General Visual Inspection of EWIS Installed in the Upper Forward Pylon (EWIS)
TASK 24-92-00-210-818-A
General Visual Inspection of EWIS Installed in the Upper Forward Pylon (EWIS)
1. Reason for the Job
Refer to the MPD TASK: 200413-04
GENERAL VISUAL INSPECTION OF EWIS INSTALLED IN THE UPPER FORWARD PYLON (EWIS)
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 24-92-00-941-072-A ** ON A/C NOT FOR ALL
Subtask 24-92-00-210-123-A ** ON A/C NOT FOR ALL
Subtask 24-92-00-410-192-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.03.31 23:26:46 UTC
General Visual Inspection of EWIS Installed in the Upper Forward Pylon (EWIS)
1. Reason for the Job
Refer to the MPD TASK: 200413-04
GENERAL VISUAL INSPECTION OF EWIS INSTALLED IN THE UPPER FORWARD PYLON (EWIS)
NOTE: This is an EWIS (Electrical Wiring Interconnection System) procedure. For the EWIS refer to ESPM 20-33-11.
2. Job Set-up InformationA. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE |
| No specific | AR | FLASHLIGHT |
| No specific | AR | MIRROR - INSPECTION, FLEXIBLE |
| No specific | AR | WARNING NOTICE(S) |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 413 | UPPER FWD PYLON |
| 414 | UPPER FWD PYLON |
| 423 | UPPER FWD PYLON |
| 424 | UPPER FWD PYLON |
| FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENG 1) | |
| 413AT, 414AR, 414BR, 414CR | |
| FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENG 2) | |
| 423AT, 424AR, 424BR, 424CR, 424DR | |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-41-00-862-002-A | De-energize the Aircraft Electrical Circuits Supplied from the External Power |
| TASK 24-41-00-862-002-A-01 | De-energize the Aircraft Electrical Circuits Supplied from the APU |
| TASK 24-41-00-862-002-A-02 | De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2) |
| TASK 54-52-11-000-805-A | Removal of the Access Skin Panels |
| TASK 54-52-11-400-805-A | Installation of the Access Skin Panels |
| ESPM 2052120 | |
Subtask 24-92-00-941-072-A ** ON A/C NOT FOR ALL
A. Safety Precautions
(1) On the center pedestal, on ENG panel 115VU:
(a) Make sure that the ENG/MODE selector switch is in the NORM position.
(b) Make sure that the ENG/MASTER 1(2) control switch was in the OFF position not less than five minutes before you do this procedure.
(c) Put WARNING NOTICE(S) in position to tell persons not to operate the ENG/MODE selector switch and the ENG/MASTER 1(2) control switch.
(2) On the ENG section of maintenance panel 50VU:
(a) Make sure that the ON legend of the FADEC GND PWR/1(2) pushbutton switch is off.
(b) Put WARNING NOTICE(S) in position to tell persons not to energize FADEC 1(2).
Subtask 24-92-00-862-160-A ** ON A/C NOT FOR ALL (1) On the center pedestal, on ENG panel 115VU:
(a) Make sure that the ENG/MODE selector switch is in the NORM position.
(b) Make sure that the ENG/MASTER 1(2) control switch was in the OFF position not less than five minutes before you do this procedure.
(c) Put WARNING NOTICE(S) in position to tell persons not to operate the ENG/MODE selector switch and the ENG/MASTER 1(2) control switch.
(2) On the ENG section of maintenance panel 50VU:
(a) Make sure that the ON legend of the FADEC GND PWR/1(2) pushbutton switch is off.
(b) Put WARNING NOTICE(S) in position to tell persons not to energize FADEC 1(2).
B. Make sure that the aircraft electrical circuits are de-energized
(Ref. AMM TASK 24-41-00-862-002).
Subtask 24-92-00-010-184-A ** ON A/C NOT FOR ALL (Ref. AMM TASK 24-41-00-862-002).
C. Get Access
(1) Put an ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE in position at the upper forward pylon.
(2) Remove the access skin panels (Ref. AMM TASK 54-52-11-000-805):
(a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENG 1)
413AT 414AR 414BR 414CR.
(b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENG 2)
423AT 424AR 424BR 424CR 424DR.
4. Procedure(1) Put an ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE in position at the upper forward pylon.
(2) Remove the access skin panels (Ref. AMM TASK 54-52-11-000-805):
(a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENG 1)
413AT 414AR 414BR 414CR.
(b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENG 2)
423AT 424AR 424BR 424CR 424DR.
Subtask 24-92-00-210-123-A ** ON A/C NOT FOR ALL
A. General Visual Inspection of all Wiring Installed in the Upper Forward Pylon
(1) Do a visual inspection of the wiring to make sure that there is no signs of ageing, alteration, overheating, scaling and deformation ESPM 2052120:
(a) On the AC/DC feeder routes 1G and 2G.
(b) On the engine control routes 1S and 2S.
(c) On the routes 1M and 2M.
(d) On the generator excitation routes: 1E and 2E.
5. Close-up(1) Do a visual inspection of the wiring to make sure that there is no signs of ageing, alteration, overheating, scaling and deformation ESPM 2052120:
(a) On the AC/DC feeder routes 1G and 2G.
(b) On the engine control routes 1S and 2S.
(c) On the routes 1M and 2M.
(d) On the generator excitation routes: 1E and 2E.
NOTE: Use a FLASHLIGHT or a MIRROR - INSPECTION, FLEXIBLE, if necessary.
(2) Make sure that there is no hydraulic, dust or fuel contamination. Subtask 24-92-00-410-192-A ** ON A/C NOT FOR ALL
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the access skin panels (Ref. AMM TASK 54-52-11-400-805):
(a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENG 1)
413AT 414AR 414BR 414CR.
(b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENG 2)
423AT 424AR 424BR 424CR 424DR.
(3) Remove the access platform(s).
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the access skin panels (Ref. AMM TASK 54-52-11-400-805):
(a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENG 1)
413AT 414AR 414BR 414CR.
(b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENG 2)
423AT 424AR 424BR 424CR 424DR.
(3) Remove the access platform(s).
Upper Forward Pylon - Inspection Area - Zones 413-414-423-424