Installation of the Pitot Probe
TASK 34-11-15-400-001-A
Installation of the Pitot Probe
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Expendable Parts
D. Referenced Information
3. Job Set-up
Subtask 34-11-15-860-050-A ** ON A/C NOT FOR ALL
Subtask 34-11-15-410-050-A
[Rev.10 from 2021]
2026.04.01 04:01:19 UTC
Installation of the Pitot Probe
WARNING:
MAKE SURE THAT THE CIRCUIT BREAKERS RELATED TO THE WEATHER RADAR ARE OPENED, SAFETIED AND TAGGED.
WARNING:
BEFORE YOU OPEN PHC CIRCUIT BREAKERS 2DA1(2,3), OPEN PROBE HEATER CIRCUIT-BREAKERS 1DA1(2), 3DA1(2,3), 4DA1(2,3) AND 5DA1(2,3). IF YOU DO NOT OBEY THIS SEQUENCE:
- THE PROBES WILL BECOME TOO HOT.
- THIS CAN CAUSE DAMAGE TO EQUIPMENT AND INJURY TO MAINTENANCE PERSONNEL.
CAUTION:
IF THERE WAS AN AIRSPEED OR ALTITUDE DISCREPANCY REPORT ON THE PREVIOUS FLIGHT, DO A RESET OF THE TWO ELAC'S (OFF-ON OF THE ELAC 1 AND 2 PUSHBUTTON SWITCHES ON THE OVERHEAD PANEL) WITH THE THREE HYDRAULIC SYSTEMS DEPRESSURIZED.
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | AR | ACCESS PLATFORM 1M(3 FT) |
| No specific | Torque wrench: range to between 0.90 and 0.73 m.daN (79.65 and 64.60 lbf.in ) ![]() |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 125 | LATERAL AVIONIC COMPARTMENT |
| 126 | LATERAL AVIONIC COMPARTMENT |
| FOR [9DA1] (PROBE-PITOT, 1) | |
| FOR [9DA3] (PROBE-PITOT, 3) | |
| 812 | |
| FOR [9DA2] (PROBE-PITOT, 2) | |
| 822 | |
| FIG.ITEM | DESIGNATION | IPC-CSN |
|---|---|---|
| 4 | GASKET | AIPC 34-11-01-03-040 |
| 4 | GASKET | AIPC 34-11-81-03-020 |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 20-28-00-912-802-A | Electrical Bonding - General Maintenance Procedure |
| TASK 20-28-00-912-803-A | Bonding Surface Preparation |
| TASK 30-31-00-710-001-A | Operational Test of the Probe Ice Protection |
| TASK 34-11-15-200-001-A | Inspection/Check of the Pitot Probe |
| TASK 34-11-15-710-001-A | Test of the Pitot Probe without the CFDS |
| TASK 52-41-00-010-002-A | Open the Avionics Compartment Doors for Access |
| TASK 52-41-00-410-002-A | Close the Avionics Compartment Doors after Access |
Subtask 34-11-15-860-050-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
(1) On the ADIRS CDU, on the panel 20VU, make sure that the three OFF/NAV/ATT selector switches are at OFF.
(2) Make sure that the ACCESS PLATFORM 1M(3 FT) is in position at zone 125 to get access to pitot probes 1 and 3 and at zone 126 to get access to pitot probe 2.
(3) Make sure that the access doors are open (Ref. AMM TASK 52-41-00-010-002):
(a) FOR [9DA1] (PROBE-PITOT, 1), [9DA3] (PROBE-PITOT, 3)
812
(b) FOR [9DA2] (PROBE-PITOT, 2)
822.
(4) Make sure that the protective covers of the sensors and probes (AOA, static, Pitot and TAT) are removed.
Subtask 34-11-15-860-050-B ** ON A/C NOT FOR ALL (1) On the ADIRS CDU, on the panel 20VU, make sure that the three OFF/NAV/ATT selector switches are at OFF.
(2) Make sure that the ACCESS PLATFORM 1M(3 FT) is in position at zone 125 to get access to pitot probes 1 and 3 and at zone 126 to get access to pitot probe 2.
(3) Make sure that the access doors are open (Ref. AMM TASK 52-41-00-010-002):
(a) FOR [9DA1] (PROBE-PITOT, 1), [9DA3] (PROBE-PITOT, 3)
812
(b) FOR [9DA2] (PROBE-PITOT, 2)
822.
(4) Make sure that the protective covers of the sensors and probes (AOA, static, Pitot and TAT) are removed.
A. Aircraft Maintenance Configuration
(1) On ADIRS MSU panel 41VU, make sure that the three OFF/NAV/ATT selector switches are at OFF.
(2) Make sure that the ACCESS PLATFORM 1M(3 FT) is in position at zone 125 to get access to pitot probes 1 and 3 and at zone 126 to get access to pitot probe 2.
(3) Make sure that the access doors are open (Ref. AMM TASK 52-41-00-010-002):
(a) FOR [9DA1] (PROBE-PITOT, 1), [9DA3] (PROBE-PITOT, 3)
812
(b) FOR [9DA2] (PROBE-PITOT, 2)
822.
(4) Make sure that the protective covers of the sensors and probes (AOA, static, Pitot and TAT) are removed.
Subtask 34-11-15-865-051-A (1) On ADIRS MSU panel 41VU, make sure that the three OFF/NAV/ATT selector switches are at OFF.
(2) Make sure that the ACCESS PLATFORM 1M(3 FT) is in position at zone 125 to get access to pitot probes 1 and 3 and at zone 126 to get access to pitot probe 2.
(3) Make sure that the access doors are open (Ref. AMM TASK 52-41-00-010-002):
(a) FOR [9DA1] (PROBE-PITOT, 1), [9DA3] (PROBE-PITOT, 3)
812
(b) FOR [9DA2] (PROBE-PITOT, 2)
822.
(4) Make sure that the protective covers of the sensors and probes (AOA, static, Pitot and TAT) are removed.
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 121VU | COM NAV/RADAR/1 | 5SQ1 | K13 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | COM NAV/RADAR/2 | 5SQ2 | K14 |
| ** ON A/C ALL | |||
| FOR FIN: 9DA1 (PROBEPITOT, 1) | |||
| 49VU | ANTI ICE/PROBES/AOA/1 | 4DA1 | D04 |
| 49VU | ANTI ICE/PROBES/PITOT/1 | 3DA1 | D02 |
| 122VU | ANTI ICE/PROBES/1/STATIC | 5DA1 | Z13 |
| 122VU | ANTI ICE/PROBES/1/TAT | 1DA1 | Z12 |
| FOR FIN: 9DA2 (PROBEPITOT, 2) | |||
| 122VU | ANTI ICE/PROBES/2/TAT | 1DA2 | Y15 |
| 122VU | ANTI ICE/PROBES/2/PITOT | 3DA2 | Y14 |
| 122VU | ANTI ICE/PROBES/2/AOA | 4DA2 | Y13 |
| 122VU | ANTI ICE/PROBES/2/STATIC | 5DA2 | Y11 |
| FOR FIN: 9DA3 (PROBEPITOT, 3) | |||
| 122VU | ANTI ICE/PROBES/3/PITOT | 3DA3 | Z16 |
| 122VU | ANTI ICE/PROBES/3/AOA | 4DA3 | Z15 |
| 122VU | ANTI ICE/PROBES/3/STATIC | 5DA3 | Z14 |
| FOR FIN: 9DA1 (PROBEPITOT, 1) | |||
| 49VU | ANTI ICE/PROBES/PHC/1 | 2DA1 | D03 |
| FOR FIN: 9DA2 (PROBEPITOT, 2) | |||
| 122VU | ANTI ICE/PROBES/PHC/2 | 2DA2 | Y12 |
| FOR FIN: 9DA3 (PROBEPITOT, 3) | |||
| 122VU | ANTI ICE/PROBES/PHC/3 | 2DA3 | Y16 |
CAUTION:
IF THERE WAS AN AIRSPEED OR ALTITUDE DISCREPANCY REPORT ON THE PREVIOUS FLIGHT, DO A RESET OF THE TWO ELAC'S (OFF-ON OF THE ELAC 1 AND 2 PUSHBUTTON SWITCHES ON THE OVERHEAD PANEL) WITH THE THREE HYDRAULIC SYSTEMS DEPRESSURIZED.
Subtask 34-11-15-420-050-A ** ON A/C NOT FOR ALL A. Installation of the Pitot Probe (9DA1, 9DA2, 9DA3)
(1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Prepare the surface of the bonding point(s)
(Ref. AMM TASK 20-28-00-912-803).
(4) Install the new AIPC 34-11-01-03-040 GASKET (4) correctly.
(a) Make sure that the sensor element (6) points in the forward direction of the aircraft.
(6) TORQUE the nuts (3) to between 0.90 and 0.73 m.daN (79.65 and 64.60 lbf.in )
from the inside of the fuselage.
(a) Make sure that the clearance between the gasket (4) and the aircraft skin is not more than 0.2 mm (0.01 in.).
(8) Make sure that all the electrical connections are clean and in the correct condition.
(9) Remove the PLUG - BLANKING from the quick-disconnect coupling (1).
(10) Connect the quick-disconnect coupling (1) to the pitot probe (5).
(11) Make sure that you can see the blue ring on the quick-disconnect coupling (1).
(12) Pull the quick-disconnect coupling (1) to make sure that it is correctly attached.
(13) Make sure that the quick-disconnect coupling (1) is correctly engaged (the pin on the quick-disconnect male part is fully engaged into the groove in the quick-disconnect female part).
(a) If you must do the two checks of the quick-disconnect coupling (1):
(16) Do the electrical resistance measurement and the final protection of the bonding point(s)
(Ref. AMM TASK 20-28-00-912-802).
(17) Do the inspection of the pitot probe (5) (Ref. AMM TASK 34-11-15-200-001).
Subtask 34-11-15-420-050-C ** ON A/C NOT FOR ALL (1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Prepare the surface of the bonding point(s)
(Ref. AMM TASK 20-28-00-912-803).
(4) Install the new AIPC 34-11-01-03-040 GASKET (4) correctly.
NOTE: There are two types of gasket:
- The gasket with one side identified as the PITOT SIDE.
- The gasket without the PITOT SIDE identification that you can install from the two sides.
NOTE: A second person is necessary to hold the pitot probe on the outside of the aircraft.
(a) If you use the removed gasket again, make sure that:- The gasket has no damage and it is in the correct condition.
- The service life of the gasket is not expired (a maximum of eight flight cycles).
(a) Make sure that the sensor element (6) points in the forward direction of the aircraft.
(6) TORQUE the nuts (3) to between 0.90 and 0.73 m.daN (79.65 and 64.60 lbf.in )
from the inside of the fuselage.(a) Make sure that the clearance between the gasket (4) and the aircraft skin is not more than 0.2 mm (0.01 in.).
NOTE: A small space between the gasket (4) and the aircraft skin is permitted.
(7) Remove the CAP - BLANKING from the electrical connector (2).(8) Make sure that all the electrical connections are clean and in the correct condition.
(9) Remove the PLUG - BLANKING from the quick-disconnect coupling (1).
(10) Connect the quick-disconnect coupling (1) to the pitot probe (5).
(11) Make sure that you can see the blue ring on the quick-disconnect coupling (1).
(12) Pull the quick-disconnect coupling (1) to make sure that it is correctly attached.
(13) Make sure that the quick-disconnect coupling (1) is correctly engaged (the pin on the quick-disconnect male part is fully engaged into the groove in the quick-disconnect female part).
WARNING:
IF YOU REPLACE PITOT PROBE 3 (9DA3), OR IF YOU REPLACE MORE THAN ONE PITOT PROBE, MAKE SURE THAT A SECOND QUALIFIED MECHANIC DOES A VISUAL INSPECTION OF THE QUICK-DISCONNECT COUPLING CONNECTION. THE TWO MECHANICS MUST SIGN OFF THE JOB.
(14) Refer to the table that follows to know if you must do the two checks of the quick-disconnect coupling (1) and/or the leak test:| Condition | Two Checks of the Quick-Disconnect Coupling | Leak Test |
|---|---|---|
| Installation of one pitot probe on the ADR 1 or ADR 2 circuit | No | No |
| Installation of one pitot probe on the ADR 3 circuit | Yes | No |
| Installation of two or more pitot probes | Yes | No |
- Tell a second qualified mechanic to do a visual inspection of the quick-disconnect coupling (1) (the signatures of the two mechanics are mandatory).
- Make sure that the quick-disconnect coupling (1) is correctly engaged (the pin on the quick-disconnect male part is fully engaged into the groove in the quick-disconnect female part).
(16) Do the electrical resistance measurement and the final protection of the bonding point(s)
(Ref. AMM TASK 20-28-00-912-802).
(17) Do the inspection of the pitot probe (5) (Ref. AMM TASK 34-11-15-200-001).
A. Installation of the Pitot Probe (9DA1, 9DA2, 9DA3)
(1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Prepare the surface of the bonding point(s)
(Ref. AMM TASK 20-28-00-912-803).
(4) Install the new AIPC 34-11-81-03-020 GASKET (4) correctly.
(a) Make sure that the sensor element (6) points in the forward direction of the aircraft.
(6) TORQUE the nuts (3) to between 0.90 and 0.73 m.daN (79.65 and 64.60 lbf.in )
from the inside of the fuselage.
(a) Make sure that the clearance between the gasket (4) and the aircraft skin is not more than 0.2 mm (0.01 in.).
(8) Make sure that all the electrical connections are clean and in the correct condition.
(9) Remove the PLUG - BLANKING from the quick-disconnect coupling (1).
(10) Connect the quick-disconnect coupling (1) to the pitot probe (5).
(11) Make sure that you can see the blue ring on the quick-disconnect coupling (1).
(12) Pull the quick-disconnect coupling (1) to make sure that it is correctly attached.
(13) Make sure that the quick-disconnect coupling (1) is correctly engaged (the pin on the quick-disconnect male part is fully engaged into the groove in the quick-disconnect female part).
(a) If you must do the two checks of the quick-disconnect coupling (1):
(16) Do the electrical resistance measurement and the final protection of the bonding point(s)
(Ref. AMM TASK 20-28-00-912-802).
(17) Do the inspection of the pitot probe (5) (Ref. AMM TASK 34-11-15-200-001).
Subtask 34-11-15-865-062-A (1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Prepare the surface of the bonding point(s)
(Ref. AMM TASK 20-28-00-912-803).
(4) Install the new AIPC 34-11-81-03-020 GASKET (4) correctly.
NOTE: There are two types of gasket:
- The gasket with one side identified as the PITOT SIDE.
- The gasket without the PITOT SIDE identification that you can install from the two sides.
NOTE: A second person is necessary to hold the pitot probe on the outside of the aircraft.
(a) If you use the removed gasket again, make sure that:- The gasket has no damage and it is in the correct condition.
- The service life of the gasket is not expired (a maximum of eight flight cycles).
(a) Make sure that the sensor element (6) points in the forward direction of the aircraft.
(6) TORQUE the nuts (3) to between 0.90 and 0.73 m.daN (79.65 and 64.60 lbf.in )
from the inside of the fuselage.(a) Make sure that the clearance between the gasket (4) and the aircraft skin is not more than 0.2 mm (0.01 in.).
NOTE: A small space between the gasket (4) and the aircraft skin is permitted.
(7) Remove the CAP - BLANKING from the electrical connector (2).(8) Make sure that all the electrical connections are clean and in the correct condition.
(9) Remove the PLUG - BLANKING from the quick-disconnect coupling (1).
(10) Connect the quick-disconnect coupling (1) to the pitot probe (5).
(11) Make sure that you can see the blue ring on the quick-disconnect coupling (1).
(12) Pull the quick-disconnect coupling (1) to make sure that it is correctly attached.
(13) Make sure that the quick-disconnect coupling (1) is correctly engaged (the pin on the quick-disconnect male part is fully engaged into the groove in the quick-disconnect female part).
WARNING:
IF YOU REPLACE PITOT PROBE 3 (9DA3), OR IF YOU REPLACE MORE THAN ONE PITOT PROBE, MAKE SURE THAT A SECOND QUALIFIED MECHANIC DOES A VISUAL INSPECTION OF THE QUICK-DISCONNECT COUPLING CONNECTION. THE TWO MECHANICS MUST SIGN OFF THE JOB.
(14) Refer to the table that follows to know if you must do the two checks of the quick-disconnect coupling (1) and/or the leak test:| Condition | Two Checks of the Quick-Disconnect Coupling | Leak Test |
|---|---|---|
| Installation of one pitot probe on the ADR 1 or ADR 2 circuit | No | No |
| Installation of one pitot probe on the ADR 3 circuit | Yes | No |
| Installation of two or more pitot probes | Yes | No |
- Tell a second qualified mechanic to do a visual inspection of the quick-disconnect coupling (1) (the signatures of the two mechanics are mandatory).
- Make sure that the quick-disconnect coupling (1) is correctly engaged (the pin on the quick-disconnect male part is fully engaged into the groove in the quick-disconnect female part).
(16) Do the electrical resistance measurement and the final protection of the bonding point(s)
(Ref. AMM TASK 20-28-00-912-802).
(17) Do the inspection of the pitot probe (5) (Ref. AMM TASK 34-11-15-200-001).
B. Table of the circuit breakers used in this procedure:
Subtask 34-11-15-942-050-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 49VU | ENGINE/2/FADEC A/AND EIU 2 | 2KS2 | A05 |
| 49VU | ENGINE/1/FADEC A/AND EIU 1 | 2KS1 | A04 |
C. Safety Precautions
(1) In the cockpit, on overhead control and indicating panel 25VU:
(a) Make sure that the PROBE/WINDOW HEAT pushbutton switch is released (the ON legend is off).
(b) Make sure that this(these) circuit breaker(s) is(are) closed:
Subtask 34-11-15-865-052-A (1) In the cockpit, on overhead control and indicating panel 25VU:
(a) Make sure that the PROBE/WINDOW HEAT pushbutton switch is released (the ON legend is off).
(b) Make sure that this(these) circuit breaker(s) is(are) closed:
- 2KS1
- 2KS2.
D. Remove the safety clips and tags and close these circuit breakers in this sequence:
Subtask 34-11-15-710-050-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 121VU | COM NAV/RADAR/1 | 5SQ1 | K13 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | COM NAV/RADAR/2 | 5SQ2 | K14 |
| ** ON A/C ALL | |||
| FOR FIN: 9DA1 (PROBEPITOT, 1) | |||
| 49VU | ANTI ICE/PROBES/PHC/1 | 2DA1 | D03 |
| FOR FIN: 9DA2 (PROBEPITOT, 2) | |||
| 122VU | ANTI ICE/PROBES/PHC/2 | 2DA2 | Y12 |
| FOR FIN: 9DA3 (PROBEPITOT, 3) | |||
| 122VU | ANTI ICE/PROBES/PHC/3 | 2DA3 | Y16 |
| FOR FIN: 9DA1 (PROBEPITOT, 1) | |||
| 122VU | ANTI ICE/PROBES/1/TAT | 1DA1 | Z12 |
| 49VU | ANTI ICE/PROBES/PITOT/1 | 3DA1 | D02 |
| 49VU | ANTI ICE/PROBES/AOA/1 | 4DA1 | D04 |
| 122VU | ANTI ICE/PROBES/1/STATIC | 5DA1 | Z13 |
| FOR FIN: 9DA2 (PROBEPITOT, 2) | |||
| 122VU | ANTI ICE/PROBES/2/TAT | 1DA2 | Y15 |
| 122VU | ANTI ICE/PROBES/2/PITOT | 3DA2 | Y14 |
| 122VU | ANTI ICE/PROBES/2/AOA | 4DA2 | Y13 |
| 122VU | ANTI ICE/PROBES/2/STATIC | 5DA2 | Y11 |
| FOR FIN: 9DA3 (PROBEPITOT, 3) | |||
| 122VU | ANTI ICE/PROBES/3/PITOT | 3DA3 | Z16 |
| 122VU | ANTI ICE/PROBES/3/AOA | 4DA3 | Z15 |
| 122VU | ANTI ICE/PROBES/3/STATIC | 5DA3 | Z14 |
E. Do the tests that follow:
(1) Do the operational test of the probe ice protection.
(Ref. AMM TASK 30-31-00-710-001).
5. Close-up(1) Do the operational test of the probe ice protection.
(Ref. AMM TASK 30-31-00-710-001).
NOTE: As an alternative procedure, you can do this operational test without the CFDS
(Ref. AMM TASK 34-11-15-710-001).
(Ref. AMM TASK 34-11-15-710-001).
Subtask 34-11-15-410-050-A
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Make sure that the drain holes on the pitot probes are not blocked by unwanted materials. (Ref. AMM TASK 34-11-15-200-001)
(3) Close the access doors (Ref. AMM TASK 52-41-00-410-002):
(a) FOR [9DA1] (PROBE-PITOT, 1), [9DA3] (PROBE-PITOT, 3)
812
(b) FOR [9DA2] (PROBE-PITOT, 2)
822.
(4) Install the protective covers on the sensors and probes (AOA, static, Pitot and TAT).
(5) Remove the access platform(s).
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Make sure that the drain holes on the pitot probes are not blocked by unwanted materials. (Ref. AMM TASK 34-11-15-200-001)
(3) Close the access doors (Ref. AMM TASK 52-41-00-410-002):
(a) FOR [9DA1] (PROBE-PITOT, 1), [9DA3] (PROBE-PITOT, 3)
812
(b) FOR [9DA2] (PROBE-PITOT, 2)
822.
(4) Install the protective covers on the sensors and probes (AOA, static, Pitot and TAT).
(5) Remove the access platform(s).
Pitot Probe