Borescope Inspection of the Oil System [CFML]
TASK 79-00-00-290-801-A
Borescope Inspection of the Oil System
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 79-00-00-941-094-A
Subtask 79-00-00-290-050-A
Subtask 79-00-00-410-089-A
[Rev.10 from 2021]
2026.04.01 03:42:43 UTC
Borescope Inspection of the Oil System
WARNING:
BE CAREFUL WHEN YOU DO WORK ON THE ENGINE PARTS AFTER THE ENGINE SHUTDOWN. USE APPLICABLE THERMAL GLOVES. THE ENGINE PARTS CAN STAY HOT FOR ONE HOUR AFTER SHUTDOWN AND CAN BURN YOU.
ZONE: 400
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 1M(3 FT) |
| No specific | 1 | BORESCOPE SET |
| No specific | AR | WARNING NOTICE(S) |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 400 | POWER PLANT, NACELLES AND PYLONS |
| FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENGINE 1) | |
| 437AL, 438AR, 451AL, 452AR | |
| FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENGINE 2) | |
| 447AL, 448AR, 461AL, 462AR | |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 71-00-51-000-803-A | Removal of the Power Plant with 2D Bootstrap |
| TASK 71-00-51-400-803-A | Installation of the Power Plant with 2D Bootstrap |
| TASK 71-13-00-010-803-A | Opening of the Fan Cowl Doors |
| TASK 71-13-00-410-803-A | Closing of the Fan Cowl Doors |
| TASK 72-00-00-290-822-A | Borescope Inspection of the Low Pressure Turbine (LPT) Blades |
| TASK 72-30-00-290-801-A | Borescope Inspection of the High Pressure Compressor Section |
| TASK 78-30-00-040-809-A | Deactivation of the Thrust Reverser System for Ground Maintenance |
| TASK 78-30-00-440-809-A | Reactivation of the Thrust Reverser System after Ground Maintenance |
| TASK 78-36-00-010-806-A | Opening of the Thrust Reverser Cowl Doors |
| TASK 78-36-00-410-806-A | Closing of the Thrust Reverser Cowl Doors |
Subtask 79-00-00-941-094-A
A. Safety Precautions
(1) On the center pedestal, on ENG panel 115VU:
(a) Make sure that the ENG/MODE selector switch is in the NORM position.
(b) Make sure that the ENG/MASTER 1(2) control switch was in the OFF position not less than five minutes before you do this procedure.
(c) Put WARNING NOTICE(S) in position to tell persons not to operate:
(a) Make sure that the ON legend of the FADEC GND PWR/1(2) pushbutton switch is off.
(b) Put a WARNING NOTICE(S) in position to tell persons not to energize FADEC 1(2).
Subtask 79-00-00-010-103-A (1) On the center pedestal, on ENG panel 115VU:
(a) Make sure that the ENG/MODE selector switch is in the NORM position.
(b) Make sure that the ENG/MASTER 1(2) control switch was in the OFF position not less than five minutes before you do this procedure.
(c) Put WARNING NOTICE(S) in position to tell persons not to operate:
- The ENG/MODE selector switch
- The ENG/MASTER 1(2) control switch.
(a) Make sure that the ON legend of the FADEC GND PWR/1(2) pushbutton switch is off.
(b) Put a WARNING NOTICE(S) in position to tell persons not to energize FADEC 1(2).
B. Get Access
(1) Open the fan cowl doors (Ref. AMM TASK 71-13-00-010-803):
(a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENGINE 1)
437AL 438AR
(b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENGINE 2)
447AL 448AR
(2) Put an ACCESS PLATFORM 1M(3 FT) in position.
Subtask 79-00-00-040-065-A (1) Open the fan cowl doors (Ref. AMM TASK 71-13-00-010-803):
(a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENGINE 1)
437AL 438AR
(b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENGINE 2)
447AL 448AR
(2) Put an ACCESS PLATFORM 1M(3 FT) in position.
C. Deactivation of the Thrust Reverser System for Ground Maintenance
Subtask 79-00-00-010-104-A WARNING:
YOU MUST DEACTIVATE THE THRUST REVERSER BEFORE YOU DO WORK ON OR AROUND IT. IF YOU DO NOT, THE THRUST REVERSER CAN OPERATE ACCIDENTALLY AND CAUSE AN INJURY AND/OR DAMAGE.
(1) Do the deactivation of the thrust reverser system for ground maintenance (Ref. AMM TASK 78-30-00-040-809). D. Get Access
(1) Open the thrust reverser cowl-doors (Ref. AMM TASK 78-36-00-010-806):
(a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENGINE 1)
451AL 452AR
(b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENGINE 2)
461AL 462AR
4. Procedure(1) Open the thrust reverser cowl-doors (Ref. AMM TASK 78-36-00-010-806):
(a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENGINE 1)
451AL 452AR
(b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENGINE 2)
461AL 462AR
Subtask 79-00-00-290-050-A
A. Borescope Inspection of the Oil System
(2) Do the borescope inspection of HPC stage 1 and 2 blades using the BORESCOPE SET at the location (1), location (2) and the location (3) (Ref. AMM TASK 72-30-00-290-801) for:
(3) Do the borescope inspection of three pressurization tubes through the borescope plug (4) and the borescope plug (5) for:
(4) If there are oil traces on the blades in the flowpath, do the borescope inspection of LP turbine using the BORESCOPE SET at the location (10) for stage 5 (Ref. AMM TASK 72-00-00-290-822).
(5)
5. Close-upNOTE: This task gives the procedure for the borescope inspection of areas of the internal engine where oil leakage could occur.
NOTE: When you do the fault isolation for an oil consumption problem, an inspection for an internal oil leak is necessary.
(1) Do the borescope inspection of High Pressure Compressor (HPC) stages 1 and 2 between the stage 1 vane and stage 1 blade using the BORESCOPE SET at the location (1) and the location (2) (Ref. AMM TASK 72-30-00-290-801) for: | INSPECT/CHECK | MAXIMUM SERVICEABLE LIMITS | REMARKS |
|---|---|---|
| 1.Oil leakage | Not serviceable, if wet with oil and if the oil consumption is more than the specified serviceable limits. | Replace the engine (Ref. AMM TASK 71-00-51-000-803) and (Ref. AMM TASK 71-00-51-400-803). |
| INSPECT/CHECK | MAXIMUM SERVICEABLE LIMITS | REMARKS |
|---|---|---|
| 1.Oil leakage | Not serviceable, if wet with oil and if the oil consumption is more than the specified serviceable limits. | Replace the engine (Ref. AMM TASK 71-00-51-000-803) and (Ref. AMM TASK 71-00-51-400-803). |
| INSPECT/CHECK | MAXIMUM SERVICEABLE LIMITS | REMARKS |
|---|---|---|
| 1.Oil leakage | Not serviceable, if wet with oil and if the oil consumption is more than the specified serviceable limits. | Replace the engine (Ref. AMM TASK 71-00-51-000-803) and (Ref. AMM TASK 71-00-51-400-803). |
| INSPECT/CHECK | MAXIMUM SERVICEABLE LIMITS | REMARKS |
|---|---|---|
| 1.Oil leakage | Not serviceable, if wet with oil and if the oil consumption is more than the specified serviceable limits. | Replace the engine (Ref. AMM TASK 71-00-51-000-803) and (Ref. AMM TASK 71-00-51-400-803). |
| INSPECT/CHECK | MAXIMUM SERVICEABLE LIMITS | REMARKS |
|---|---|---|
| 1.Oil leakage | Not serviceable, if wet with oil and if the oil consumption is more than the specified serviceable limits. | Replace the engine (Ref. AMM TASK 71-00-51-000-803) and (Ref. AMM TASK 71-00-51-400-803). |
Subtask 79-00-00-410-089-A
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the thrust reverser cowl-doors (Ref. AMM TASK 78-36-00-410-806):
(a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENGINE 1)
451AL 452AR
(b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENGINE 2)
461AL 462AR
Subtask 79-00-00-440-065-A (1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the thrust reverser cowl-doors (Ref. AMM TASK 78-36-00-410-806):
(a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENGINE 1)
451AL 452AR
(b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENGINE 2)
461AL 462AR
B. Do the reactivation of the thrust reverser system after ground maintenance (Ref. AMM TASK 78-30-00-440-809).
Subtask 79-00-00-410-090-A
Borescope Inspection of the Oil System