Installation of the Lining
TASK 25-45-26-400-001-A
Installation of the Lining
Self explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
B. Referenced Information
3. Job Set-up
Subtask 25-45-26-860-050-A
Subtask 25-45-26-210-050-A
Subtask 25-45-26-410-050-A
[Rev.10 from 2021]
2026.04.01 06:17:00 UTC
Installation of the Lining
ZONE: 200
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 200 | UPPER HALF FUSELAGE |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-42-00-861-001-A | Energize the Ground Service Network from the External Power |
| TASK 24-42-00-862-001-A | De-energize the Ground Service Network Supplied from the External Power |
| TASK 25-45-38-000-001-A | Removal of the Washbasin |
| TASK 25-45-38-400-001-A | Installation of the Washbasin |
Subtask 25-45-26-860-050-A
A. Aircraft Maintenance Configuration
(1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
(2) Make sure that the washbasin is removed (Ref. AMM TASK 25-45-38-000-001) or (Ref. AMM D/O 38-32-43-00).
4. Procedure(1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
(2) Make sure that the washbasin is removed (Ref. AMM TASK 25-45-38-000-001) or (Ref. AMM D/O 38-32-43-00).
Subtask 25-45-26-210-050-A
A. Preparation for Installation
(1) Clean the component interfaces and the adjacent area.
(2) Make sure that the parts retained from the removed component are clean and in the correct condition.
(3) Do an inspection of the component interfaces and the adjacent area.
Subtask 25-45-26-420-050-B (1) Clean the component interfaces and the adjacent area.
(2) Make sure that the parts retained from the removed component are clean and in the correct condition.
(3) Do an inspection of the component interfaces and the adjacent area.
B. Installation of the Lining
(1) Do an inspection of the component interfaces and the adjacent area.
(2) Put the lining (1) in position and install the washers (3) and the screws (2).
(3) Install the roller bracket (4).
(4) Install the rollers (5) on the roller bracket (4).
5. Close-up(1) Do an inspection of the component interfaces and the adjacent area.
(2) Put the lining (1) in position and install the washers (3) and the screws (2).
(3) Install the roller bracket (4).
(4) Install the rollers (5) on the roller bracket (4).
Subtask 25-45-26-410-050-A
A. Close Access
(1) If the washbasin is removed, install it (Ref. AMM TASK 25-45-38-400-001) or (Ref. AMM D/O 38-32-43-40).
Subtask 25-45-26-862-050-A (1) If the washbasin is removed, install it (Ref. AMM TASK 25-45-38-400-001) or (Ref. AMM D/O 38-32-43-40).
Wash Basin Lining