Installation of the Cove Light Panel
TASK 25-23-48-400-001-A
Installation of the Cove Light Panel
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 25-23-48-860-050-A
Subtask 25-23-48-420-051-A ** ON A/C NOT FOR ALL
Subtask 25-23-48-862-050-A
[Rev.10 from 2021]
2026.03.31 23:31:59 UTC
Installation of the Cove Light Panel
ZONE: 200
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| 98A25207503000 | 1 | PULLEY ASSEMBLY - SEALING CORD |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 200 | UPPER HALF FUSELAGE |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-861-002-A-02 | Energize the Aircraft Electrical Circuits from Engine 1(2) |
| TASK 24-42-00-862-001-A | De-energize the Ground Service Network Supplied from the External Power |
Subtask 25-23-48-860-050-A
A. Aircraft Maintenance Configuration
(1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-41-00-861-002).
(2) Clean the component interfaces and the adjacent area.
(3) Do an inspection of the component interfaces and the adjacent area.
(4) Make sure that the parts retained from the removed component are clean and in the correct condition.
4. Procedure(1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-41-00-861-002).
(2) Clean the component interfaces and the adjacent area.
(3) Do an inspection of the component interfaces and the adjacent area.
(4) Make sure that the parts retained from the removed component are clean and in the correct condition.
Subtask 25-23-48-420-051-A ** ON A/C NOT FOR ALL
A. Installation of the Cove Light Panel (3)
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Engage the brackets (6) of the cove light panel (3) in the fitting (5).
(3) Connect the bonding strap (8) to the cable socket (7).
(4) Align the flange (2) with the rail (1).
(5) Engage the flange (2) on the rail (1).
(6) Make sure that the dimension 'X' is 10 +2 mm or -2 mm (0.3937 +0.0787 in. or -0.0787 in.).
(7) Install the seal (4) if removed into the rail (1). Use 98A25207503000 PULLEY ASSEMBLY - SEALING CORD.
Subtask 25-23-48-420-051-B ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Engage the brackets (6) of the cove light panel (3) in the fitting (5).
(3) Connect the bonding strap (8) to the cable socket (7).
(4) Align the flange (2) with the rail (1).
(5) Engage the flange (2) on the rail (1).
(6) Make sure that the dimension 'X' is 10 +2 mm or -2 mm (0.3937 +0.0787 in. or -0.0787 in.).
(7) Install the seal (4) if removed into the rail (1). Use 98A25207503000 PULLEY ASSEMBLY - SEALING CORD.
A. Installation of the Cove Light Panel (3)
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Engage the brackets (6) of the cove light panel (3) in the fitting (5).
(3) Align the flange (2) with the rail (1).
(4) Engage the flange (2) on the rail (1).
(5) Make sure that the dimension 'X' is 10 +2 mm or -2 mm (0.3937 +0.0787 in. or -0.0787 in.).
(6) If removed, install the seal (4) into the rail (1). Use 98A25207503000 PULLEY ASSEMBLY - SEALING CORD.
5. Close-up(1) Make sure that the work area is clean and clear of tools and other items.
(2) Engage the brackets (6) of the cove light panel (3) in the fitting (5).
(3) Align the flange (2) with the rail (1).
(4) Engage the flange (2) on the rail (1).
(5) Make sure that the dimension 'X' is 10 +2 mm or -2 mm (0.3937 +0.0787 in. or -0.0787 in.).
(6) If removed, install the seal (4) into the rail (1). Use 98A25207503000 PULLEY ASSEMBLY - SEALING CORD.
Subtask 25-23-48-862-050-A
Cove Light Panels