Yellow hydraulic system.
(Ref. AMM TASK 29-14-00-614-001).
   (19) Do the complete test procedure again two times to make sure that the system operates correct.
   (20) Disconnect the 98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR or 98D29003501003 FILL UNIT - AIR (10) or the alternative pressure supply from the gas-charging valve (5).
   (21) Disconnect the test manifold (3) from the drain valve (17) of the reservoir (16).
   (22) Remove the blanking cap from the fitting (15).
   (23) Make sure that the hydraulic line end-fittings are serviceable.
   (24) Loosely install the line end fitting (12) on the fitting (15).
CAUTION: USE A SECOND WRENCH TO APPLY COUNTERTORQUE TO THE UNION WHEN YOU DISCONNECT/CONNECT HYDRAULIC LINES ON UNIONS. IF YOU DO NOT USE THE SECOND WRENCH, THERE IS A RISK THAT YOU WILL LOOSEN OR TIGHTEN THE UNION TOO MUCH.
   (25) TORQUE the line end fitting (12) to between 4.3 and 3.9 m.daN (31.71 and 28.76 lbf.ft ) T.
   (26) Remove the adapter hose (14) from the fitting (15).
   (27) Make sure that the hydraulic line end-fittings are serviceable.
   (28) Loosely install the line end fitting (13) on the fitting (15).
   (29) TORQUE the line end fitting (13) to between 1.3 and 1.2 m.daN (115.04 and 106.19 lbf.in )
T.
Subtask 29-14-00-080-050-A Subtask 29-14-00-280-053-A
G. Test of the Automatic Drain Valve of the Reservoir Pressurization Unit
   (1) Make sure that the reservoirs of the Green, Blue and Yellow hydraulic systems are depressurized.
(
Ref. AMM TASK 29-14-00-614-001).
   (2) Start the APU (Ref. AMM D/O 49-00-00-86) or
(Ref. AMM TASK 49-00-00-860-008) or
(Ref. AMM TASK 49-00-00-860-005).
   (3) Make sure that the bleed air supply from the APU is set to supply the reservoir pressurizing system (Ref. AMM TASK 36-12-00-710-001).
   (4) Make sure that the automatic drain valve (22) of the reservoir pressurization unit (21) is closed (you can see the green indicator).
   (5) Stop the operation of the APU (Ref. AMM D/O 49-00-00-86) or
(Ref. AMM TASK 49-00-00-860-006) or
(Ref. AMM TASK 49-00-00-860-009).
   (6) Depressurize the reservoirs of the Green, Yellow and Blue hydraulic systems.
(Ref. AMM TASK 29-14-00-614-001).
   (7) Do the test procedure of the automatic drain valve again two times to make sure that the operation is correct.
5. Close-up
Subtask 29-14-00-860-061-A
A. Put the aircraft back to the serviceable condition.
   (1) Fill the reservoirs of the Green, Yellow and Blue hydraulic systems (Ref. AMM TASK 12-12-29-611-001), or (Ref. AMM TASK 12-12-29-611-002).
   (2) Remove the containers.
   (3) Make sure that the work area is clean and clear of tools and other items.
   (4) Close the access door 195BB.
   (5) Remove the warning notices from:
  • The flight compartment
  • The ground service panels of the Green, Yellow and Blue hydraulic systems.
   (6) Remove the ground support and maintenance equipment, the special and standard tools and all other items.
Subtask 29-14-00-865-068-A
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C ALL
123VUB HYD/ELEC PUMP2701GJAB09
123VUY HYD/ELEC/PUMP3802GXAB06
123VUY HYD/ELEC/ELEC PUMP/NORM3801GXAB03
[Rev.10 from 2021] 2026.04.01 00:24:13 UTC