FIN: (1146GM) GRND SERV MANIFOLD
Zone: 146
AMM TASK
- MANIFOLD - GROUND LEAKAGE MEASUREMENT
-
29-19-41-000-001-A
Removal of the Ground Leakage-Measurement Manifold of the Green Hydraulic System -
29-19-41-400-001-A
Installation of the Ground Leakage-Measurement Manifold of the Green Hydraulic System -
29-19-41-000-002-A
Removal of the Ground Leakage-Measurement Manifold of the Blue Hydraulic System -
29-19-41-400-002-A
Installation of the Ground Leakage-Measurement Manifold of the Blue Hydraulic System -
29-19-41-000-003-A
Removal of the Ground Leakage-Measurement Manifold of the Yellow Hydraulic System -
29-19-41-400-003-A
Installation of the Ground Leakage-Measurement Manifold of the Yellow Hydraulic System
-
29-19-41-000-001-A