W DOC AIRBUS | AMM A320F

Operational Test of the Transfer Inhibition


TASK 24-22-00-710-002-A
Operational Test of the Transfer Inhibition


ZONE: 210
1. Reason for the Job
Refer to the MPD TASK: 242200-01
OPERATIONAL CHECK OF TRANSFER INHIBITION
Make sure that the transfer function is off when you release the BUS TIE pushbutton switch.
2. Job Set-up Information
 A. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
210
CKPT,FWD COMPT BHD TO FLT COMPT BULKHEAD
 B. Referenced Information
REFERENCE
DESIGNATION
TASK 24-41-00-861-002-A
Energize the Aircraft Electrical Circuits from the External Power
TASK 24-41-00-861-002-A-01
Energize the Aircraft Electrical Circuits from the APU
TASK 24-41-00-861-002-A-02
Energize the Aircraft Electrical Circuits from Engine 1(2)
TASK 24-41-00-862-002-A
De-energize the Aircraft Electrical Circuits Supplied from the External Power
TASK 24-41-00-862-002-A-01
De-energize the Aircraft Electrical Circuits Supplied from the APU
TASK 24-41-00-862-002-A-02
De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2)
3. Job Set-up
Subtask 24-22-00-860-052-A
A. Aircraft Maintenance Configuration
   (1) Energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-861-002).
   (2) On the ELEC panel 35VU, make sure that the BAT1 and BAT2 pushbutton switches are pushed.
4. Procedure
Subtask 24-22-00-710-051-A
A. Operational test of the transfer inhibition
ACTION
RESULT
1.On the panel 35VU:
  • release the BUS TIE pushbutton switch.
In the cockpit, on the panel 35VU:
  • loss of the power supply from the electrical ground power unit:
    .the OFF legend of the BUS TIE pushbutton switch comes on.
NOTE: This shows that the transfer contactors are open.
The batteries are the only available power supply.
2.On the panel 35VU:
  • push the BUS TIE pushbutton switch.
In the cockpit, on the panel 35VU:
  • the OFF legend of the BUS TIE pushbutton switch goes off.
    All the aircraft electrical circuits are supplied.
5. Close-up
Subtask 24-22-00-862-051-A
A. Put the aircraft back to its initial configuration.
   (1) De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002)