Installation of the Additional Center-Tank (ACT) Relay-Box
TASK 25-71-11-400-001-A
Installation of the Additional Center-Tank (ACT) Relay-Box
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 25-71-11-860-050-A ** ON A/C NOT FOR ALL
Subtask 25-71-11-420-050-A ** ON A/C NOT FOR ALL
Subtask 25-71-11-865-053-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.03.31 23:41:55 UTC
Installation of the Additional Center-Tank (ACT) Relay-Box
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | AR | ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 122 | AVIONICS COMPARTMENT |
| 822 |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-861-002-A-02 | Energize the Aircraft Electrical Circuits from Engine 1(2) |
| TASK 24-41-00-862-002-A | De-energize the Aircraft Electrical Circuits Supplied from the External Power |
| TASK 24-41-00-862-002-A-01 | De-energize the Aircraft Electrical Circuits Supplied from the APU |
| TASK 24-41-00-862-002-A-02 | De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2) |
Subtask 25-71-11-860-050-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
(1) Make sure that the aircraft is energized (Ref. AMM TASK 24-41-00-861-002).
(2) Make sure that the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE is in position at the access door 822.
(3) Make sure that the access door 822 is open.
Subtask 25-71-11-865-052-A ** ON A/C NOT FOR ALL (1) Make sure that the aircraft is energized (Ref. AMM TASK 24-41-00-861-002).
(2) Make sure that the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE is in position at the access door 822.
(3) Make sure that the access door 822 is open.
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 121VU | ACT1/REFUEL & SPLY | 33QU | L29 |
| 121VU | ACT XFR VALVE MAN CTL | 30QH | N29 |
| 121VU | ACT1/CTL & SPLY | 9QH | P29 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | ACT2/REFUEL & SPLY | 34QU | L28 |
| 121VU | ACT2/CTL & SPLY | 10QH | P28 |
Subtask 25-71-11-420-050-A ** ON A/C NOT FOR ALL
A. Installation of the ACT Relay Box
(1) Install the mounting assy (8) and the four screws (9).
(2) Tighten the screws (9).
(3) Install the four clip nuts (7) on the mounting assy (8).
(4) Put the relay box (1) in position on the mounting assy (8).
(5) Install and tighten the four screws (6).
(6) Connect the electrical connectors (4) and (5) to the relay box (1).
(8) Tighten the screws (3).
5. Close-up(1) Install the mounting assy (8) and the four screws (9).
(2) Tighten the screws (9).
(3) Install the four clip nuts (7) on the mounting assy (8).
(4) Put the relay box (1) in position on the mounting assy (8).
(5) Install and tighten the four screws (6).
(6) Connect the electrical connectors (4) and (5) to the relay box (1).
NOTE: Make sure that the two electrical connectors are installed correctly.
(7) Install the cover (2) and the four screws (3). (8) Tighten the screws (3).
Subtask 25-71-11-865-053-A ** ON A/C NOT FOR ALL
A. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 25-71-11-410-050-A ** ON A/C NOT FOR ALL Subtask 25-71-11-862-050-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 121VU | ACT1/REFUEL & SPLY | 33QU | L29 |
| 121VU | ACT XFR VALVE MAN CTL | 30QH | N29 |
| 121VU | ACT1/CTL & SPLY | 9QH | P29 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | ACT2/REFUEL & SPLY | 34QU | L28 |
| 121VU | ACT2/CTL & SPLY | 10QH | P28 |
Additional Center Tank (ACT) Relay Box