1. Reason for the Job
Refer to the MPD TASK: ZL-133-01
GENERAL VISUAL INSPECTION OF UNDERFLOOR BAY OF FWD CARGO COMPARTMENT (EWIS)
NOTE: This is an EWIS (Electrical Wiring Interconnection System) procedure. EWIS is defined in ESPM 20-33-11.
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
AR
ACCESS PLATFORM 2M (6 FT)
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
133
BAY UNDER FWD CAR COMPT FLOOR
134
BAY UNDER FWD CAR COMPT FLOOR
133AL, 134AR, 825
 C. Referenced Information
REFERENCE
DESIGNATION
TASK 52-30-00-860-001-A
Open the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump
TASK 52-30-00-860-002-A
Close the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump
TASK 53-22-14-000-001-A
Removal of the Forward Cargo-Compartment Floor-Panels
TASK 53-22-14-000-002-A
Removal of the Maintenance Panels at Frame 35.5
TASK 53-22-14-400-001-A
Installation of the Forward Cargo-Compartment Floor-Panels
TASK 53-22-14-400-001-A-01
Installation of the Forward Cargo-Compartment Floor-Panels (Alternative Installation Procedure with the Skyflex Option)
TASK 53-22-14-400-002-A
Installation of the Maintenance Panels at Frame 35.5
TASK 06-41-53-00
FUSELAGE-DESCRIPTION AND OPERATION
3. Job Set-up
Subtask 05-21-30-010-051-A ** ON A/C NOT FOR ALL
A. Get Access
   (1) Put the ACCESS PLATFORM 2M (6 FT) in position at zones 133 and 134.
   (2) Open access doors 133AL and 134AR.
   (3) Open forward cargo-compartment door 825 (Ref. AMM TASK 52-30-00-860-001).
   (4) Remove the floor panels in the forward cargo compartment between FR24 and FR34 (Ref. AMM TASK 53-22-14-000-001) (For access location see (Ref. AMM D/O 06-41-53-00) zone 133-134).
   (5) If installed, remove the Additional Center Tank (ACT) (Ref. AMM TASK 28-11-27-000-007).
Subtask 05-21-30-010-051-C ** ON A/C NOT FOR ALL
A. Get Access
   (1) Put the ACCESS PLATFORM 2M (6 FT) in position at zones 133 and 134.
   (2) Open access doors 133AL and 134AR.
   (3) Open forward cargo-compartment door 825 (Ref. AMM TASK 52-30-00-860-001).
   (4) Remove the floor panels in the forward cargo compartment between FR24 and FR35.7 (Ref. AMM TASK 53-22-14-000-001) (For access location see (Ref. AMM D/O 06-41-53-00) zone 133-134).
   (5) Remove the maintenance floor panels between FR35.5 and FR35.7 (Ref. AMM TASK 53-22-14-000-002).
4. Procedure
Subtask 05-21-30-210-051-A
A. Inspection
   (1) Do a general visual inspection of the underfloor bay of the forward cargo compartment.
   (2) Make sure that there are no signs of corrosion, cracks or damage.
   (3) Make sure that all the installations (wiring, ducting, piping) are attached correctly.
5. Close-up
Subtask 05-21-30-410-051-A ** ON A/C NOT FOR ALL
A. Close Access
   (1) If removed, install the ACT (Ref. AMM TASK 28-11-27-400-005).
   (2) Install the floor panels in the forward cargo compartment between FR24 and FR34 (Ref. AMM TASK 53-22-14-400-001) (For access location see (Ref. AMM D/O 06-41-53-00) zone 133-134).
   (3) Close forward cargo-compartment door 825 (Ref. AMM TASK 52-30-00-860-002).
   (4) Close access doors 133AL and 134AR.
   (5) Remove the access platform(s).
Subtask 05-21-30-410-051-C ** ON A/C NOT FOR ALL
A. Close Access
   (1) Install the maintenance floor panels between FR35.5 and FR35.7 (Ref. AMM TASK 53-22-14-400-002).
   (2) Install the floor panels in the forward cargo compartment between FR24 and FR35.7 (Ref. AMM TASK 53-22-14-400-001) (For access location see (Ref. AMM D/O 06-41-53-00) zone 133-134).
   (3) Close forward cargo-compartment door 825 (Ref. AMM TASK 52-30-00-860-002).
   (4) Close access doors 133AL and 134AR.
   (5) Remove the access platform(s).