Electrical Bonding - General Maintenance Procedure
TASK 20-28-00-912-802-A
Electrical Bonding - General Maintenance Procedure
This task gives general bonding process and the cross-references to:
A. Consumable Materials
B. Referenced Information
3. Job Set-up
Subtask 20-28-00-941-064-A
Subtask 20-28-00-010-052-A
[Rev.10 from 2021]
2026.03.31 22:59:59 UTC
Electrical Bonding - General Maintenance Procedure
WARNING:
BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
1. Reason for the JobThis task gives general bonding process and the cross-references to:
- The procedure to do the electrical bonding of components (preparation, cleaning, assembly and protection).
- The table of maximum resistance values which gives the cross references to different measurement methods.
- The procedure to do detailed inspection on bonding lead installed on movable surfaces.
A. Consumable Materials
| REFERENCE | DESIGNATION |
|---|---|
| (Material No.08BAA9) | Non Aqueous Cleaner-General - - |
| (Material No.14SBA1) | Textile-Lint free Cotton - |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 20-28-00-869-002-A | Table of the Maximum Permitted Resistance-Values |
| TASK 20-28-00-912-803-A | Bonding Surface Preparation |
| TASK 20-28-00-912-804-A | Bonding Point Temporary Protection |
| TASK 20-28-00-912-805-A | Assembly of Components for Bonding |
| TASK 20-28-00-912-806-A | Bonding Final Protection |
| ESPM 205120 | |
Subtask 20-28-00-941-064-A
A. There is no special job set-up for this task.
4. ProcedureSubtask 20-28-00-010-052-A
A. Definition
Electrical bonding is a process to make a current path between electrically conductive parts to make sure that there is electrical continuity. This path can be between:
Subtask 20-28-00-010-053-A Electrical bonding is a process to make a current path between electrically conductive parts to make sure that there is electrical continuity. This path can be between:
- Two structural Parts
- A system point and the structure.
B. General Bonding Principle
Do the bonding procedure during the installation of the equipment or the part assembly (access doors, fairings, antenna, fittings or pipes etc.) after the removal.
To do the electrical bonding, do the steps that follow:
Subtask 20-28-00-912-071-A Do the bonding procedure during the installation of the equipment or the part assembly (access doors, fairings, antenna, fittings or pipes etc.) after the removal.
To do the electrical bonding, do the steps that follow:
- Prepare the bonding surfaces
- Apply temporary protection (if necessary)
- Assemble the different parts of the assembly
- Find the correct value of the ohmic resistance
- Do a check of the ohmic resistance value
- Apply the final protection on the bonding assembly (if applicable).
C. Bonding Surface Preparation
(1) Prepare the bonding surfaces (Ref. AMM TASK 20-28-00-912-803).
(2) If it is not possible to install the part or equipment in 1 week or less after the removal:
Subtask 20-28-00-400-050-A (1) Prepare the bonding surfaces (Ref. AMM TASK 20-28-00-912-803).
(2) If it is not possible to install the part or equipment in 1 week or less after the removal:
- Apply temporary protection on the bare bonding surfaces (Ref. AMM TASK 20-28-00-912-804).
NOTE: This step is not necessary for:
- Composite access panels and the fairings
- Titanium and corrosion-resistant steel parts (Non corrosion materials).
D. Equipment Assembly
(1) If the bare surfaces are protected with temporary protection materials, remove temporary protection material with Non Aqueous Cleaner-General - - (Material No.08BAA9) and a Textile-Lint free Cotton - (Material No.14SBA1) .
(2) Assemble the fasteners (nuts, bolts, screws, washers etc.), bonding leads, clamp or the equipment.
To do this, refer to the instructions as follows:
(a) For electrical connectors, Refer to ESPM 205120.
(b) For all other components (Ref. AMM TASK 20-28-00-912-805).
Subtask 20-28-00-760-050-A (1) If the bare surfaces are protected with temporary protection materials, remove temporary protection material with Non Aqueous Cleaner-General - - (Material No.08BAA9) and a Textile-Lint free Cotton - (Material No.14SBA1) .
(2) Assemble the fasteners (nuts, bolts, screws, washers etc.), bonding leads, clamp or the equipment.
To do this, refer to the instructions as follows:
(a) For electrical connectors, Refer to ESPM 205120.
(b) For all other components (Ref. AMM TASK 20-28-00-912-805).
E. Electrical Resistance Measurement
(1) Refer to the table of maximum ohmic resistance-values (Ref. AMM TASK 20-28-00-869-002).
The table gives information of:
Subtask 20-28-00-916-096-A (1) Refer to the table of maximum ohmic resistance-values (Ref. AMM TASK 20-28-00-869-002).
The table gives information of:
- The maximum permitted value
- The applicable measurement test.
- Apply final protection to the bonding assembly (go to paragraph final protection).
Bonding Process - Flow Chart