Installation of the Generator Substitution Kit for Trouble Shooting (131-9(A))
TASK 49-11-00-400-006-A
Installation of the Generator Substitution Kit for Trouble Shooting (131-9(A))
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Consumable Materials
C. Work Zones and Access Panels
D. Expendable Parts
E. Referenced Information
3. Job Set-up
Subtask 49-11-00-860-069-A ** ON A/C NOT FOR ALL
Subtask 49-11-00-420-060-A ** ON A/C NOT FOR ALL
Subtask 49-11-00-710-054-A ** ON A/C NOT FOR ALL
Subtask 49-11-00-410-063-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.01 01:26:43 UTC
Installation of the Generator Substitution Kit for Trouble Shooting (131-9(A))
WARNING:
DO NOT TOUCH THE APU UNTIL IT IS SUFFICIENTLY COOL TO PREVENT BURNS WHEN YOU DO THE MAINTENANCE TASK(S).
WARNING:
BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Consumable Materials
| REFERENCE | DESIGNATION |
|---|---|
| (Material No.03ABA1) | Synthetic base Lubricating Oil-Turbine Engine - - |
| (Material No.03ABB1) | Synthetic base Lubricating Oil-Turbine Engine Low Temp. - |
| (Material No.14QFB1) | Wire-Locking Dia: 0.8 mm CRES Nickel Alloy - |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 315AL, 316AR |
| FIG.ITEM | DESIGNATION | IPC-CSN |
|---|---|---|
| 2 | SEAL | AIPC 49-11-04-05-150 |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-42-00-861-001-A | Energize the Ground Service Network from the External Power |
| TASK 24-42-00-862-001-A | De-energize the Ground Service Network Supplied from the External Power |
| TASK 29-00-00-864-001-A | Put the Related Hydraulic System in the Depressurized Configuration before Maintenance Action |
| TASK 49-00-00-860-008-A | APU Start by External Power |
| TASK 49-00-00-860-008-A-01 | APU Start by Batteries |
| TASK 49-00-00-860-009-A | APU Shutdown by External Power (131-9(A)) |
| TASK 49-00-00-860-009-A-01 | APU Shutdown by Batteries (131-9(A)) |
| TASK 49-90-00-600-007-A | Check Oil Level and Replenish (131-9(A)) |
| TASK 52-41-00-010-001-A | Open the APU Doors for Access |
| TASK 52-41-00-410-001-A | Close the APU Doors after Access |
Subtask 49-11-00-860-069-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
(1) Energize the ground service network
(Ref. AMM TASK 24-42-00-861-001).
(2) On the panel 25VU make sure that the APU MASTER SW p/bsw is OFF.
(3) Make sure that the hydraulic systems are depressurized
(Ref. AMM TASK 29-00-00-864-001).
Subtask 49-11-00-865-067-A ** ON A/C NOT FOR ALL (1) Energize the ground service network
(Ref. AMM TASK 24-42-00-861-001).
(2) On the panel 25VU make sure that the APU MASTER SW p/bsw is OFF.
(3) Make sure that the hydraulic systems are depressurized
(Ref. AMM TASK 29-00-00-864-001).
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
Subtask 49-11-00-010-062-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 121VU | APU/APU/CTL | 2KD | L42 |
| 121VU | APU/ECB/SPLY | 1KD | L41 |
C. Get Access
(1) Make sure that the access platform is in position below the APU compartment.
(2) Make sure that the APU access doors 315AL and 316AR are open (Ref. AMM TASK 52-41-00-010-001).
(3) Make sure that the LIGHT SW 11LJ is set to the ON position.
(4) Put the ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE in position below the APU compartment.
(5) Do an inspection of the component interfaces and the adjacent area.
4. Procedure(1) Make sure that the access platform is in position below the APU compartment.
(2) Make sure that the APU access doors 315AL and 316AR are open (Ref. AMM TASK 52-41-00-010-001).
(3) Make sure that the LIGHT SW 11LJ is set to the ON position.
(4) Put the ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE in position below the APU compartment.
(5) Do an inspection of the component interfaces and the adjacent area.
Subtask 49-11-00-420-060-A ** ON A/C NOT FOR ALL
A. Installation of the Generator Substitution Kit
(1) Clean the component interfaces and the adjacent area.
(2) Remove the nuts (4) from the generator mounting flange (1).
(3) Lubricate the screws (11) with Synthetic base Lubricating Oil-Turbine Engine - - (Material No.03ABA1) or Synthetic base Lubricating Oil-Turbine Engine Low Temp. - (Material No.03ABB1) .
(4) Install the seal plate (10) in the cover assembly (3) with the screws (11). Tighten the screws (11).
(5) Apply a thin layer of Synthetic base Lubricating Oil-Turbine Engine - - (Material No.03ABA1) or Synthetic base Lubricating Oil-Turbine Engine Low Temp. - (Material No.03ABB1) on a new AIPC 49-11-04-05-150 SEAL (2) and install the cover assembly (3) on the mounting flange (1).
(6) Put the generator cable support (6) (Ref. AIPC 49-11-04-05-010) in position on the cover assembly (3).
(7) Attach the cover assembly (3) and the generator cable support (6) with the nuts (4).
(8) TORQUE the nuts (4) to between 4.4 and 3.9 m.daN (32.45 and 28.76 lbf.ft )
.
(9) Safety of the drain plug (5):
14QFB1 Wire-Locking Dia: 0.8 mm CRES Nickel Alloy - .
(10) Remove the nuts (8) from the generator cable support (6).
(12) Secure the electrical cables (9) with the nuts (8).
(13) Attach the electrical cables (9) with the clamp (14).
(14) Install the spacer (15), clamp (14), washer (13), screw (12), washer (16) and nut (17) in the generator cable support (6).
(15) TORQUE the nut (17) to between 0.24 and 0.22 m.daN (21.24 and 19.47 lbf.in )
.
Subtask 49-11-00-865-068-A ** ON A/C NOT FOR ALL (1) Clean the component interfaces and the adjacent area.
(2) Remove the nuts (4) from the generator mounting flange (1).
(3) Lubricate the screws (11) with Synthetic base Lubricating Oil-Turbine Engine - - (Material No.03ABA1) or Synthetic base Lubricating Oil-Turbine Engine Low Temp. - (Material No.03ABB1) .
(4) Install the seal plate (10) in the cover assembly (3) with the screws (11). Tighten the screws (11).
(5) Apply a thin layer of Synthetic base Lubricating Oil-Turbine Engine - - (Material No.03ABA1) or Synthetic base Lubricating Oil-Turbine Engine Low Temp. - (Material No.03ABB1) on a new AIPC 49-11-04-05-150 SEAL (2) and install the cover assembly (3) on the mounting flange (1).
(6) Put the generator cable support (6) (Ref. AIPC 49-11-04-05-010) in position on the cover assembly (3).
(7) Attach the cover assembly (3) and the generator cable support (6) with the nuts (4).
(8) TORQUE the nuts (4) to between 4.4 and 3.9 m.daN (32.45 and 28.76 lbf.ft )
. (9) Safety of the drain plug (5):
WARNING:
USE PROTECTIVE GOGGLES AND GLOVES WHEN YOU REMOVE OR INSTALL LOCKWIRE. EACH TIME YOU CUT LOCKWIRE, REMOVE AND DISCARD IT IMMEDIATELY. LOOSE LOCKWIRE CAN CUT YOU OR MAKE YOU BLIND, AND/OR CAN CAUSE DAMAGE.
(a) Make sure that the drain plug (5) is fully tightened and safetied with (10) Remove the nuts (8) from the generator cable support (6).
NOTE: Refer to the marks on the generator cable support when you install the electrical cable connections.
(11) Connect the electrical connector (7) and the electrical cables (9) to the generator cable support (6). (12) Secure the electrical cables (9) with the nuts (8).
(13) Attach the electrical cables (9) with the clamp (14).
(14) Install the spacer (15), clamp (14), washer (13), screw (12), washer (16) and nut (17) in the generator cable support (6).
(15) TORQUE the nut (17) to between 0.24 and 0.22 m.daN (21.24 and 19.47 lbf.in )
. B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 49-11-00-210-055-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 121VU | APU/APU/CTL | 2KD | L42 |
| 121VU | APU/ECB/SPLY | 1KD | L41 |
CAUTION:
USE ONLY APPROVED TYPES/BRANDS OF LUBRICANTS. DO NOT MIX TYPES OF LUBRICANTS (TYPE 1 3-CTS OIL WITH TYPE 2 5-CTS OIL). DO NOT MIX OILS OF DIFFERENT BRANDS MORE THAN NECESSARY.
CAUTION:
MAKE SURE THAT THE APU AIR INTAKE IS FULLY CLOSED TO MAKE SURE THAT THE SHUTDOWN OF THE APU WAS CORRECT. IF THE APU AIR INTAKE IS NOT FULLY CLOSED, OPERATE THE APU AT NO-LOAD FOR 5 MINUTES THEN DO A NORMAL SHUTDOWN.
C. Inspection Check NOTE: Oil level inspection and servicing should be checked not less than 15 minutes after the last shutdown. Do not re-service before the APU is operated again.
(1) Do a visual check of the oil quantity on the APU oil level. Add oil if the oil level is on or less than the ADD mark on the sight glass (Ref. AMM TASK 49-90-00-600-007). D. Test
(2) Examine the joint between the mounting flange (1) and the cover assembly (3) for oil leakage.
5. Close-upWARNING:
MAKE SURE THAT YOU HAVE THE CORRECT FIRE FIGHTING EQUIPMENT AVAILABLE.
(1) Start and operate the APU (Ref. AMM TASK 49-00-00-860-008). (2) Examine the joint between the mounting flange (1) and the cover assembly (3) for oil leakage.
NOTE: No leakage of oil is permitted.
(3) Stop the APU (Ref. AMM TASK 49-00-00-860-009). Subtask 49-11-00-410-063-A ** ON A/C NOT FOR ALL
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Set the LIGHT control SW 11LJ to the OFF position.
(3) Close the APU access doors 315AL 316AR and (Ref. AMM TASK 52-41-00-410-001).
(4) Remove the access platform(s).
Subtask 49-11-00-860-070-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Set the LIGHT control SW 11LJ to the OFF position.
(3) Close the APU access doors 315AL 316AR and (Ref. AMM TASK 52-41-00-410-001).
(4) Remove the access platform(s).
B. Aircraft Maintenance Configuration
(1) Put the related hydraulic system in the pressurized configuration (Ref. AMM TASK 29-00-00-864-001).
(2) De-energize the ground service network
(Ref. AMM TASK 24-42-00-862-001).
(3) Remove the WARNING NOTICE(S).
(4) Make an entry in the aircraft technical log book.
(1) Put the related hydraulic system in the pressurized configuration (Ref. AMM TASK 29-00-00-864-001).
(2) De-energize the ground service network
(Ref. AMM TASK 24-42-00-862-001).
(3) Remove the WARNING NOTICE(S).
(4) Make an entry in the aircraft technical log book.
APU Generator - Substitution Kit