Energize the Aircraft Electrical Circuits from the External Power
TASK 24-41-00-861-002-A
Energize the Aircraft Electrical Circuits from the External Power
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 24-41-00-860-050-A
Subtask 24-41-00-861-051-B
[Rev.10 from 2021]
2026.03.31 23:24:05 UTC
Energize the Aircraft Electrical Circuits from the External Power
WARNING:
MAKE SURE THAT ALL THE CIRCUITS IN MAINTENANCE ARE ISOLATED BEFORE YOU SUPPLY ELECTRICAL POWER TO THE AIRCRAFT. UNWANTED ELECTRICAL POWER CAN BE DANGEROUS.
CAUTION:
DO NOT USE A GROUND POWER UNIT WITH A CAPACITY LESS THAN 90 KVA. IF YOU USE A LESS POWERFUL UNIT:
1. Reason for the Job- AN OVERLOAD OF THE GROUND POWER UNIT COULD OCCUR
- IT COULD BE NECESSARY TO RESET MANY COMPUTERS ON THE AIRCRAFT.
NOTE: There are alternative methods for this procedure. This task gives one of the methods. For the other methods, refer to the other tasks in this page block.
2. Job Set-up InformationA. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| 98A24403000000 | 1 | CABLE HOLDING STRAP |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 121AL |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 12-31-31-660-001-A | Cold Weather Maintenance - Indicating/Recording systems and Navigation |
| TASK 12-34-24-869-002-A | Aircraft Grounding (Earthing) for the Maintenance Operations |
| TASK 12-34-24-869-002-A-01 | Aircraft Grounding (Earthing) during Transit, Turnaround or Overnight Stop |
| TASK 24-41-00-040-001-A | Visual Inspection of the External Power Receptacle |
| TASK 31-60-00-860-001-A | EIS Start Procedure |
| TASK 31-60-00-860-002-A | EIS Stop Procedure |
| ESPM 2055100 | |
| TASK 24-41-51-000-001-A | Removal of the External Power Receptacle (for corrective action) |
| TASK 24-41-51-400-001-A | Installation of the External Power Receptacle (for corrective action) |
Subtask 24-41-00-860-050-A
A. Aircraft Maintenance Configuration
Subtask 24-41-00-010-050-A NOTE: In the avionics compartment, if the temperature is below -15 deg.C (5.00 deg.F), do the cold-weather maintenance procedure (Ref. AMM TASK 12-31-31-660-001).
(1) Ground (Earth) the aircraft if necessary (Ref. AMM TASK 12-34-24-869-002): - For grounding (earthing) you must obey the local area regulations.
B. Get Access
(1) Open the access door 121AL to get access to the external power receptacle and the panel 108VU.
Subtask 24-41-00-480-050-A (1) Open the access door 121AL to get access to the external power receptacle and the panel 108VU.
C. Install the cable holding strap
(1) Attach the 98A24403000000 CABLE HOLDING STRAP to the feeder cable.
(2) Connect the snap hook of the cable holding strap to the fitting on the aircraft structure.
Subtask 24-41-00-420-050-A (1) Attach the 98A24403000000 CABLE HOLDING STRAP to the feeder cable.
(2) Connect the snap hook of the cable holding strap to the fitting on the aircraft structure.
D. Connection of the connector
(a) If you find contamination:
(a) If you find burns and/or pits, scratches and/or nibbles, and/or if the pins are not correctly aligned:
4. ProcedureWARNING:
BEFORE YOU CONNECT THE GROUND POWER UNIT TO THE EXTERNAL POWER RECEPTACLE OF THE AIRCRAFT, MAKE SURE THAT THE EXTERNAL ELECTRICAL POWER SUPPLY IS NOT ENERGIZED. IF IT IS ENERGIZED, DANGEROUS ARCING CAN OCCUR.
CAUTION:
MAKE SURE THAT THE CABLE STRAP SUPPORTS ALL THE WEIGHT OF THE CABLE WHEN THE CONNECTOR IS CONNECTED. THIS PREVENTS DAMAGE TO THE EXTERNAL POWER RECEPTACLE.
CAUTION:
BEFORE YOU CONNECT THE GROUND POWER UNIT TO THE AIRCRAFT, MAKE SURE THAT THERE ARE NO FOREIGN OBJECTS OR FLUID IN THE EXTERNAL POWER RECEPTACLE OR THE GPU CONNECTOR. FOREIGN OBJECTS AND FLUID CAN CAUSE AN OVERHEAT AND/OR DAMAGE TO EQUIPMENT.
(1) Examine the external power-supply cable and the external power receptacle before you do the connection. (a) If you find contamination:
- Clean the external power receptacle or the GPU connector ESPM 2055100.
- Replace the external power receptacle (Ref. AMM TASK 24-41-51-000-001) and (Ref. AMM TASK 24-41-51-400-001).
(a) If you find burns and/or pits, scratches and/or nibbles, and/or if the pins are not correctly aligned:
- Replace the external power receptacle (Ref. AMM TASK 24-41-51-000-001) and (Ref. AMM TASK 24-41-51-400-001).
Subtask 24-41-00-861-051-B
A. Energize the Aircraft Electrical Circuit from the External Power
(1) On the ELEC panel 35VU, make sure that:
(4) If the protection circuits operate correctly:
(Ref. AMM TASK 31-60-00-860-001).
(a) On the ECAM control panel, push the ELEC key (on the lower ECAM DU, the ELEC page comes into view).
(b) On the ELEC page, make sure that these EXT PWR parameters are correct:
(Ref. AMM TASK 31-60-00-860-002).
(1) On the ELEC panel 35VU, make sure that:
- The GEN1, GEN2, APU GEN, BUS TIE, COMMERCIAL and AC ESS FEED pushbutton switches are pushed.
- All the other pushbutton switches are released.
- The BLOWER and EXTRACT pushbutton switches are pushed.
(4) If the protection circuits operate correctly:
- On the panel 108VU, the EXT PWR/NOT IN USE indicator light and EXT PWR/AVAIL caution light come on.
- On the panel 35VU, the AVAIL legend on the EXT PWR pushbutton switch comes on.
- The AVAIL legend goes off.
- The ON legend of the EXT PWR pushbutton switch
- The FAULT legend of the GEN1 and GEN2 pushbutton switches
- The OFF legend of the BAT1 and BAT2 pushbutton switches
- The OFF legend of the GALY & CAB pushbutton switch.
NOTE: That means the electronics rack ventilation operates correctly.
(8) On the panel 35VU, push the BAT1 and BAT2 pushbutton switches: - The OFF legends go off.
(Ref. AMM TASK 31-60-00-860-001).
(a) On the ECAM control panel, push the ELEC key (on the lower ECAM DU, the ELEC page comes into view).
(b) On the ELEC page, make sure that these EXT PWR parameters are correct:
- AC V = 115 + or - 5V,
- FRQ HZ = 400 + or - 10HZ.
(Ref. AMM TASK 31-60-00-860-002).
External Power Receptacle - Location