Installation of the Coat Stowage
TASK 25-13-46-400-001-A
Installation of the Coat Stowage
Self explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
B. Referenced Information
3. Job Set-up
Subtask 25-13-46-860-050-A
Subtask 25-13-46-420-050-A
Subtask 25-13-46-410-050-A
[Rev.10 from 2021]
2026.03.31 23:29:21 UTC
Installation of the Coat Stowage
WARNING:
BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
ZONE: 211
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 211 | COCKPIT |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-42-00-861-001-A | Energize the Ground Service Network from the External Power |
| TASK 24-42-00-862-001-A | De-energize the Ground Service Network Supplied from the External Power |
| TASK 25-13-41-400-001-A | Installation of the Ceiling Panels |
| TASK 25-13-41-400-002-A | Installation of the Sidewall Panels |
| TASK 25-13-46-000-001-A | Removal of the Coat Stowage |
Subtask 25-13-46-860-050-A
A. Aircraft Maintenance Configuration
(1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
(2) Make sure that the removal task is completed before you do the installation task (Ref. AMM TASK 25-13-46-000-001).
4. Procedure(1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
(2) Make sure that the removal task is completed before you do the installation task (Ref. AMM TASK 25-13-46-000-001).
Subtask 25-13-46-420-050-A
A. Installation of the Coat Stowage
(1) Put the panel (15) in position and install the washers (3) and the bolts (2).
(2) Tighten the bolts (2).
(3) Put the panel (11) in position and install the washers (4) and the bolts (5).
(4) Tighten the bolts (5).
(5) Put the covers (8) and (10) in position and install the screws (9).
(6) Tighten the screws (9).
(7) Put the panel (12) in position and install the washers (7), the bolt (1) and (6) and the screws (13) and (14).
(8) Tighten the bolts (1) and (6) and the screws (13) and (14).
(9) Put the bar (17) in position and install the setscrews (16).
(10) Tighten the setscrews (16).
5. Close-up(1) Put the panel (15) in position and install the washers (3) and the bolts (2).
(2) Tighten the bolts (2).
(3) Put the panel (11) in position and install the washers (4) and the bolts (5).
(4) Tighten the bolts (5).
(5) Put the covers (8) and (10) in position and install the screws (9).
(6) Tighten the screws (9).
(7) Put the panel (12) in position and install the washers (7), the bolt (1) and (6) and the screws (13) and (14).
(8) Tighten the bolts (1) and (6) and the screws (13) and (14).
(9) Put the bar (17) in position and install the setscrews (16).
(10) Tighten the setscrews (16).
Subtask 25-13-46-410-050-A
A. Close Access
(1) If removed, install the ceiling panels (Ref. AMM TASK 25-13-41-400-001).
(2) If removed, install the sidewall panels (Ref. AMM TASK 25-13-41-400-002).
(3) Make sure that the work area is clean and clear of tools and other items.
Subtask 25-13-46-862-050-A (1) If removed, install the ceiling panels (Ref. AMM TASK 25-13-41-400-001).
(2) If removed, install the sidewall panels (Ref. AMM TASK 25-13-41-400-002).
(3) Make sure that the work area is clean and clear of tools and other items.
Coat Stowage