1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
200
UPPER HALF FUSELAGE
261BC
 B. Referenced Information
REFERENCE
DESIGNATION
TASK 24-42-00-861-001-A
Energize the Ground Service Network from the External Power
TASK 24-42-00-862-001-A
De-energize the Ground Service Network Supplied from the External Power
TASK 25-23-42-000-002-A
Removal of the Ceiling Panels - Aft Utility Area
TASK 25-23-42-400-002-A
Installation of the Ceiling Panels - Aft Utility Area
TASK 25-65-00-740-001-A
Emergency Locator Transmitter (ELT) System - BITE Test
TASK 25-65-00-840-001-A
Procedure after a Change of Aircraft Registration Number
F DONGLE (141 MX) ** ON A/C NOT FOR ALL
F DONGLE (141 MX) ** ON A/C NOT FOR ALL
3. Job Set-up
Subtask 25-65-35-860-052-B ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
   (1) Make sure that the ground service network is energized (Ref. AMM TASK 24-42-00-861-001).
   (2) Make sure that the ceiling panel 261BC is removed (Ref. AMM TASK 25-23-42-000-002).
4. Procedure
Subtask 25-65-35-560-053-B ** ON A/C NOT FOR ALL
A. Preparation for Installation
   (1) If the aircraft registration code/number (ICAO) is changed refer to (Ref. AMM TASK 25-65-00-840-001).
Subtask 25-65-35-420-053-B ** ON A/C NOT FOR ALL
B. Installation of the Programming Dongle 141MX
F DONGLE (141 MX) ** ON A/C NOT FOR ALL
F DONGLE (141 MX) ** ON A/C NOT FOR ALL
   (1) Make sure that the ON/OFF/ARM switch (6) is in the OFF position.
   (2) Do an inspection of the component interfaces and the adjacent area.
   (3) Remove the CAP-BLANKING from each electrical connector and receptacle.
   (4) Make sure that all the electrical connections are clean and in the correct condition.
   (5) Clean the component interfaces and the adjacent area.
   (6) Connect the electrical connector (1) with the bracket (5).
   (7) Connect the electrical connector (3) or the programming-dongle (2) to the connector (7) of the ELT (4).
Subtask 25-65-35-740-052-B ** ON A/C NOT FOR ALL
C. Do the BITE test (Ref. AMM TASK 25-65-00-740-001).
5. Close-up
Subtask 25-65-35-410-052-B ** ON A/C NOT FOR ALL
A. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.
   (2) Install the ceiling panel 261BC (Ref. AMM TASK 25-23-42-400-002).
   (3) Remove the ground support and maintenance equipment, the special and standard tools and all other items.
Subtask 25-65-35-862-052-B ** ON A/C NOT FOR ALL
B. De-energize the ground service network (Ref. AMM TASK 24-42-00-862-001).