Installation of the Differential Pressure Indicator
TASK 29-14-41-400-803-A
Installation of the Differential Pressure Indicator
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Consumable Materials
C. Work Zones and Access Panels
D. Referenced Information
3. Job Set-up
Subtask 29-14-41-860-069-A
Subtask 29-14-41-420-057-A
Subtask 29-14-41-860-070-A
[Rev.10 from 2021]
2026.04.01 07:54:34 UTC
Installation of the Differential Pressure Indicator
WARNING:
BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | Torque wrench: range to between 23.0 and 21.3 lbf.in (0.26 and 0.24 m.daN ) ![]() |
| REFERENCE | DESIGNATION |
|---|---|
| (Material No.14CCB6) | Testing Medium-Leak Detection - Oxygen System |
| (Material No.14QFB1) | Wire-Locking Dia: 0.8 mm CRES Nickel Alloy - |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 191DB, 195BB |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 29-00-00-864-001-A | Put the Related Hydraulic System in the Depressurized Configuration before Maintenance Action |
| TASK 29-14-00-614-001-A | Depressurization of the Hydraulic Reservoirs |
| TASK 29-14-00-614-002-A | Pressurization of the Hydraulic Reservoirs through the Ground Connector |
| TASK 29-14-00-614-002-A-01 | Pressurization of the Hydraulic Reservoirs with the Auxiliary Power Unit (APU) |
| TASK 29-14-00-720-001-A | Functional Test of the Pressurizing System of the Hydraulic Reservoirs |
Subtask 29-14-41-860-069-A
A. Aircraft Maintenance Configuration
(1) Make sure that the WARNING NOTICE(S) are in position to tell person not to pressurize Green, Blue and Yellow hydraulic systems:
(4) Make sure that the reservoirs of the Green, Blue and Yellow hydraulic systems are depressurized.
(Ref. AMM TASK 29-14-00-614-001).
(5) Make sure that the access panel 195BB is open.
Subtask 29-14-41-865-068-A (1) Make sure that the WARNING NOTICE(S) are in position to tell person not to pressurize Green, Blue and Yellow hydraulic systems:
- In the cockpit on the hydraulic section 40VU of the overhead panel
- On the ground service panel of the Green, Blue and Yellow hydraulic systems.
- In the cockpit on the AIR COND overhead panel 30VU
- On the access door 191DB.
(4) Make sure that the reservoirs of the Green, Blue and Yellow hydraulic systems are depressurized.
(Ref. AMM TASK 29-14-00-614-001).
(5) Make sure that the access panel 195BB is open.
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 49VU | HYD/HYD PWR/B WARN/& CTL | 2702GJ | C12 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | HYDRAULIC/G HYD/PUMP ENG1/CTL | 1701GK | H12 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/G HYD/PUMP ENG1/CTL | 1701GK | R35 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/HYD POWER/Y | 3803GX | N30 |
| 121VU | HYDRAULIC/G HYD/PUMP ENG1/MONG | 1702GK | R34 |
| ** ON A/C ALL | |||
| 121VU | APU/APU/CTL | 2KD | L42 |
| 121VU | APU/ECB/SPLY | 1KD | L41 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/HYD POWER/Y | 3803GX | N31 |
| 121VU | HYDRAULIC/G HYD/PUMP ENG1/MONG | 1702GK | R33 |
| ** ON A/C ALL | |||
| 123VU | B HYD/ELEC PUMP | 2701GJ | AB09 |
| 123VU | Y HYD/ELEC/PUMP | 3802GX | AB06 |
| 123VU | Y HYD/ELEC/ELEC PUMP/NORM | 3801GX | AB03 |
Subtask 29-14-41-420-057-A
A. Installation of the Differential Pressure indicator
(1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Install new packings (4) and (5) on the differential pressure indicator (2).
(4) Put the differential pressure indicator (2) in the reservoir pressurization unit (1).
(5) Loosely install the screws (3).
(6) TORQUE the screws (3) to between 23.0 and 21.3 lbf.in (0.26 and 0.24 m.daN )
.
14QFB1 Wire-Locking Dia: 0.8 mm CRES Nickel Alloy - .
Subtask 29-14-41-865-069-A (1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Install new packings (4) and (5) on the differential pressure indicator (2).
(4) Put the differential pressure indicator (2) in the reservoir pressurization unit (1).
(5) Loosely install the screws (3).
(6) TORQUE the screws (3) to between 23.0 and 21.3 lbf.in (0.26 and 0.24 m.daN )
. WARNING:
USE PROTECTIVE GOGGLES AND GLOVES WHEN YOU REMOVE OR INSTALL LOCKWIRE. EACH TIME YOU CUT LOCKWIRE, REMOVE AND DISCARD IT IMMEDIATELY. LOOSE LOCKWIRE CAN CUT YOU OR MAKE YOU BLIND, AND/OR CAN CAUSE DAMAGE.
(7) Safety the screws (3) with B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 29-14-41-710-056-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 49VU | HYD/HYD PWR/B WARN/& CTL | 2702GJ | C12 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | HYDRAULIC/G HYD/PUMP ENG1/CTL | 1701GK | H12 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/G HYD/PUMP ENG1/CTL | 1701GK | R35 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/HYD POWER/Y | 3803GX | N30 |
| 121VU | HYDRAULIC/G HYD/PUMP ENG1/MONG | 1702GK | R34 |
| ** ON A/C ALL | |||
| 121VU | APU/APU/CTL | 2KD | L42 |
| 121VU | APU/ECB/SPLY | 1KD | L41 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/HYD POWER/Y | 3803GX | N31 |
| 121VU | HYDRAULIC/G HYD/PUMP ENG1/MONG | 1702GK | R33 |
| ** ON A/C ALL | |||
| 123VU | B HYD/ELEC PUMP | 2701GJ | AB09 |
| 123VU | Y HYD/ELEC/PUMP | 3802GX | AB06 |
| 123VU | Y HYD/ELEC/ELEC PUMP/NORM | 3801GX | AB03 |
C. Leak test
(1) Do an functional test of the reservoir pressurization unit (Ref. AMM TASK 29-14-00-720-001).
(2) Apply the Testing Medium-Leak Detection - Oxygen System (Material No.14CCB6) to the connection area of the differential pressure indicator (2) and the reservoir pressurization unit. Make sure that there is no leakage.
5. Close-up(1) Do an functional test of the reservoir pressurization unit (Ref. AMM TASK 29-14-00-720-001).
(2) Apply the Testing Medium-Leak Detection - Oxygen System (Material No.14CCB6) to the connection area of the differential pressure indicator (2) and the reservoir pressurization unit. Make sure that there is no leakage.
Subtask 29-14-41-860-070-A
A. Put the aircraft back to its initial configuration.
(1) Make sure that the hydraulic systems are depressurized
(Ref. AMM TASK 29-00-00-864-001).
(2) Make sure that hydraulic reservoirs are pressurized (Ref. AMM TASK 29-14-00-614-002).
(3) Make sure that the work area is clean and clear of tools and other items.
Subtask 29-14-41-410-056-A Subtask 29-14-41-942-054-A (1) Make sure that the hydraulic systems are depressurized
(Ref. AMM TASK 29-00-00-864-001).
(2) Make sure that hydraulic reservoirs are pressurized (Ref. AMM TASK 29-14-00-614-002).
(3) Make sure that the work area is clean and clear of tools and other items.
C. Put the aircraft back to its initial configuration.
(1) Remove the WARNING NOTICE(S) from the cockpit, ground service panel and access panel 191DB.
(1) Remove the WARNING NOTICE(S) from the cockpit, ground service panel and access panel 191DB.
Differential Pressure Indicator