1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 26-23-25-861-050-A ** ON A/C NOT FOR ALL
Subtask 26-23-25-020-051-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.03.31 23:46:20 UTC
Removal of the Diaphragm in the Aft Cargo Compartment
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | AR | ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE |
| No specific | AR | ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE |
| No specific | AR | PLUG - BLANKING |
| No specific | AR | SAFETY CLIP - CIRCUIT BREAKER |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 150 | AFT CARGO COMPARTMENT FWD PRESS BULKHEAD TO AFT BULKHEAD OF AFT CARGO COMPARTMENT |
| 160 | BULK CARGO COMPARTMENT AFT BULKHEAD OF AFT CARGO COMPARTMENT TO AFT BULKHEAD OF BULK CARGO COMPARTMENT |
| 170 | AFT CAB U/FLOOR COMPT AFT BHD OF BULK |
| 161DW, 811, 826 |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-42-00-861-001-A | Energize the Ground Service Network from the External Power |
| TASK 25-55-12-000-001-A | Removal of the Aft Cargo-Compartment Partition at FR65 |
| TASK 52-30-00-860-001-A | Open the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump |
| TASK 52-41-00-010-002-A | Open the Avionics Compartment Doors for Access |
Subtask 26-23-25-861-050-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
(1) Energize the ground service network
(Ref. AMM TASK 24-42-00-861-001).
Subtask 26-23-25-010-052-A ** ON A/C NOT FOR ALL (1) Energize the ground service network
(Ref. AMM TASK 24-42-00-861-001).
B. Get access to the avionics compartment.
(1) Put the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE in position below the access door 811.
(2) Open the access door 811 (Ref. AMM TASK 52-41-00-010-002).
Subtask 26-23-25-865-053-A ** ON A/C NOT FOR ALL (1) Put the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE in position below the access door 811.
(2) Open the access door 811 (Ref. AMM TASK 52-41-00-010-002).
C. Open, safety and tag this(these) circuit breaker(s):
Subtask 26-23-25-010-053-C ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 49VU | AIR COND/CARGO FIRE/EXTIG/BTL2 | 8WX | C04 |
| 49VU | AIR COND/CARGO FIRE/EXTIG/BTL1 | 1WX | C03 |
D. Get Access
(1) Put the ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE in position below the aft cargo-compartment door 826.
(2) Open the aft cargo-compartment door 826 (Ref. AMM TASK 52-30-00-860-001).
(3) Set the CARGO COMPT LIGHT switch 8LU to the ON position.
(4) Remove the partition panel 161DW (Ref. AMM TASK 25-55-12-000-001).
4. Procedure(1) Put the ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE in position below the aft cargo-compartment door 826.
(2) Open the aft cargo-compartment door 826 (Ref. AMM TASK 52-30-00-860-001).
(3) Set the CARGO COMPT LIGHT switch 8LU to the ON position.
(4) Remove the partition panel 161DW (Ref. AMM TASK 25-55-12-000-001).
Subtask 26-23-25-020-051-A ** ON A/C NOT FOR ALL
A. Removal of the Diaphragm
(1) Hold the diaphragm (3) and loosen the nuts (2).
(2) Carefully disconnect the pipes (1) from the diaphragm (3).
(3) Remove the diaphragm (3).
(4) Put the PLUG-BLANKING in each disconnected line end.
(1) Hold the diaphragm (3) and loosen the nuts (2).
(2) Carefully disconnect the pipes (1) from the diaphragm (3).
(3) Remove the diaphragm (3).
(4) Put the PLUG-BLANKING in each disconnected line end.