Installation of the Flush Control Unit
TASK 38-31-12-400-001-A
Installation of the Flush Control Unit
Self explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
B. Referenced Information
3. Job Set-up
Subtask 38-31-12-860-050-A ** ON A/C NOT FOR ALL
Subtask 38-31-12-420-050-A ** ON A/C NOT FOR ALL
Subtask 38-31-12-410-050-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.01 01:20:16 UTC
Installation of the Flush Control Unit
NOTE: The procedure for the installation of the flush control unit is the same for all lavatories.
ZONE: 200
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 200 | UPPER HALF FUSELAGE |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-42-00-861-001-A | Energize the Ground Service Network from the External Power |
| TASK 24-42-00-862-001-A | De-energize the Ground Service Network Supplied from the External Power |
| TASK 25-45-22-000-001-A | Removal of the Toilet Shroud and the Seat |
| TASK 25-45-22-400-001-A | Installation of the Toilet Shroud and the Seat |
| TASK 38-31-00-710-009-A | Operational Test of the Toilet Unit |
Subtask 38-31-12-860-050-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
(1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
(2) Make sure that the lavatory door is open.
(3) Make sure that the toilet shroud is removed (Ref. AMM TASK 25-45-22-000-001).
Subtask 38-31-12-865-057-A ** ON A/C NOT FOR ALL (1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
(2) Make sure that the lavatory door is open.
(3) Make sure that the toilet shroud is removed (Ref. AMM TASK 25-45-22-000-001).
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 2001VU | VACU TOIL SYS-VACUUM-SYS | 35MG | A06 |
| ** ON A/C NOT FOR ALL | |||
| 2001VU | VACU TOIL SYS-VACUUM-GEN | 33MG | A08 |
| 2001VU | VACU TOIL SYS-LAV PWR-E | 34MG | A04 |
| 2001VU | VACU TOIL SYS-LAV PWR-D | 39MG | A03 |
| 2001VU | VACU TOIL SYS-LAV PWR-A | 32MG | A01 |
| ** ON A/C NOT FOR ALL | |||
| 2001VU | VACU TOIL SYS-LAV PWR-L | 45MG | A02 |
| ** ON A/C NOT FOR ALL | |||
| 2001VU | VACU TOIL SYS-VACU-SYS | 35MG | A06 |
| ** ON A/C NOT FOR ALL | |||
| 2001VU | VACU TOIL SYS-LAV PWR-L | 23MG | A05 |
Subtask 38-31-12-420-050-A ** ON A/C NOT FOR ALL
A. Installation of the Flush Control Unit
(1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Put the flush control unit (5) in position.
(4) Install the washers (2), the bolts (1) and the nuts (3).
(5) Remove the CAP-BLANKING from each electrical connector and receptacle.
(6) Make sure that all the electrical connections are clean and in the correct condition.
Subtask 38-31-12-710-050-A ** ON A/C NOT FOR ALL (1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Put the flush control unit (5) in position.
(4) Install the washers (2), the bolts (1) and the nuts (3).
(5) Remove the CAP-BLANKING from each electrical connector and receptacle.
(6) Make sure that all the electrical connections are clean and in the correct condition.
CAUTION:
MAKE SURE THAT ELECTRICAL CONNECTORS ARE CLEAN WHEN YOU CONNECT THEM. THE CONTAMINATION OF ELECTRICAL CONNECTORS CAN CAUSE DAMAGE TO THE EQUIPMENT.
(7) Connect the electrical connectors (4), (6), (7) and (8). B. Do an operational test of the toilet unit to make sure that it flushes correctly (Ref. AMM TASK 38-31-00-710-009).
5. Close-upSubtask 38-31-12-410-050-A ** ON A/C NOT FOR ALL
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the toilet shroud (Ref. AMM TASK 25-45-22-400-001).
(3) Close the lavatory door.
Subtask 38-31-12-862-050-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the toilet shroud (Ref. AMM TASK 25-45-22-400-001).
(3) Close the lavatory door.
Flush Control Unit