Operational Test of the APU Low Pressure Fuel Valve using each individual Motor in turn
TASK 28-29-00-710-001-A
Operational Test of the APU Low Pressure Fuel Valve using each individual Motor in turn
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Referenced Information
3. Job Set-up
Subtask 28-29-00-860-050-A
Subtask 28-29-00-710-050-B ** ON A/C NOT FOR ALL
Subtask 28-29-00-865-053-A
[Rev.10 from 2021]
2026.04.01 04:25:53 UTC
Operational Test of the APU Low Pressure Fuel Valve using each individual Motor in turn
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | AR | SAFETY CLIP - CIRCUIT BREAKER |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-861-002-A-02 | Energize the Aircraft Electrical Circuits from Engine 1(2) |
| TASK 24-41-00-862-002-A | De-energize the Aircraft Electrical Circuits Supplied from the External Power |
| TASK 24-41-00-862-002-A-01 | De-energize the Aircraft Electrical Circuits Supplied from the APU |
| TASK 24-41-00-862-002-A-02 | De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2) |
| TASK 31-60-00-860-001-A | EIS Start Procedure |
Subtask 28-29-00-860-050-A
A. Aircraft Maintenance Configuration
(1) Energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-861-002).
(2) Do the EIS start procedure (upper ECAM DU and lower ECAM DU only)
(Ref. AMM TASK 31-60-00-860-001).
(3) On the APU section of the overhead panel 25VU, make sure that the APU MASTER SW is in the off position (the ON legend is off).
(4) On the FUEL overhead panel 40VU, make sure that all L TK PUMPS and R TK PUMPS pushbutton switches are released (the OFF legends are on).
Subtask 28-29-00-865-052-A (1) Energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-861-002).
(2) Do the EIS start procedure (upper ECAM DU and lower ECAM DU only)
(Ref. AMM TASK 31-60-00-860-001).
(3) On the APU section of the overhead panel 25VU, make sure that the APU MASTER SW is in the off position (the ON legend is off).
(4) On the FUEL overhead panel 40VU, make sure that all L TK PUMPS and R TK PUMPS pushbutton switches are released (the OFF legends are on).
B. Make sure that this(these) circuit breaker(s) is(are) closed:
Subtask 28-29-00-865-057-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 121VU | APU/APU/CTL | 2KD | L42 |
| 121VU | APU/ECB/SPLY | 1KD | L41 |
| 121VU | APU/FUEL/LP VALVE/CTL | 1QF | M40 |
| 121VU | APU/FUEL/LP VALVE/SPLY | 2QF | M39 |
C. Open, safety and tag this(these) circuit breaker(s):
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 121VU | APU/FUEL/PUMP/CTL | 3QC | M38 |
Subtask 28-29-00-710-050-B ** ON A/C NOT FOR ALL
A. Operational test of the APU LP Fuel Valve using each individual motor in turn
Subtask 28-29-00-710-050-C ** ON A/C NOT FOR ALL | ACTION | RESULT |
|---|---|
1.On the circuit breaker panel 121VU:
| |
2.On the ECAM control panel:
| On the lower ECAM display unit:
|
3.On the APU section of the overhead panel 25VU:
| On the APU section of the overhead panel 25VU:
|
| | On the lower ECAM display unit:
|
4.On the APU section of the overhead panel 25VU:
| On the APU section of the overhead panel 25VU:
|
| | On the lower ECAM display unit:
|
5.On the circuit breaker panel 121VU:
| |
6.On the APU section of the overhead panel 25VU:
| On the APU section of the overhead panel 25VU:
|
| | On the lower ECAM display unit:
|
7.On the APU section of the overhead panel 25VU:
| On the APU section of the overhead panel 25VU:
|
| | On the lower ECAM display unit:
|
8.On the circuit breaker panel 121VU:
| |
A. Operational test of the APU LP Fuel Valve using each individual motor in turn
5. Close-up| ACTION | RESULT |
|---|---|
1.On circuit breaker panel 121VU:
| |
2.On the ECAM control panel:
| On the lower ECAM display unit:
|
3.On the APU section of overhead panel 25VU:
| On the APU section of overhead panel 25VU:
|
| | On the lower ECAM display unit:
|
4.On the APU section of overhead panel 25VU:
| On the APU section of overhead panel 25VU:
|
| | On the lower ECAM display unit:
|
5.On circuit breaker panel 121VU:
| |
6.On the APU section of overhead panel 25VU:
| On the APU section of overhead panel 25VU:
|
| | On the lower ECAM display unit:
|
7.On the APU section of overhead panel 25VU:
| On the APU section of overhead panel 25VU:
|
| | On the lower ECAM display unit:
|
8.On circuit breaker panel 121VU:
| |
Subtask 28-29-00-865-053-A
A. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 28-29-00-860-051-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 121VU | APU/FUEL/PUMP/CTL | 3QC | M38 |
B. Put the aircraft back to its initial configuration.
(1) On the ECAM control panel, set the UPPER DISPLAY and LOWER DISPLAY potentiometers to OFF.
(2) De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002).
(3) Put the system back to the serviceable condition.
(1) On the ECAM control panel, set the UPPER DISPLAY and LOWER DISPLAY potentiometers to OFF.
(2) De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002).
(3) Put the system back to the serviceable condition.