W DOC AIRBUS | AMM A320F

Installation of the Waste Box


TASK 25-45-17-400-001-A
Installation of the Waste Box


ZONE: 200
1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
200
UPPER HALF FUSELAGE
 B. Referenced Information
REFERENCE
DESIGNATION
TASK 24-42-00-861-001-A
Energize the Ground Service Network from the External Power
TASK 24-42-00-862-001-A
De-energize the Ground Service Network Supplied from the External Power
TASK 25-45-18-400-002-A
Installation of the Access Door in the Lavatory
TASK 26-25-41-400-001-A
Installation of the Fire Extinguisher Bottle
3. Job Set-up
Subtask 25-45-17-860-050-A
A. Aircraft Maintenance Configuration
   (1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
4. Procedure
Subtask 25-45-17-210-050-A
A. Preparation for Installation
   (1) Clean the component interfaces and the adjacent area.
   (2) Make sure that the parts retained from the removed component are clean and in the correct condition.
   (3) Do an inspection of the component interfaces and the adjacent area.
Subtask 25-45-17-420-050-A
B. Installation of the Waste Box
   (1) Put the waste container console (10) in position and install the screws (8) and the washers (9).
   (2) Put the waste chute (3) on the waste container console (10) and install the screws (4), the washers (5) and the nuts (6).
   (3) Install the fire extinguisher (11) (Ref. AMM TASK 26-25-41-400-001).
   (4) Install the waste container (7).
   (5) If necessary, close the access door (2) on the lavatory front wall.
   (6) Install the access door (1) inside the lavatory if removed (Ref. AMM TASK 25-45-18-400-002).
5. Close-up
Subtask 25-45-17-862-050-A
A. De-energize the ground service network
(Ref. AMM TASK 24-42-00-862-001).