1. Reason for the Job
Refer to the MPD TASK: 200171-01
CLEANING OF EWIS INSTALLED IN THE AFT CABIN UNDERFLOOR COMPARTMENT (ONLY IF CONTAMINATED)(EWIS)
NOTE: This is an EWIS (Electrical Wiring Interconnection System) procedure. EWIS is defined in ESPM 20-33-11.
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
1
ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
171
AFT CABIN U/FLOOR COMPARTMENT
172
AFT CABIN U/FLOOR COMPARTMENT
171AL, 172AR
 C. Referenced Information
REFERENCE
DESIGNATION
TASK 24-41-00-862-002-A
De-energize the Aircraft Electrical Circuits Supplied from the External Power
TASK 24-41-00-862-002-A-01
De-energize the Aircraft Electrical Circuits Supplied from the APU
TASK 24-41-00-862-002-A-02
De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2)
TASK 25-55-12-000-001-A
Removal of the Aft Cargo-Compartment Partition at FR65
TASK 25-55-12-400-001-A
Installation of the Aft Cargo-Compartment Partition at FR65
TASK 53-00-00-000-801-A
Removal of the Floor Panels in the Cabin from FR12 to FR70
TASK 53-00-00-000-801-A-01
Removal of the Floor Panels in the Cabin from FR12 to FR70 (Alternative Removal Procedure - Dry Sealing Concept)
TASK 53-00-00-000-801-A-02
Removal of the Cabin Floor Panels from FR12 to FR70 (Alternative Removal Procedure with the Skyflex Option)
TASK 53-00-00-400-801-A
Installation of the Floor Panels in the Cabin from FR12 to FR70
TASK 53-00-00-400-801-A-01
Installation of the Floor Panels in the Cabin from FR12 to FR70 (Alternative Installation Procedure - Dry Sealing Concept)
TASK 53-00-00-400-801-A-02
Installation of the Cabin Floor Panels from FR12 to FR70 (Alternative Installation Procedure with the Skyflex Option)
ESPM 2055000
TASK 06-41-53-00
FUSELAGE-DESCRIPTION AND OPERATION
3. Job Set-up
Subtask 24-92-00-010-087-A
A. Get Access
   (1) Put an ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE in position below the access panels:
172AR 171AL.
   (2) Open access panels:
Subtask 24-92-00-862-075-A
B. De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002).
4. Procedure
Subtask 24-92-00-410-181-A
A. Preparation for Cleaning of Contaminated Wiring
   (1) Remove the AFT cargo-compartment partition FR65 (Ref. AMM TASK 25-55-12-000-001).
   (2) Remove the cabin floor panels from FR65 to FR70 (Ref. AMM TASK 53-00-00-000-801), (Ref. AMM D/O 06-41-53-00).
Subtask 24-92-00-160-050-A
B. Cleaning of All Wiring Installed in the AFT Cabin Underfloor Compartment (Only Contaminated Wiring).
   (1) Clean wiring if there is dust or lint contamination ESPM 2055000.
     (a) On the AC/DC power-distribution routes: 1P and 2P.
     (b) On the flight control routes: 7S and 8S.
     (c) On the engine control routes: 1S and 2S APU.
     (d) On other routes: 1M and 2M.
5. Close-up
Subtask 24-92-00-410-085-A
A. Close Access
   (1) Installation of the cabin floor panels from FR65 to FR70 (Ref. AMM TASK 53-00-00-400-801), (Ref. AMM D/O 06-41-53-00).
   (2) Install the AFT cargo-compartment partition FR65 (Ref. AMM TASK 25-55-12-400-001).
   (3) Close the access panels:
   (4) Remove the access platform(s).
[Rev.10 from 2021] 2026.03.31 23:26:59 UTC