GENERAL VISUAL INSPECTION OF ELEVATOR (EWIS)
TASK 05-23-30-200-005-A
GENERAL VISUAL INSPECTION OF ELEVATOR (EWIS)
1. Reason for the Job
Refer to the MPD TASK: ZL-335-01
GENERAL VISUAL INSPECTION OF ELEVATOR (EWIS)
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 05-23-30-010-054-A
Subtask 05-23-30-210-054-A
Subtask 05-23-30-410-054-A
[Rev.10 from 2021]
2026.03.31 22:49:45 UTC
GENERAL VISUAL INSPECTION OF ELEVATOR (EWIS)
1. Reason for the Job
Refer to the MPD TASK: ZL-335-01
GENERAL VISUAL INSPECTION OF ELEVATOR (EWIS)
NOTE: This is an EWIS (Electrical Wiring Interconnection System) procedure. EWIS is defined in ESPM 20-33-11.
2. Job Set-up InformationA. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | AR | ACCESS PLATFORM 3M (10 FT) |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 335 | ELEVATOR |
| 345 | ELEVATOR |
| 334BB, 334DB, 334FB, 334HB, 335AB, 335BB, 335CB, 335DB, 344BB, 344DB, 344FB, 344HB, 345AB, 345BB, 345CB, 345DB |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 55-13-11-000-001-A | Remove/Open of the Trimmable Horizontal Stabilizer (THS) Trailing-Edge Access-Panels |
| TASK 55-13-11-400-001-A | Install/Close of the Trimmable Horizontal Stabilizer (THS) Trailing-Edge Access-Panels |
| TASK 55-22-11-000-001-A | Removal of the Elevator Leading Edge Access Panels 335AB (345AB), 335BB (345BB), 335CB (345CB), 335DB (345DB). |
| TASK 55-22-11-400-001-A | Installation of the Elevator Leading Edge Access Panels 335AB (345AB), 335BB (345BB), 335CB (345CB), 335DB (345DB). |
Subtask 05-23-30-010-054-A
A. Get Access
(1) Put an ACCESS PLATFORM 3M (10 FT) in position.
(2) Remove the trailing edge access panels:
334BB 334DB 334FB, 334HB.
344BB 344DB 344FB, 344HB.
(Ref. AMM TASK 55-13-11-000-001)
(3) Remove the elevator leading edge access panels
335AB 335BB, 335CB 335DB.
345AB 345BB, 345CB 345DB.
(Ref. AMM TASK 55-22-11-000-001)
4. Procedure(1) Put an ACCESS PLATFORM 3M (10 FT) in position.
(2) Remove the trailing edge access panels:
334BB 334DB 334FB, 334HB.
344BB 344DB 344FB, 344HB.
(Ref. AMM TASK 55-13-11-000-001)
(3) Remove the elevator leading edge access panels
335AB 335BB, 335CB 335DB.
345AB 345BB, 345CB 345DB.
(Ref. AMM TASK 55-22-11-000-001)
Subtask 05-23-30-210-054-A
A. Inspection
(1) Do a general visual inspection of the elevator.
(2) Make sure that there are no signs of corrosion, cracks or damage.
(3) Make sure that all the installations (wiring, ducting, piping) are attached correctly.
5. Close-up(1) Do a general visual inspection of the elevator.
(2) Make sure that there are no signs of corrosion, cracks or damage.
(3) Make sure that all the installations (wiring, ducting, piping) are attached correctly.
Subtask 05-23-30-410-054-A
A. Close Access
(1) Install the trailing edge access panels
334BB 334DB 334FB, 334HB.
344BB 344DB 344FB, 344HB.
(Ref. AMM TASK 55-13-11-400-001)
(2) Install the elevator leading edge access panels
335AB 335BB, 335CB 335DB.
345AB 345BB, 345CB 345DB.
(Ref. AMM TASK 55-22-11-400-001)
(3) Remove the access platform(s).
(1) Install the trailing edge access panels
334BB 334DB 334FB, 334HB.
344BB 344DB 344FB, 344HB.
(Ref. AMM TASK 55-13-11-400-001)
(2) Install the elevator leading edge access panels
335AB 335BB, 335CB 335DB.
345AB 345BB, 345CB 345DB.
(Ref. AMM TASK 55-22-11-400-001)
(3) Remove the access platform(s).