Bonding Point Temporary Protection
TASK 20-28-00-912-804-A
Bonding Point Temporary Protection
This procedure is applicable, when the bonding installation of the part or the equipment is not possible in 1 week or less after the removal.
2. Job Set-up Information
A. Consumable Materials
B. Referenced Information
3. Job Set-up
Subtask 20-28-00-941-066-A
Subtask 20-28-00-916-097-A
[Rev.10 from 2021]
2026.04.01 04:50:35 UTC
Bonding Point Temporary Protection
WARNING:
BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
1. Reason for the JobThis procedure is applicable, when the bonding installation of the part or the equipment is not possible in 1 week or less after the removal.
2. Job Set-up Information
A. Consumable Materials
| REFERENCE | DESIGNATION |
|---|---|
| (Material No.03GEE1) | Synthetic Oil base Grease-Fuel and Oxidized Environment Fluorinated - |
| (Material No.03HBD9) | Synthetic Ester base Grease-General Purpose Low Temp - |
| REFERENCE | DESIGNATION |
|---|---|
Subtask 20-28-00-941-066-A
A. There is no special job set-up for this task.
4. ProcedureSubtask 20-28-00-916-097-A
A. Temporary protection of the bare surface
(1) Materials:
(1) Materials:
- Synthetic Ester base Grease-General Purpose Low Temp - (Material No.03HBD9) on all the bare surfaces but do not apply Synthetic Ester base Grease-General Purpose Low Temp - (Material No.03HBD9) on the oxygen system circuits
- Synthetic Oil base Grease-Fuel and Oxidized Environment Fluorinated - (Material No.03GEE1) on the oxygen circuits.
Bonding - Temporary Protection - Typical