Installation of the Pylon Bleed-Air Ducts


TASK 36-11-49-400-013-A
Installation of the Pylon Bleed-Air Ducts


WARNING: MAKE SURE THAT THE PNEUMATIC SYSTEM IS DEPRESSURIZED BEFORE YOU START WORK. PRESSURIZED AIR CAN CAUSE INJURY TO PERSONNEL.
WARNING: PUT THE SAFETY DEVICES AND THE WARNING NOTICES IN POSITION BEFORE YOU START A TASK ON OR NEAR:
  • THE FLIGHT CONTROLS
  • THE FLIGHT CONTROL SURFACES
  • THE LANDING GEAR AND THE RELATED DOORS
  • COMPONENTS THAT MOVE.
MOVEMENT OF COMPONENTS CAN KILL OR CAUSE INJURY TO PERSONS AND/OR CAN CAUSE DAMAGE TO THE EQUIPMENT.
1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
AR
ACCESS PLATFORM 5M (16 FT)- ADJUSTABLE
No specific
AR
WARNING NOTICE(S)
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
413DT, 423DT, 471AL, 471AR, 481AL, 481AR
 C. Expendable Parts
FIG.ITEM
DESIGNATION
IPC-CSN
4
SEALS
AIPC 36-11-06-01-140
 D. Referenced Information
REFERENCE
DESIGNATION
TASK 20-26-00-910-002-A
Installation of Expansion Joints
TASK 24-41-00-861-002-A
Energize the Aircraft Electrical Circuits from the External Power
TASK 24-41-00-861-002-A-01
Energize the Aircraft Electrical Circuits from the APU
TASK 24-41-00-862-002-A
De-energize the Aircraft Electrical Circuits Supplied from the External Power
TASK 24-41-00-862-002-A-01
De-energize the Aircraft Electrical Circuits Supplied from the APU
TASK 36-11-42-000-001-A
Removal of the Bleed-Air Precooler Exchanger
TASK 36-11-42-400-001-A
Installation of the Bleed-Air Precooler Exchanger
TASK 36-11-43-000-001-A
Removal of the Fan-Air Valve Control-Thermostat
TASK 36-11-43-400-001-A
Installation of the Fan-Air Valve Control-Thermostat
TASK 36-11-55-000-001-A
Removal of the Bleed-Pressure-Regulator Valve Control-Solenoid
TASK 36-11-55-400-001-A
Installation of the Bleed-Pressure-Regulator Valve Control-Solenoid
TASK 36-12-00-860-001-A
Pressurization of the Bleed System with the APU
TASK 36-12-00-860-002-A
Pressurization of the Bleed System through the HP Ground Connector
TASK 49-00-00-860-009-A
APU Shutdown by External Power (131-9(A))
TASK 49-00-00-860-009-A-01
APU Shutdown by Batteries (131-9(A))
3. Job Set-up
Subtask 36-11-49-860-058-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
   (1) Make sure that the aircraft electrical circuits are energized (Ref. AMM TASK 24-41-00-861-002) or (Ref. AMM TASK 24-41-00-861-002).
   (2) Make sure that engine 1(2) shutdown occurred for a minimum of 5 minutes before you do this procedure.
   (3) On AIR COND panel 30VU:
  • Make sure that the ENG 1(2) BLEED pushbutton switch is released (the OFF legend is on),
  • Make sure that the APU BLEED pushbutton switch is released (the ON legend is off),
  • Make sure that the WARNING NOTICE(S) to tell persons not to operate the pneumatic system is in position.
   (4) On ENG panel 115VU:
  • Make sure that the WARNING NOTICE(S) to tell persons not to start engine 1(2) is in position.
   (5) On the HP ground connector:
  • Make sure that the WARNING NOTICE(S) to tell persons not to pressurize the pneumatic system is in position.
   (6) On the ENG section of maintenance panel 50VU:
  • Make sure that the ON legend of the ENG/FADEC GND PWR 1(2) pushbutton switch is off,
  • Make sure that the WARNING NOTICE(S) to tell persons not to energize FADEC 1(2) is in position.
   (7) Make sure that the ACCESS PLATFORM 5M (16 FT)- ADJUSTABLE is in position below the engine.
Subtask 36-11-49-010-200-B ** ON A/C NOT FOR ALL
B. Get Access
   (1) Make sure that the fan-air valve-control thermostat (Ref. AMM TASK 36-11-43-000-001) is removed.
   (2) Make sure that the bleed pressure-regulator valve control-solenoid (Ref. AMM TASK 36-11-55-000-001) is removed.
   (3) Make sure that the bleed-air precooler exchanger (Ref. AMM TASK 36-11-42-000-001) is removed.
   (4) Make sure that these access panels are removed:
     (a) For the left pylon:
     (b) For the right pylon:
Subtask 36-11-49-865-072-A ** ON A/C NOT FOR ALL
C. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
49VUAIR BLEED/ENG 1/CTL3HA1D12
49VUAIR BLEED/ENG 1/MONG2HA1D11
122VUAIR BLEED/ENG 2/CTL3HA2Z23
122VUAIR BLEED/ENG 2/MONG2HA2Z22
4. Procedure
Subtask 36-11-49-420-057-B ** ON A/C NOT FOR ALL
A. Installation of the Wing Connection Sleeve
   (1) If you use the APU to energize the electrical circuits, stop the APU:
   (2) In the cockpit, on the SD bleed page:
     (a) Make sure that the pressure and the temperature of the bleed-air duct system are in ambient conditions.
WARNING: MAKE SURE THAT THE PNEUMATIC SYSTEM IS DEPRESSURIZED BEFORE YOU START WORK. PRESSURIZED AIR CAN CAUSE INJURY TO PERSONNEL.
WARNING: DO NOT TOUCH THE UNIT UNTIL IT IS SUFFICIENTLY COOL TO PREVENT BURNS WHEN YOU DO THE MAINTENANCE TASK(S).
   (3) Remove the blanking plugs from the disconnected line ends.
   (4) Install a new AIPC 36-11-06-01-140 SEALS (4) in the first expansion joint (6) (Ref. AMM TASK 20-26-00-910-002).
   (5) Install a new AIPC 36-11-06-01-140 SEALS (4) in the other expansion joint (6) (Ref. AMM TASK 20-26-00-910-002).
   (6) Install the wing connection sleeve (3).
Subtask 36-11-49-420-071-C ** ON A/C NOT FOR ALL
B. Installation of the Pylon Bleed-Air Ducts (Ref. AMM TASK 20-26-00-910-002)
   (1) Install the clamp (2) but do not tighten it at this time.
   (2) Install the expansion joint (6) on the wing connection sleeve (3).
   (3) Install the clamp (7) on the expansion joint (6).
   (4) Install the other expansion joint (6). Do not tighten the clamp (7).
   (5) Install the aft pipe of the exchanger (11).
   (6) Install the bolts (8), the washers (9) and the nuts (10) and tighten the nuts.
   (7) Install the tab (13) and the nut (12) on the clamp (7) and tighten the nut.
   (8) Tighten the clamps (7) and (2).
Subtask 36-11-49-820-050-A ** ON A/C NOT FOR ALL
C. Make sure that the expansion joints (6) are in the correct position in relation to the wing connection sleeve (3) and the pipe (11).
Subtask 36-11-49-720-062-A ** ON A/C NOT FOR ALL
D. Do this test:
   (1) Pressurize the bleed system through the HP ground connector (Ref. AMM TASK 36-12-00-860-002) or with the APU (Ref. AMM TASK 36-12-00-860-001).
   (2) 0n the panel 30VU, put the X-BLEED selector switch in the OPEN position.
   (3) If you pressurize the bleed system through the HP ground connector, the supplied pressure 30 psi (2.07 bar) must be stable.
   (4) Make sure that there are no leaks at the junctions of the installed duct.
5. Close-up
Subtask 36-11-49-865-073-A ** ON A/C NOT FOR ALL
A. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
49VUAIR BLEED/ENG 1/CTL3HA1D12
49VUAIR BLEED/ENG 1/MONG2HA1D11
122VUAIR BLEED/ENG 2/CTL3HA2Z23
122VUAIR BLEED/ENG 2/MONG2HA2Z22
Subtask 36-11-49-410-062-B ** ON A/C NOT FOR ALL
B. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.
   (2) Install the fan-air valve-control thermostat (Ref. AMM TASK 36-11-43-400-001).
   (3) Install the bleed-pressure-regulated valve-control solenoid (Ref. AMM TASK 36-11-55-400-001).
   (4) Install the bleed-air precooler exchanger (Ref. AMM TASK 36-11-42-400-001).
   (5) Install these access panels:
     (a) For the left pylon:
     (b) For the right pylon:
Subtask 36-11-49-942-060-A ** ON A/C NOT FOR ALL
C. Close Access
   (1) Remove the access platform(s).
   (2) Remove the WARNING NOTICE(S).
Subtask 36-11-49-862-070-A ** ON A/C NOT FOR ALL
D. De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002) or (Ref. AMM TASK 24-41-00-862-002).