W DOC AIRBUS | AMM A320F

Installation of the Drain Valve of the Yellow Reservoir


TASK 29-13-41-400-005-A
Installation of the Drain Valve of the Yellow Reservoir


WARNING: MAKE SURE THAT THE GROUND SAFETY-LOCKS ARE IN POSITION ON THE LANDING GEAR. THIS WILL PREVENT UNWANTED MOVEMENT OF THE LANDING GEAR, AND THUS POSSIBLE INJURY TO PERSONS AND DAMAGE TO THE AIRCRAFT AND/OR EQUIPMENT.
ZONE: 196
1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
2
WARNING NOTICE(S)
No specific
Torque wrench: range to between 1.50 and 1.40 m.daN (11.06 and 10.32 lbf.ft ) T
 B. Consumable Materials
REFERENCE
DESIGNATION
(Material No.02ABA1)
Phosphate Ester Hydraulic Fluid-General Power - -
No specific
lockwire, corrosion resistant steel dia 0.8mm (0.032in.)
 C. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
196
HYDRAULIC COMPT AND FAIRINGS
196BB
 D. Expendable Parts
FIG.ITEM
DESIGNATION
IPC-CSN
15
PACKING
AIPC 29-13-41-01-170
 E. Referenced Information
REFERENCE
DESIGNATION
TASK 12-12-29-611-001-A
Fill the Hydraulic Fluid Reservoir with a Hand Pump
TASK 12-12-29-611-002-A
Fill the Hydraulic Fluid Reservoir with a Hydraulic Service Cart
TASK 24-41-00-861-002-A
Energize the Aircraft Electrical Circuits from the External Power
TASK 24-41-00-861-002-A-01
Energize the Aircraft Electrical Circuits from the APU
TASK 24-41-00-861-002-A-02
Energize the Aircraft Electrical Circuits from Engine 1(2)
TASK 24-41-00-862-002-A
De-energize the Aircraft Electrical Circuits Supplied from the External Power
TASK 24-41-00-862-002-A-01
De-energize the Aircraft Electrical Circuits Supplied from the APU
TASK 24-41-00-862-002-A-02
De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2)
TASK 29-00-00-864-001-A
Put the Related Hydraulic System in the Depressurized Configuration before Maintenance Action
TASK 29-00-00-910-002-A
Safety Procedures of the Hydraulic System
TASK 29-14-00-614-001-A
Depressurization of the Hydraulic Reservoirs
TASK 29-14-00-614-002-A
Pressurization of the Hydraulic Reservoirs through the Ground Connector
TASK 29-14-00-614-002-A-01
Pressurization of the Hydraulic Reservoirs with the Auxiliary Power Unit (APU)
TASK 29-23-00-860-001-A
Disconnection of the Isolation Coupling of the Power Transfer Unit (PTU)
TASK 29-23-00-860-002-A
Connection of the Isolation Coupling of the Power Transfer Unit (PTU)
3. Job Set-up
Subtask 29-13-41-860-056-A
A. Aircraft Maintenance Configuration
WARNING: OBEY THE HYDRAULIC SAFETY PROCEDURES.
   (1) Obey the hydraulic safety procedures (Ref. AMM TASK 29-00-00-910-002).
   (2) Make sure that the access door 196BB is open.
   (3) Make sure that the Yellow hydraulic system is depressurized and put it in the maintenance configuration.
(Ref. AMM TASK 29-00-00-864-001).
   (4) Make sure that the reservoir of the Yellow hydraulic system is depressurized.
(Ref. AMM TASK 29-14-00-614-001).
   (5) Make sure that the isolation coupling of the Power Transfer Unit (PTU) is disconnected. (Ref. AMM TASK 29-23-00-860-001).
   (6) Make sure that the WARNING NOTICE(S) are in position to to tell persons not to pressurize the Yellow hydraulic system:
  • in the cockpit on the hydraulic section 40VU of the overhead panel,
  • on the ground service panel of the Yellow hydraulic system.
Subtask 29-13-41-865-066-A
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
121VUHYDRAULIC/HYD POWER/Y3803GXN30
** ON A/C NOT FOR ALL
121VUHYDRAULIC/HYD POWER/Y3803GXN31
** ON A/C ALL
123VUY HYD/ELEC/PUMP3802GXAB06
123VUY HYD/ELEC/ELEC PUMP/NORM3801GXAB03
4. Procedure
Subtask 29-13-41-420-053-A Subtask 29-13-41-860-068-A
B. Preparation for the Test
   (1) Energize the aircraft electrical circuits
(
Ref. AMM TASK 24-41-00-861-002).
   (2) Fill the reservoir of the Yellow hydraulic system (Ref. AMM TASK 12-12-29-611-001) or (Ref. AMM TASK 12-12-29-611-002).
   (3) Pressurize the reservoir of the Yellow hydraulic system (Ref. AMM TASK 29-14-00-614-002).
Subtask 29-13-41-790-052-A
C. Leak Test of the Hydraulic Connections
   (1) Examine the connection of the drain valve (16) and the union.
   (2) Make sure that there are no leaks.
5. Close-up
Subtask 29-13-41-860-057-A
A. Put the aircraft back to the serviceable condition.
   (1) Make sure that the level of fluid in the reservoir of the Yellow hydraulic system is correct. Add fluid as necessary (Ref. AMM TASK 12-12-29-611-001) or (Ref. AMM TASK 12-12-29-611-002).
   (2) De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002).
   (3) Connect the isolation coupling of the Power Transfer Unit (PTU) (Ref. AMM TASK 29-23-00-860-002).
   (4) Remove the WARNING NOTICE(S).
Subtask 29-13-41-410-053-A
B. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.
   (2) Close the access door 196BB.
Subtask 29-13-41-865-067-A
C. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
121VUHYDRAULIC/HYD POWER/Y3803GXN30
** ON A/C NOT FOR ALL
121VUHYDRAULIC/HYD POWER/Y3803GXN31
** ON A/C ALL
123VUY HYD/ELEC/PUMP3802GXAB06
123VUY HYD/ELEC/ELEC PUMP/NORM3801GXAB03