Installation of the Door Frame Linings of the Right Forward Emergency Exit Door in Zone 232
TASK 25-23-47-400-009-A
Installation of the Door Frame Linings of the Right Forward Emergency Exit Door in Zone 232
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Referenced Information
3. Job Set-up
Subtask 25-23-47-860-054-A ** ON A/C NOT FOR ALL
Subtask 25-23-47-420-065-A ** ON A/C NOT FOR ALL
Subtask 25-23-47-865-064-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.03.31 23:31:46 UTC
Installation of the Door Frame Linings of the Right Forward Emergency Exit Door in Zone 232
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Referenced Information
| REFERENCE | DESIGNATION |
|---|---|
| TASK 11-00-00-400-002-A | Installation of the Decals |
| TASK 23-73-00-740-005-A | BITE-Test of the Cabin Intercommunication Data System (CIDS) through the CFDS |
| TASK 23-73-00-740-005-B | Interface and Power-Up Test of the Cabin Intercommunication Data System (CIDS) through the CFDS |
| TASK 24-42-00-861-001-A | Energize the Ground Service Network from the External Power |
| TASK 24-42-00-862-001-A | De-energize the Ground Service Network Supplied from the External Power |
| TASK 25-62-49-400-001-A | Installation of the Escape-Slide Inflation Reservoir |
| TASK 26-10-00-740-801-A | BITE Test of the Smoke Detection Function - System Test |
| TASK 33-51-11-400-001-A | Installation of the Cabin Emergency Light |
| TASK 33-51-13-400-001-A | Installation of the Cabin Wall-Mounted Emergency-Exit-Markers |
| TASK 33-51-16-400-001-A | Installation of the Emergency Exit Sign |
| TASK 52-22-00-010-001-A | Opening of the Emergency Exit Doors from the Passenger Compartment |
| TASK 52-22-00-410-001-A | Closing of the Emergency Exit Doors from the Passenger Compartment |
Subtask 25-23-47-860-054-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
(1) Make sure that the access platform is in position on the related emergency exit door.
(2) Make sure that the related emergency exit door is open (Ref. AMM TASK 52-22-00-010-001)
(3) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001)
Subtask 25-23-47-865-063-A ** ON A/C NOT FOR ALL (1) Make sure that the access platform is in position on the related emergency exit door.
(2) Make sure that the related emergency exit door is open (Ref. AMM TASK 52-22-00-010-001)
(3) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001)
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 49VU | COM/CIDS/DEU B/ESS | 153RH | G03 |
| 49VU | LIGHTING/EMER LT/CABIN | 2WL | H06 |
| 49VU | LIGHTING/EMER LT/CABIN | 1WL | H05 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | COM NAV/CIDS/DEU B/NORM | 162RH | M09 |
| ** ON A/C NOT FOR ALL | |||
| 122VU | LIGHTING/CABIN/EMER/LT | 3WL | V07 |
Subtask 25-23-47-420-065-A ** ON A/C NOT FOR ALL
A. Installation of the Door Frame Lining 232HX
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Put the door frame lining (20) in position on the door frame structure and engage the attach brackets to the yo-yo rolls.
(3) Install the handle section LWR (41), the washers (39) and the screws (40).
(4) Install the cover (43) to the handle section LWR (41).
Subtask 25-23-47-420-066-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Put the door frame lining (20) in position on the door frame structure and engage the attach brackets to the yo-yo rolls.
(3) Install the handle section LWR (41), the washers (39) and the screws (40).
(4) Install the cover (43) to the handle section LWR (41).
NOTE: Make sure that the lugs (42) of the cover (43) engage correctly and you hear a click.
(5) If necessary install the recessed panel (19). NOTE: Make sure that the burrtape touches correctly.
B. Installation of the Door Frame Lining 232LX
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Put the door frame lining (21) in position on the door frame structure and engage the attach brackets to the yo-yo rolls.
(3) Install the handle section LWR (41), the washers (39) and the screws (40).
(4) Install the cover (43) to the handle section LWR (41).
Subtask 25-23-47-420-067-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Put the door frame lining (21) in position on the door frame structure and engage the attach brackets to the yo-yo rolls.
(3) Install the handle section LWR (41), the washers (39) and the screws (40).
(4) Install the cover (43) to the handle section LWR (41).
NOTE: Make sure that the lugs (42) of the cover (43) engage correctly and you hear a click.
C. Installation of the Door Frame Lining(s) 232KX and/or 232GX
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Put the door frame lining(s) (35) and/or (38) in position on the door frame structure, engage the attach brackets to the yo-yo rolls.
(3) Install the door frame lining(s) (35) and/or (38), the washers (37) and the screws (36).
Subtask 25-23-47-420-068-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Put the door frame lining(s) (35) and/or (38) in position on the door frame structure, engage the attach brackets to the yo-yo rolls.
(3) Install the door frame lining(s) (35) and/or (38), the washers (37) and the screws (36).
D. Installation of the Door Frame Lining
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Remove the PLUG-BLANKING from each disconnected line end.
(3) Install the outlet (34), the washers (33) and the screws (32) to the door frame lining (28).
(4) Install the door frame lining (28), the washers (31) and the screws (30) to the door frame structure.
(5) Install the hose and the clamp (29).
Subtask 25-23-47-420-069-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Remove the PLUG-BLANKING from each disconnected line end.
(3) Install the outlet (34), the washers (33) and the screws (32) to the door frame lining (28).
(4) Install the door frame lining (28), the washers (31) and the screws (30) to the door frame structure.
(5) Install the hose and the clamp (29).
E. Installation of the Door Frame Lining 232EX and 232DX
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the door frame lining (15), the washers (17) and the screws (16).
(3) Install the door frame lining (18), the washers (37) and the screws (36).
Subtask 25-23-47-420-070-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the door frame lining (15), the washers (17) and the screws (16).
(3) Install the door frame lining (18), the washers (37) and the screws (36).
F. Installation of the Door Frame Lining 232NX and 232YX, if removed
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the door frame lining (22) and (27), the washers (24), (26) and the screws (23), (25).
(3) Close the access panel (9).
Subtask 25-23-47-420-071-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the door frame lining (22) and (27), the washers (24), (26) and the screws (23), (25).
(3) Close the access panel (9).
G. Installation of the Door Frame Lining
(1) Make sure that the work area is clean and clear of tools and other items.
(2) If you removed the inflation reservoir, install it (Ref. AMM TASK 25-62-49-400-001).
(3) Make sure that the access panel (9) is open.
(4) Hold the door frame lining (8) in position on the door frame structure.
(5) Install the shims (14), the washers (11) and (13) and the screws (10) and (12).
(6) Close the access panel (9).
Subtask 25-23-47-420-072-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) If you removed the inflation reservoir, install it (Ref. AMM TASK 25-62-49-400-001).
(3) Make sure that the access panel (9) is open.
(4) Hold the door frame lining (8) in position on the door frame structure.
(5) Install the shims (14), the washers (11) and (13) and the screws (10) and (12).
(6) Close the access panel (9).
H. Installation of Escape-Slide Lever Cover, if removed
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the escape-slide lever cover (1), the washers (4) and the screws (2), (3).
Subtask 25-23-47-420-078-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the escape-slide lever cover (1), the washers (4) and the screws (2), (3).
I. Installation of the Hook
(1) Install the hook (5), the washers (7) and the screws (6).
Subtask 25-23-47-210-069-A ** ON A/C NOT FOR ALL (1) Install the hook (5), the washers (7) and the screws (6).
J. Visual Inspection
(1) Make sure that all placards of the retained/new components are in the correct condition and in good condition.
(2) If necessary install new placards, refer to (Ref. AMM TASK 11-00-00-400-002) (Ref. AMM D/O 11-32-25-00)
5. Close-up(1) Make sure that all placards of the retained/new components are in the correct condition and in good condition.
(2) If necessary install new placards, refer to (Ref. AMM TASK 11-00-00-400-002) (Ref. AMM D/O 11-32-25-00)
Subtask 25-23-47-865-064-A ** ON A/C NOT FOR ALL
A. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 25-23-47-740-052-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 49VU | COM/CIDS/DEU B/ESS | 153RH | G03 |
| 49VU | LIGHTING/EMER LT/CABIN | 2WL | H06 |
| 49VU | LIGHTING/EMER LT/CABIN | 1WL | H05 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | COM NAV/CIDS/DEU B/NORM | 162RH | M09 |
| ** ON A/C NOT FOR ALL | |||
| 122VU | LIGHTING/CABIN/EMER/LT | 3WL | V07 |
B. Interface and Power-up Test of the Cabin Intercommunication Data System (CIDS)
(1) Do the interface and power-up test of the CIDS (Ref. AMM TASK 23-73-00-740-005).
Subtask 25-23-47-740-053-A ** ON A/C NOT FOR ALL (1) Do the interface and power-up test of the CIDS (Ref. AMM TASK 23-73-00-740-005).
C. BITE Test of the Smoke Detection Function (SDF)
(1) Do the BITE test of the SDF (Ref. AMM TASK 26-10-00-740-801).
Subtask 25-23-47-410-070-A ** ON A/C NOT FOR ALL (1) Do the BITE test of the SDF (Ref. AMM TASK 26-10-00-740-801).
D. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the related emergency exit door (Ref. AMM TASK 52-22-00-410-001).
(3) Install the cabin emergency lights 34WL (Ref. AMM TASK 33-51-11-400-001).
(4) Install the cabin-wall mounted emergency-exit-marker 90WL4 (Ref. AMM TASK 33-51-13-400-001).
(5) Install the emergency exit sign 46WL (Ref. AMM TASK 33-51-16-400-001).
(6) Remove the access platform(s).
Subtask 25-23-47-862-054-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the related emergency exit door (Ref. AMM TASK 52-22-00-410-001).
(3) Install the cabin emergency lights 34WL (Ref. AMM TASK 33-51-11-400-001).
(4) Install the cabin-wall mounted emergency-exit-marker 90WL4 (Ref. AMM TASK 33-51-13-400-001).
(5) Install the emergency exit sign 46WL (Ref. AMM TASK 33-51-16-400-001).
(6) Remove the access platform(s).
Door Frame Linings - Emergency Exit, zone 232