Installation of the Ceiling Panels
TASK 25-13-41-400-001-A
Installation of the Ceiling Panels
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
B. Referenced Information
3. Job Set-up
Subtask 25-13-41-865-051-A
Subtask 25-13-41-420-050-A
Subtask 25-13-41-865-052-A
[Rev.10 from 2021]
2026.03.31 23:29:01 UTC
Installation of the Ceiling Panels
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 211 | COCKPIT |
| 212 | COCKPIT |
| REFERENCE | DESIGNATION |
|---|---|
Subtask 25-13-41-865-051-A
A. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 49VU | LIGHTING/EMER LT/CKPT/DOME | 1LE | H08 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | LIGHTING/EMER LT/CKPT/DOME | 1LE | H06 |
| ** ON A/C ALL | |||
| 122VU | LIGHTING/CKPT/DOME | 3LE | Y06 |
Subtask 25-13-41-420-050-A
A. Installation of the Ceiling Panels
(1) Put the panel (3) in position.
(2) Install and tighten the screws (2) on the panel (3).
(3) Lock the fasteners (1) on the panel (3).
(4) Engage the emergency descent device in the panel (4).
(5) Put the panel (4) in position.
(6) Install and tighten the screws (2) on the panel (4).
(7) Lock the fasteners (1) on the panel (4).
(8) Put the panel (5) in position.
(9) Install and tighten the screws (2) on the panel (5).
(10) Lock the fasteners (1) on the panel (5).
(11) Put the panel (6) in position.
(12) Install and tighten the screws (2) on the panel (6).
(13) Lock the fasteners (1) on the panel (6).
(14) Install the panel (7).
(15) Put the panel (8) in position.
(16) Install and tighten the screws (2) on the panel (8).
(17) Lock the fasteners (1) on the panel (8).
(18) Put the panel (9) in position.
(19) Install and tighten the screws (2) on the panel (9).
(20) Lock the fasteners (1) on the panel (9).
(21) Put the panel (10) in position.
(22) Install and tighten the screws (2) on the panel (10).
(23) Lock the fasteners (1) on the panel (10).
(24) Put the panel (11) in position and push it to engage the clip (12).
5. Close-up(1) Put the panel (3) in position.
(2) Install and tighten the screws (2) on the panel (3).
(3) Lock the fasteners (1) on the panel (3).
(4) Engage the emergency descent device in the panel (4).
(5) Put the panel (4) in position.
(6) Install and tighten the screws (2) on the panel (4).
(7) Lock the fasteners (1) on the panel (4).
(8) Put the panel (5) in position.
(9) Install and tighten the screws (2) on the panel (5).
(10) Lock the fasteners (1) on the panel (5).
(11) Put the panel (6) in position.
(12) Install and tighten the screws (2) on the panel (6).
(13) Lock the fasteners (1) on the panel (6).
(14) Install the panel (7).
(15) Put the panel (8) in position.
(16) Install and tighten the screws (2) on the panel (8).
(17) Lock the fasteners (1) on the panel (8).
(18) Put the panel (9) in position.
(19) Install and tighten the screws (2) on the panel (9).
(20) Lock the fasteners (1) on the panel (9).
(21) Put the panel (10) in position.
(22) Install and tighten the screws (2) on the panel (10).
(23) Lock the fasteners (1) on the panel (10).
(24) Put the panel (11) in position and push it to engage the clip (12).
Subtask 25-13-41-865-052-A
A. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 25-13-41-942-050-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 49VU | LIGHTING/EMER LT/CKPT/DOME | 1LE | H08 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | LIGHTING/EMER LT/CKPT/DOME | 1LE | H06 |
| ** ON A/C ALL | |||
| 122VU | LIGHTING/CKPT/DOME | 3LE | Y06 |
B. Make sure that the work area is clean and clear of tools and other items.
Ceiling Panels