1. Reason for the Job
Refer to the MPD TASK: 200221-01
CLEANING OF EWIS INSTALLED IN THE FORWARD CABIN UTILITY AREA (ONLY IF CONTAMINATED) (EWIS)
NOTE: This is an EWIS (Electrical Wiring Interconnection System) procedure. EWIS is defined in ESPM 20-33-11.
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
1
ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
221
FWD CAB UTILITY AREA
222
FWD CAB UTILITY AREA
 C. Referenced Information
REFERENCE
DESIGNATION
TASK 24-41-00-862-002-A
De-energize the Aircraft Electrical Circuits Supplied from the External Power
TASK 24-41-00-862-002-A-01
De-energize the Aircraft Electrical Circuits Supplied from the APU
TASK 24-41-00-862-002-A-02
De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2)
TASK 25-23-45-000-002-A
Removal of the Door Frame Linings from the Right Forward Passenger/Crew Door
TASK 25-23-45-000-005-A
Removal of the Door Frame Linings from the Left Forward Passenger/Crew Door
TASK 25-23-45-400-006-A
Installation of the Door Frame Linings on the Left Forward Passenger/Crew Door
TASK 25-23-45-400-007-A
Installation of the Door Frame Linings on the Right Forward Passenger/Crew Door
TASK 52-10-00-010-001-A
Opening of the Passenger/Crew Door
TASK 52-10-00-410-001-A
Closing of the Passenger/Crew Door
TASK 53-00-00-000-801-A
Removal of the Floor Panels in the Cabin from FR12 to FR70
TASK 53-00-00-000-801-A-01
Removal of the Floor Panels in the Cabin from FR12 to FR70 (Alternative Removal Procedure - Dry Sealing Concept)
TASK 53-00-00-000-801-A-02
Removal of the Cabin Floor Panels from FR12 to FR70 (Alternative Removal Procedure with the Skyflex Option)
TASK 53-00-00-400-801-A
Installation of the Floor Panels in the Cabin from FR12 to FR70
TASK 53-00-00-400-801-A-01
Installation of the Floor Panels in the Cabin from FR12 to FR70 (Alternative Installation Procedure - Dry Sealing Concept)
TASK 53-00-00-400-801-A-02
Installation of the Cabin Floor Panels from FR12 to FR70 (Alternative Installation Procedure with the Skyflex Option)
ESPM 2055000
TASK 06-41-53-00
FUSELAGE-DESCRIPTION AND OPERATION
3. Job Set-up
Subtask 24-92-00-010-100-A
A. Get Access
   (1) Put an ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE in position at the zone 831 (841).
   (2) Open the forward passenger/crew door 831 (841) (Ref. AMM TASK 52-10-00-010-001).
Subtask 24-92-00-862-088-A
B. De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002).
4. Procedure
Subtask 24-92-00-410-171-A
A. Preparation for Cleaning
   (1) Remove the door frame linings at the left and right FWD passenger/crew door (Ref. AMM TASK 25-23-45-000-005), (Ref. AMM TASK 25-23-45-000-002) and (Ref. AMM D/O 06-41-53-00).
   (2) Remove the floor panels in the cabin from FR12 to FR20 (Ref. AMM TASK 53-00-00-000-801).
Subtask 24-92-00-160-056-A
B. Cleaning of All Wiring Installed in the Forward Cabin Utility-Area (Only Contaminated Wiring)
   (1) Clean the wiring if there is dust or lint contamination ESPM 2055000.
     (a) On the AC/DC power-distribution route: 1P.
     (b) On other routes: 2M and 1R.
5. Close-up
Subtask 24-92-00-410-098-A
A. Close Access
   (1) Install the floor panels in the cabin from FR12 to FR20 (Ref. AMM TASK 53-00-00-400-801).
   (2) Install the door frame linings at the left and right FWD passenger/crew door (Ref. AMM TASK 25-23-45-400-006) and (Ref. AMM TASK 25-23-45-400-007).
   (3) Close the forward passenger/crew door 831 (841) (Ref. AMM TASK 52-10-00-410-001).
   (4) Remove the access platform(s).