General Visual Inspection of Shroud Box (EWIS)
TASK 05-25-70-200-002-A
General Visual Inspection of Shroud Box (EWIS)
Refer to the MPD TASK: ZL-572-01
GENERAL VISUAL INSPECTION OF SHROUD BOX (EWIS)
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 05-25-70-866-050-A Subtask 05-25-70-010-051-B
Subtask 05-25-70-210-051-A
Subtask 05-25-70-410-051-B
[Rev.10 from 2021]
2026.03.31 22:50:30 UTC
General Visual Inspection of Shroud Box (EWIS)
WARNING:
DO NOT EXTEND THE SLATS AND FLAPS WHEN THE THRUST REVERSER COWLS ARE DEPLOYED IN THE 45 DEG. POSITION.
1. Reason for the JobRefer to the MPD TASK: ZL-572-01
GENERAL VISUAL INSPECTION OF SHROUD BOX (EWIS)
NOTE: This is an EWIS (Electrical Wiring Interconnection System) procedure. EWIS is defined in ESPM 20-33-11.
2. Job Set-up InformationA. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 2M (6 FT) |
| No specific | 1 | FLASHLIGHT |
| No specific | 1 | MIRROR - INSPECTION, FLEXIBLE |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 572 | SHROUD BOX STA 0 TO STA 1800 |
| 672 | SHROUD BOX STA 0 TO STA 1800 |
| 571AB, 671AB |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 27-50-00-866-008-A | Extension of the Flaps on the Ground |
| TASK 27-50-00-866-008-A-01 | Extension of the Flaps/Slats on the Ground |
| TASK 27-50-00-866-009-A | Retraction of the Flaps on the Ground |
| TASK 27-50-00-866-009-A-01 | Retraction of the Flaps/Slats on the Ground |
| TASK 57-51-37-000-002-A | Removal of the Access Panels 571AB(671AB), 573AB(673AB), 573BB(673BB), 573CB(673CB), 573EB(673EB) |
| TASK 57-51-37-400-002-A | Installation of the Access Panels 571AB(671AB), 573AB(673AB), 573BB(673BB), 573CB(673CB), 573EB(673EB) |
Subtask 05-25-70-866-050-A Subtask 05-25-70-010-051-B
B. Get Access
(1) Put the ACCESS PLATFORM 2M (6 FT) in position.
(2) Remove access panel 571AB ( 671AB) (Ref. AMM TASK 57-51-37-000-002).
4. Procedure(1) Put the ACCESS PLATFORM 2M (6 FT) in position.
(2) Remove access panel 571AB ( 671AB) (Ref. AMM TASK 57-51-37-000-002).
Subtask 05-25-70-210-051-A
A. Inspection
(1) Do a general visual inspection of the shroud box (zones 572 and 672) with the FLASHLIGHT and the MIRROR - INSPECTION, FLEXIBLE .
(2) Make sure that there are no signs of corrosion, cracks or damage on all the parts of the components and the structure that you can see.
(3) Make sure that all the installations (wiring and piping) are correctly attached.
5. Close-up(1) Do a general visual inspection of the shroud box (zones 572 and 672) with the FLASHLIGHT and the MIRROR - INSPECTION, FLEXIBLE .
(2) Make sure that there are no signs of corrosion, cracks or damage on all the parts of the components and the structure that you can see.
(3) Make sure that all the installations (wiring and piping) are correctly attached.
Subtask 05-25-70-410-051-B
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install access panel 571AB ( 671AB) (Ref. AMM TASK 57-51-37-400-002).
(3) Remove the access platform(s).
Subtask 05-25-70-866-051-A (1) Make sure that the work area is clean and clear of tools and other items.
(2) Install access panel 571AB ( 671AB) (Ref. AMM TASK 57-51-37-400-002).
(3) Remove the access platform(s).
Shroud Box