Functional Check of Reservoir Low Level Warning
TASK 29-31-00-710-001-A
Functional Check of Reservoir Low Level Warning
Refer to the MPD TASK: 293100-01
FUNCTIONAL CHECK OF RESERVOIR LOW LEVEL WARNING
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Consumable Materials
C. Work Zones and Access Panels
D. Referenced Information
3. Job Set-up
Subtask 29-31-00-010-052-A
Subtask 29-31-00-710-050-A
Subtask 29-31-00-860-050-B
[Rev.10 from 2021]
2026.04.01 00:27:30 UTC
Functional Check of Reservoir Low Level Warning
WARNING:
DO NOT GET HYDRAULIC FLUID ON YOUR SKIN, IN YOUR EYES OR IN YOUR MOUTH. HYDRAULIC FLUID IS POISONOUS AND CAN GO THROUGH YOUR SKIN AND INTO YOUR BODY. FLUSH HYDRAULIC FLUID FROM YOUR EYES, MOUTH OR SKIN WITH WATER. GET MEDICAL AID IF YOU GET HYDRAULIC FLUID IN YOUR EYES OR MOUTH.
WARNING:
OBEY THE HYDRAULIC SAFETY PROCEDURES.
WARNING:
BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
1. Reason for the JobRefer to the MPD TASK: 293100-01
FUNCTIONAL CHECK OF RESERVOIR LOW LEVEL WARNING
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | CONTAINER - HYDRAULIC FLUID RESISTANT |
| No specific | 1 | CONTAINER 1 L (1/4 USGAL) |
| No specific | 1 | HOSE - HYDRAULIC, LOW PESSURE |
| No specific | AR | WARNING NOTICE(S) |
| 97A29102035000 | 1 | CONNECTOR-PRESSURIZING,HYDRAULIC TANK |
| 98D29003501000 | 1 | FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR |
| 98D29003501003 | 1 | FILL UNIT - AIR |
| ALT29000001 | 1 | HYD GRND PWR UNIT3000 |
| REFERENCE | DESIGNATION |
|---|---|
| (Material No.02ABA1) | Phosphate Ester Hydraulic Fluid-General Power - - |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 190 | BELLY FAIR, AIR CONDITIONING & HYD COMPT |
| 195 | HYDRAULIC COMPT AND FAIRINGS |
| 197 | REAR FAIRING |
| 198 | REAR FAIRING |
| 195BB, 196BB, 197CB, 197EB, 197FB, 198CB |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-861-002-A-02 | Energize the Aircraft Electrical Circuits from Engine 1(2) |
| TASK 24-41-00-862-002-A | De-energize the Aircraft Electrical Circuits Supplied from the External Power |
| TASK 24-41-00-862-002-A-01 | De-energize the Aircraft Electrical Circuits Supplied from the APU |
| TASK 24-41-00-862-002-A-02 | De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2) |
| TASK 29-00-00-864-001-A | Put the Related Hydraulic System in the Depressurized Configuration before Maintenance Action |
| TASK 29-00-00-910-002-A | Safety Procedures of the Hydraulic System |
| TASK 31-60-00-860-001-A | EIS Start Procedure |
| TASK 31-60-00-860-002-A | EIS Stop Procedure |
| TASK 32-12-00-010-001-A | Open the Main Gear Doors for Access |
| TASK 32-12-00-410-001-A | Close the Main Gear Doors after Access |
Subtask 29-31-00-010-052-A
A. Get Access
(1) Open the access doors 196BB 195BB 197CB 197EB 197FB 198CB.
(2) Open the right main door of the main landing gear (Ref. AMM TASK 32-12-00-010-001).
Subtask 29-31-00-860-052-A (1) Open the access doors 196BB 195BB 197CB 197EB 197FB 198CB.
(2) Open the right main door of the main landing gear (Ref. AMM TASK 32-12-00-010-001).
B. Aircraft Maintenance Configuration
(2) Make sure that the hydraulic systems are depressurized and put them in the maintenance configuration
(Ref. AMM TASK 29-00-00-864-001).
(3) Put WARNING NOTICE(S) to tell persons not to pressurize the hydraulic systems:
(5) Do the EIS start procedure (upper ECAM DU and lower ECAM DU only)
(Ref. AMM TASK 31-60-00-860-001).
(6) On the ECAM control panel on the center pedestal, push the HYD pushbutton switch. Make sure that the HYD page is shown on the lower (system) display on the ECAM.
Subtask 29-31-00-865-053-A WARNING:
OBEY THE HYDRAULIC SAFETY PROCEDURES.
(1) Obey the hydraulic safety procedures (Ref. AMM TASK 29-00-00-910-002). (2) Make sure that the hydraulic systems are depressurized and put them in the maintenance configuration
(Ref. AMM TASK 29-00-00-864-001).
(3) Put WARNING NOTICE(S) to tell persons not to pressurize the hydraulic systems:
- In the flight compartment on the hydraulic section 40VU of the overhead panel.
- On the ground service panels of the Green, Yellow and Blue hydraulic systems.
(5) Do the EIS start procedure (upper ECAM DU and lower ECAM DU only)
(Ref. AMM TASK 31-60-00-860-001).
(6) On the ECAM control panel on the center pedestal, push the HYD pushbutton switch. Make sure that the HYD page is shown on the lower (system) display on the ECAM.
C. Make sure that this(these) circuit breaker(s) is(are) closed:
Subtask 29-31-00-860-051-B ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 49VU | HYD/HYD PWR/B WARN/& CTL | 2702GJ | C12 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/G HYD/PUMP ENG1/MONG | 1702GK | R34 |
| ** ON A/C ALL | |||
| 121VU | HYDRAULIC/LOW/LVL/IND | 1832GQ | N32 |
| 121VU | HYDRAULIC/HYD/QTY/IND | 1831GQ | P35 |
| 121VU | HYDRAULIC/Y HYD/PUMP ENG2/MONG | 3700GD | Q37 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/G HYD/PUMP ENG1/MONG | 1702GK | R33 |
D. Preparation for the Test
(1) Remove the blanking cap from the ground connector for the pressurization of reservoirs on the reservoir pressurization unit 1360GM.
(2) Connect the 98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR or 98D29003501003 FILL UNIT - AIR to the ground connector on the reservoir pressurization unit 1360GM.
1 On the ground service panel of the Green hydraulic system, remove the blanking cap from the reservoir fill connection 1007GM.
2 Connect the hose of the hydraulic ground-service cart to the reservoir fill connection.
(b) If no hydraulic ground-service cart is available, connect the hand pump 1009GM as follows:
1 Remove the blanking cap from the reservoir fill valve 1698GM on the hand pump 1009GM.
2 Get the flexible hose 1699GM from its stowage in the ground service panel of the Green hydraulic system.
3 Connect the flexible hose to the reservoir fill valve.
4 Put the other end of the flexible hose in a container of clean hydraulic fluid.
5 Get the hand pump lever 3270GM from its position in the ground service panel of the Yellow hydraulic system.
6 Connect the hand pump lever to the hand pump 1009GM.
7 Extend the hand pump lever.
(4) Connect a HOSE - HYDRAULIC, LOW PESSURE with a 9/16-18 UNJF female adapter to the drain valve of the reservoir of the Green hydraulic system.
(5) Put the free end of the hose into the CONTAINER - HYDRAULIC FLUID RESISTANT.
(6) Look at the quantity indicator of the three reservoirs and write down the quantity of hydraulic fluid in each reservoir.
(7) Set the ground connector on the reservoir pressurization unit 1360GM to OPEN.
(8) Fill the reservoirs with air to a pressure of 50 psig (refer to the gages on the reservoirs to find the air pressure). Keep the supply of air constant until the pressure in the reservoirs is always more than 35 psig (2.5 bar). If the air supply is not constant, the pressure decreases when you drain the fluid from the reservoirs.
Subtask 29-31-00-860-051-C ** ON A/C NOT FOR ALL (1) Remove the blanking cap from the ground connector for the pressurization of reservoirs on the reservoir pressurization unit 1360GM.
(2) Connect the 98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR or 98D29003501003 FILL UNIT - AIR to the ground connector on the reservoir pressurization unit 1360GM.
NOTE: If the pressurizing tool is not available, you can use an alternative supply of air. The supply must have a pressure of 5 bar (72.5189 psi) and it must have a filter. The filter must have a rating of 5 microns or better.
As alternative to the air source, you can use the nitrogen source with 97A29102035000 CONNECTOR-PRESSURIZING,HYDRAULIC TANK.
(3) A supply approximately 40 l (10.5668 USgal) of Phosphate Ester Hydraulic Fluid-General Power - - (Material No.02ABA1) is necessary. You can use: As alternative to the air source, you can use the nitrogen source with 97A29102035000 CONNECTOR-PRESSURIZING,HYDRAULIC TANK.
- An approved ALT29000001 HYD GRND PWR UNIT3000
- The hand pump 1009GM of the reservoir filling system which is part of the aircraft equipment.
1 On the ground service panel of the Green hydraulic system, remove the blanking cap from the reservoir fill connection 1007GM.
2 Connect the hose of the hydraulic ground-service cart to the reservoir fill connection.
(b) If no hydraulic ground-service cart is available, connect the hand pump 1009GM as follows:
1 Remove the blanking cap from the reservoir fill valve 1698GM on the hand pump 1009GM.
2 Get the flexible hose 1699GM from its stowage in the ground service panel of the Green hydraulic system.
3 Connect the flexible hose to the reservoir fill valve.
4 Put the other end of the flexible hose in a container of clean hydraulic fluid.
5 Get the hand pump lever 3270GM from its position in the ground service panel of the Yellow hydraulic system.
6 Connect the hand pump lever to the hand pump 1009GM.
7 Extend the hand pump lever.
(4) Connect a HOSE - HYDRAULIC, LOW PESSURE with a 9/16-18 UNJF female adapter to the drain valve of the reservoir of the Green hydraulic system.
(5) Put the free end of the hose into the CONTAINER - HYDRAULIC FLUID RESISTANT.
(6) Look at the quantity indicator of the three reservoirs and write down the quantity of hydraulic fluid in each reservoir.
(7) Set the ground connector on the reservoir pressurization unit 1360GM to OPEN.
(8) Fill the reservoirs with air to a pressure of 50 psig (refer to the gages on the reservoirs to find the air pressure). Keep the supply of air constant until the pressure in the reservoirs is always more than 35 psig (2.5 bar). If the air supply is not constant, the pressure decreases when you drain the fluid from the reservoirs.
D. Preparation for the Test
(1) Remove the blanking cap from the ground connector for the pressurization of reservoirs on the reservoir pressurization unit 1360GM.
(2) Connect the 98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR or 98D29003501003 FILL UNIT - AIR to the ground connector on the reservoir pressurization unit 1360GM.
1 On the ground service panel of the Green hydraulic system, remove the blanking cap from the reservoir fill connection 1007GM.
2 Connect the hose of the hydraulic ground-service cart to the reservoir fill connection.
(b) If no hydraulic ground-service cart is available, connect the hand pump 1009GM as follows:
1 Remove the blanking cap from the reservoir fill valve 1698GM on the hand pump 1009GM.
2 Get the flexible hose 1699GM from its stowage in the ground service panel of the Green hydraulic system.
3 Connect the flexible hose to the reservoir fill valve.
4 Put the other end of the flexible hose in a container of clean hydraulic fluid.
5 Get the hand pump lever 3270GM from its position in the ground service panel of the Yellow hydraulic system.
6 Connect the hand pump lever to the hand pump 1009GM.
7 Extend the hand pump lever.
(4) Connect a HOSE - HYDRAULIC, LOW PESSURE with a 9/16-18 UNJF female adapter to the drain valve of the reservoir of the Green hydraulic system.
(5) Put the free end of the hose into the CONTAINER - HYDRAULIC FLUID RESISTANT.
(6) Look at the quantity indicator of the three reservoirs and write down the quantity of hydraulic fluid in each reservoir.
(7) Set the ground connector on the reservoir pressurization unit 1360GM to OPEN.
(8) Fill the reservoirs with air to a pressure of 50 psig (refer to the gages on the reservoirs to find the air pressure). Keep the supply of air constant until the pressure in the reservoirs is always more than 35 psig (2.5 bar). If the air supply is not constant, the pressure decreases when you drain the fluid from the reservoirs.
4. Procedure(1) Remove the blanking cap from the ground connector for the pressurization of reservoirs on the reservoir pressurization unit 1360GM.
(2) Connect the 98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR or 98D29003501003 FILL UNIT - AIR to the ground connector on the reservoir pressurization unit 1360GM.
NOTE: If the pressurizing tool is not available, you can use an alternative supply of air. The supply must have a pressure of 5 bar (72.5189 psi) and it must have a filter. The filter must have a rating of 5 microns or better.
As alternative to the air source, you can use the nitrogen source with 97A29102035000 CONNECTOR-PRESSURIZING,HYDRAULIC TANK.
(3) A supply approximately 40 l (10.5668 USgal) of Phosphate Ester Hydraulic Fluid-General Power - - (Material No.02ABA1) is necessary. You can use: As alternative to the air source, you can use the nitrogen source with 97A29102035000 CONNECTOR-PRESSURIZING,HYDRAULIC TANK.
- An approved ALT29000001 HYD GRND PWR UNIT3000
- The hand pump 1009GM of the reservoir filling system which is part of the aircraft equipment.
NOTE: It is not permitted to use high-density fluid Skydrol 500B-4.
(a) To connect the hydraulic ground-service cart to the aircraft: 1 On the ground service panel of the Green hydraulic system, remove the blanking cap from the reservoir fill connection 1007GM.
2 Connect the hose of the hydraulic ground-service cart to the reservoir fill connection.
(b) If no hydraulic ground-service cart is available, connect the hand pump 1009GM as follows:
1 Remove the blanking cap from the reservoir fill valve 1698GM on the hand pump 1009GM.
2 Get the flexible hose 1699GM from its stowage in the ground service panel of the Green hydraulic system.
3 Connect the flexible hose to the reservoir fill valve.
4 Put the other end of the flexible hose in a container of clean hydraulic fluid.
5 Get the hand pump lever 3270GM from its position in the ground service panel of the Yellow hydraulic system.
6 Connect the hand pump lever to the hand pump 1009GM.
7 Extend the hand pump lever.
(4) Connect a HOSE - HYDRAULIC, LOW PESSURE with a 9/16-18 UNJF female adapter to the drain valve of the reservoir of the Green hydraulic system.
(5) Put the free end of the hose into the CONTAINER - HYDRAULIC FLUID RESISTANT.
(6) Look at the quantity indicator of the three reservoirs and write down the quantity of hydraulic fluid in each reservoir.
(7) Set the ground connector on the reservoir pressurization unit 1360GM to OPEN.
(8) Fill the reservoirs with air to a pressure of 50 psig (refer to the gages on the reservoirs to find the air pressure). Keep the supply of air constant until the pressure in the reservoirs is always more than 35 psig (2.5 bar). If the air supply is not constant, the pressure decreases when you drain the fluid from the reservoirs.
Subtask 29-31-00-710-050-A
A. Do this test:
5. Close-up| ACTION | RESULT |
|---|---|
| 1.On the reservoir of the Green hydraulic system: | |
|
|
| |
| 2.When the fluid quantity indicator 1834GQ on the Green ground service panel or the quantity indicator of the reservoir shows the fluid quantity between 3.4 l (0.90 USgal) and 2.6 l (0.69 USgal). | On the ECAM lower Display Unit (DU):
On the glareshield panels 130VU and 131VU:
|
| 3.On the reservoir of the Green hydraulic system: | |
|
|
| 4.On the ground service panel of the Green hydraulic system: | The reservoir of the Green hydraulic system is connected to the reservoir filling system. On the reservoir indicator 1834GQ: |
|
|
| 5.Use the hydraulic ground-service cart or the hand pump to put fluid into the reservoir of the Green hydraulic system until all the warnings go off. | |
| 6.Open the circuit breaker 1832GQ | The usual low-level warning system is inoperative. |
| 7.On the reservoir of the Green hydraulic system: | |
|
|
| |
8.When the fluid quantity indicator 1834GQ on the Green ground service panel or the quantity indicator of the reservoir shows the fluid quantity between 3.5 l (0.92 USgal) and 3.3 l (0.87 USgal):
| |
9.On the reservoir of the Green hydraulic system:
|
|
10.On the reservoir of the Green hydraulic system:
| |
11.On the reservoir of the Green hydraulic system:
| |
| 12.When the CONTAINER 1 L (1/4 USGAL) is fully filled. | On the ECAM lower DU:
On the glareshield panels 130VU and 131VU:
|
| 13.On the reservoir of the Green hydraulic system: | |
|
|
| 14.Use the hydraulic ground-service cart or the hand pump to put fluid into the reservoir of the Green hydraulic system until the warnings on the ECAM displays go off. | |
| 15.On the ground service panel of the Green hydraulic system: | On the reservoir indicator 1834GQ: |
|
|
| 16.Close the circuit breaker 1832GQ. | The usual low-level warning system is operative. |
| 17.Remove the hose and the adapter from the drain valve of the reservoir of the Green hydraulic system. 18.Remove the CONTAINER 1 L (1/4 USGAL) and CONTAINER - HYDRAULIC FLUID RESISTANT. 19.Connect the hose and the adapter to the drain valve of the reservoir of the Yellow hydraulic system. 20.Put the free end of the hose into the CONTAINER - HYDRAULIC FLUID RESISTANT. | |
| 21.On the reservoir of the Yellow hydraulic system: | |
|
|
| |
| 22.When the the fluid quantity indicator 1834GQ on the Green ground service panel or the quantity indicator of the reservoir shows the fluid quantity between 3.4 l (0.90 USgal) and 2.6 l (0.69 USgal). | On the ECAM lower DU:
On the glareshield panels 130VU and 131VU:
|
| 23.On the reservoir of the Yellow hydraulic system: | |
|
|
| 24.On the ground service panel of the Green hydraulic system: | The reservoir of the Yellow hydraulic system is connected to the reservoir filling system. On the reservoir indicator 1834GQ: |
|
|
| 25.Use the hydraulic ground-service cart or the hand pump to put fluid into the reservoir of the Yellow hydraulic system until all the warnings go off. | |
| 26.Open the circuit breaker 1832GQ. | The usual low-level warning system is inoperative. |
| 27.On the reservoir of the Yellow hydraulic system: | |
|
|
| |
28.When the the fluid quantity indicator 1834GQ on the Green ground service panel, or the quantity indicator of the reservoir shows the fluid quantity between 3.5 l (0.92 USgal) and 3.3 l (0.87 USgal):
| |
29.On the reservoir of the Yellow hydraulic system:
|
|
30.On the reservoir of the Yellow hydraulic system:
| |
31.On the reservoir of the Yellow hydraulic system:
| |
| 32.When the CONTAINER 1 L (1/4 USGAL) is fully filled. | On the ECAM lower DU:
On the glareshield panels 130VU and 131VU:
|
| 33.On the reservoir of the Yellow hydraulic system: | |
|
|
| 34.Use the hydraulic ground-service cart or the hand pump to put fluid into the reservoir of the Yellow hydraulic system until the warnings on the ECAM displays go off. | |
| 35.On the ground service panel of the Green hydraulic system: | On the reservoir indicator 1834GQ: |
|
|
| 36.Close the circuit breaker 1832GQ. | The usual low-level warning system is operative. |
| 37.Remove the hose and the adapter from the drain valve of the reservoir of the Yellow hydraulic system. 38.Remove the CONTAINER - HYDRAULIC FLUID RESISTANT and CONTAINER 1 L (1/4 USGAL). | |
| 39.Connect the hose and the adapter to the drain valve of the reservoir of the Blue hydraulic system. NOTE: The drain valve of the reservoir of the Blue hydraulic system is on the ground service panel of the Blue hydraulic system. | |
| 40.Put the free end of the hose into the CONTAINER - HYDRAULIC FLUID RESISTANT. | |
| 41.On the ground service panel of the Blue hydraulic system: | |
|
|
| |
| 42.When the the fluid quantity indicator 1834GQ on the Green ground service panel or the quantity indicator of the reservoir shows the fluid quantity between 2.0 l (0.53 USgal) and 2.3 l (0.61 USgal). | On the ECAM lower DU:
On the glareshield panels 130VU and 131VU:
|
| 43.On the ground service panel of the Blue hydraulic system: | |
|
|
| 44.On the ground service panel of the Green hydraulic system: | The reservoir of the Blue hydraulic system is connected to the reservoir filling system. On the reservoir indicator 1834GQ: |
|
|
| 45.Use the hydraulic ground-service cart or the hand pump to put fluid into the reservoir of the Blue hydraulic system until all the warnings go off. | |
| 46.Open the circuit breaker 1832GQ. | The usual low-level warning system is inoperative. |
| 47.On the ground service panel of the Blue hydraulic system: | |
|
|
| |
48.When the fluid quantity indicator 1834GQ on the Green ground service panel, or the quantity indicator of the reservoir shows the fluid quantity between 2.9 l (0.77 USgal) and 2.7 l (0.71 USgal):
| |
49.On the ground service panel of the Blue hydraulic system:
|
|
50.On the ground service panel of the Blue hydraulic system:
| |
51.On the ground service panel of the Blue hydraulic system:
| |
| 52.When the CONTAINER 1 L (1/4 USGAL) is fully filled. | On the ECAM lower DU:
In the glareshield panels 130VU and 131VU:
|
| 53.On the ground service panel of the Blue hydraulic system: | |
|
|
| 54.Use the hydraulic ground-service cart or the hand pump to put fluid into the reservoir of the Blue hydraulic system until the warnings on the ECAM displays go off. | |
| 55.On the ground service panel of the Green hydraulic system: | On the reservoir indicator: |
|
|
| 56.Close the circuit breaker 1832GQ. | The usual low-level warning system is operative. |
Subtask 29-31-00-860-050-B
A. Put the aircraft back to the serviceable condition
(1) Disconnect the hose and the adapter from the drain valve of the reservoir of the Blue hydraulic system.
(2) Remove the container.
(3) Stop the supply of air but do not disconnect the supply from the ground connector of the reservoir pressurization unit 1360GM.
(4) On the ground service panel of the Green hydraulic system, set the reservoir-filling manual selector-valve to BLUE.
(5) Use the hydraulic ground-service cart or the hand pump and fill the reservoir of the Blue hydraulic system to the same level as before the test.
(6) On the ground service panel of the Green hydraulic system, set the reservoir selector valve to YELLOW.
(7) Fill the reservoir of the Yellow hydraulic system to the same level as before the test.
(8) On the ground service panel of the Green hydraulic system, set the reservoir-filling manual selector-valve to GREEN.
(9) Fill the reservoir of the Green hydraulic system to the same level as before the test.
(10) On the ground service panel of the Green hydraulic system, set the reservoir-filling manual selector-valve to NEUTRAL.
(11) Make sure that all three reservoirs are pressurized to 50 psig. If necessary, use the air supply to fill them to the correct pressure.
(12) Set the ground connector of the reservoir pressurization unit 1360GM to the CLOSE position and disconnect the 98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR or 98D29003501003 FILL UNIT - AIR.
(13) Disconnect the hydraulic fluid supply:
(a) If a hydraulic ground-service cart was used:
1 Disconnect the hose from the fill connection 1007GM.
2 Install the blanking cap on the fill connection.
(b) If the hand pump 1009GM was used:
1 Remove the hand pump lever 3270GM from the hand pump.
2 Retract the hand pump lever and put it in its position in the ground service panel of the Yellow hydraulic system.
3 Disconnect the flexible hose 1699GM from the reservoir fill valve 1698GM and put it back into its stowage.
4 Install the blanking cap on the reservoir fill valve.
(14) Do the EIS stop procedure
(Ref. AMM TASK 31-60-00-860-002).
(15) De-energize the aircraft electrical circuits (Ref. AMM TASK 24-41-00-862-002).
(16) Remove the WARNING NOTICE(S).
Subtask 29-31-00-410-053-A (1) Disconnect the hose and the adapter from the drain valve of the reservoir of the Blue hydraulic system.
(2) Remove the container.
(3) Stop the supply of air but do not disconnect the supply from the ground connector of the reservoir pressurization unit 1360GM.
(4) On the ground service panel of the Green hydraulic system, set the reservoir-filling manual selector-valve to BLUE.
(5) Use the hydraulic ground-service cart or the hand pump and fill the reservoir of the Blue hydraulic system to the same level as before the test.
(6) On the ground service panel of the Green hydraulic system, set the reservoir selector valve to YELLOW.
(7) Fill the reservoir of the Yellow hydraulic system to the same level as before the test.
(8) On the ground service panel of the Green hydraulic system, set the reservoir-filling manual selector-valve to GREEN.
(9) Fill the reservoir of the Green hydraulic system to the same level as before the test.
(10) On the ground service panel of the Green hydraulic system, set the reservoir-filling manual selector-valve to NEUTRAL.
(11) Make sure that all three reservoirs are pressurized to 50 psig. If necessary, use the air supply to fill them to the correct pressure.
(12) Set the ground connector of the reservoir pressurization unit 1360GM to the CLOSE position and disconnect the 98D29003501000 FILL UNIT-AIR PRESSURIZING TOOL, HYDRAULIC RESERVOIR or 98D29003501003 FILL UNIT - AIR.
(13) Disconnect the hydraulic fluid supply:
(a) If a hydraulic ground-service cart was used:
1 Disconnect the hose from the fill connection 1007GM.
2 Install the blanking cap on the fill connection.
(b) If the hand pump 1009GM was used:
1 Remove the hand pump lever 3270GM from the hand pump.
2 Retract the hand pump lever and put it in its position in the ground service panel of the Yellow hydraulic system.
3 Disconnect the flexible hose 1699GM from the reservoir fill valve 1698GM and put it back into its stowage.
4 Install the blanking cap on the reservoir fill valve.
(14) Do the EIS stop procedure
(Ref. AMM TASK 31-60-00-860-002).
(15) De-energize the aircraft electrical circuits (Ref. AMM TASK 24-41-00-862-002).
(16) Remove the WARNING NOTICE(S).
B. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the right main door of the main landing gear (Ref. AMM TASK 32-12-00-410-001).
(3) Remove the ground support and maintenance equipment, the special and standard tools and all other items.
(4) Close the access doors 196BB 195BB 197CB 197EB 197FB 198CB.
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the right main door of the main landing gear (Ref. AMM TASK 32-12-00-410-001).
(3) Remove the ground support and maintenance equipment, the special and standard tools and all other items.
(4) Close the access doors 196BB 195BB 197CB 197EB 197FB 198CB.