Installation of the Protective Cover of the Forestay Bearing
TASK 32-21-24-400-803-A
Installation of the Protective Cover of the Forestay Bearing
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Consumable Materials
C. Work Zones and Access Panels
D. Expendable Parts
E. Referenced Information
3. Job Set-up
Subtask 32-21-24-010-058-A
Subtask 32-21-24-110-053-A
Subtask 32-21-24-410-055-A
[Rev.10 from 2021]
2026.04.01 00:42:32 UTC
Installation of the Protective Cover of the Forestay Bearing
WARNING:
MAKE SURE THAT THE GROUND SAFETY-LOCKS ARE IN POSITION ON THE LANDING GEAR. THIS WILL PREVENT UNWANTED MOVEMENT OF THE LANDING GEAR, AND THUS POSSIBLE INJURY TO PERSONS AND DAMAGE TO THE AIRCRAFT AND/OR EQUIPMENT.
WARNING:
BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE |
| No specific | 1 | BLOWING EQUIPMENT - DRY AIR |
| REFERENCE | DESIGNATION |
|---|---|
| (Material No.03GBC1) | Synthetic Oil base Grease-General Purpose Lithium Thickened Low Temp. - |
| (Material No.03GBD1) | Synthetic Oil base Grease-General Purpose Lithium Thickened - |
| (Material No.06LCG9) | Non Hardening Jointing Putty-Medium Temp. Area - - |
| (Material No.08BBB1) | Non Aqueous Cleaner-- Petroleum Based - |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 812, 822 |
| FIG.ITEM | DESIGNATION | IPC-CSN |
|---|---|---|
| 2 | COTTER PINS | AIPC 32-21-01-01-010 |
| 5 | COTTER PINS | AIPC 32-21-01-01-010 |
| 2 | O-RINGS | AIPC 32-21-01-01-060 |
| 5 | O-RINGS | AIPC 32-21-01-01-060 |
| 1 | O-RING | AIPC 32-21-01-01-075 |
| 4 | O-RING | AIPC 32-21-01-01-075 |
| 2 | COTTER PINS | AIPC 32-21-81-01-060 |
| 5 | COTTER PINS | AIPC 32-21-81-01-060 |
| 2 | O-RINGS | AIPC 32-21-81-01-100 |
| 5 | O-RINGS | AIPC 32-21-81-01-100 |
| 1 | O-RING | AIPC 32-21-81-01-120 |
| 4 | O-RING | AIPC 32-21-81-01-120 |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 07-11-00-581-003-A | Lifting of the Aircraft at the Forward Jacking Point, MLG Wheels on the Ground |
| TASK 07-11-00-586-001-A | Lowering of the Aircraft at Forward Jacking Point, MLG Wheels on the Ground |
Subtask 32-21-24-010-058-A
A. Get Access
(1) Make sure that the aircraft is lifted on jacks at the forward jacking point (Ref. AMM TASK 07-11-00-581-003).
(2) Make sure that access doors 812 and 822 are open.
(3) Make sure that the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE is in position in zone 123.
4. Procedure(1) Make sure that the aircraft is lifted on jacks at the forward jacking point (Ref. AMM TASK 07-11-00-581-003).
(2) Make sure that access doors 812 and 822 are open.
(3) Make sure that the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE is in position in zone 123.
Subtask 32-21-24-110-053-A
A. Preparation for Installation
(1) Clean all the components with Non Aqueous Cleaner-- Petroleum Based - (Material No.08BBB1) .
(2) Dry the components with BLOWING EQUIPMENT - DRY AIR.
Subtask 32-21-24-420-056-A ** ON A/C NOT FOR ALL (1) Clean all the components with Non Aqueous Cleaner-- Petroleum Based - (Material No.08BBB1) .
(2) Dry the components with BLOWING EQUIPMENT - DRY AIR.
B. Installation of the Protective Cover of the Forestay Bearing
(1) Apply a thin layer of Synthetic Oil base Grease-General Purpose Lithium Thickened Low Temp. - (Material No.03GBC1) or Synthetic Oil base Grease-General Purpose Lithium Thickened - (Material No.03GBD1) on the new AIPC 32-21-01-01-075 O-RING (1) or AIPC 32-21-81-01-120 O-RING (1) and the new AIPC 32-21-01-01-060 O-RINGS (2) or AIPC 32-21-81-01-100 O-RINGS (2).
(2) Install the O-rings (1) and (2) on the protective cover (3).
(3) Install the protective cover (3)
(4) Install the washers (4) and nuts (6).
(5) Tighten the nuts (6).
(7) Do a visual inspection of the swivel bearing from the inside of the nose gear compartment to:
Subtask 32-21-24-420-056-B ** ON A/C NOT FOR ALL (1) Apply a thin layer of Synthetic Oil base Grease-General Purpose Lithium Thickened Low Temp. - (Material No.03GBC1) or Synthetic Oil base Grease-General Purpose Lithium Thickened - (Material No.03GBD1) on the new AIPC 32-21-01-01-075 O-RING (1) or AIPC 32-21-81-01-120 O-RING (1) and the new AIPC 32-21-01-01-060 O-RINGS (2) or AIPC 32-21-81-01-100 O-RINGS (2).
(2) Install the O-rings (1) and (2) on the protective cover (3).
(3) Install the protective cover (3)
(4) Install the washers (4) and nuts (6).
(5) Tighten the nuts (6).
WARNING:
USE PROTECTIVE GOGGLES WHEN YOU REMOVE OR INSTALL A COTTER PIN. EACH TIME YOU REMOVE A COTTER PIN DURING THE TASK, DISCARD IT IMMEDIATELY. A LOOSE COTTER PIN CAN CUT YOU OR MAKE YOU BLIND.
(6) Safety the nuts (6) with the new AIPC 32-21-01-01-010 COTTER PINS (5) or AIPC 32-21-81-01-060 COTTER PINS (5).(7) Do a visual inspection of the swivel bearing from the inside of the nose gear compartment to:
- Make sure that it is correctly installed against the airframe panel, with no space between them.
B. Installation of the Protective Cover of the Forestay Bearing
(1) Apply a thin layer of Synthetic Oil base Grease-General Purpose Lithium Thickened Low Temp. - (Material No.03GBC1) or Synthetic Oil base Grease-General Purpose Lithium Thickened - (Material No.03GBD1) on the new AIPC 32-21-01-01-075 O-RING (4) or AIPC 32-21-81-01-120 O-RING (4) and the new AIPC 32-21-01-01-060 O-RINGS (5) or AIPC 32-21-81-01-100 O-RINGS (5).
(2) Install the O-rings (4) and (5) on the protective cover (6).
(3) Apply a thin layer of Non Hardening Jointing Putty-Medium Temp. Area - - (Material No.06LCG9) to the bolts (7).
(4) If you cannot install one or more bolts (7) because of the load on the forestay, manually push the NLG wheels forward to release the load.
(7) Install the remaining bolt (7) through the protective cover (6), and install the washers (3) and nuts (1).
(8) Tighten the nuts (1).
(10) Do a visual inspection of the swivel bearing from the inside of the nose gear compartment to:
5. Close-up(1) Apply a thin layer of Synthetic Oil base Grease-General Purpose Lithium Thickened Low Temp. - (Material No.03GBC1) or Synthetic Oil base Grease-General Purpose Lithium Thickened - (Material No.03GBD1) on the new AIPC 32-21-01-01-075 O-RING (4) or AIPC 32-21-81-01-120 O-RING (4) and the new AIPC 32-21-01-01-060 O-RINGS (5) or AIPC 32-21-81-01-100 O-RINGS (5).
(2) Install the O-rings (4) and (5) on the protective cover (6).
(3) Apply a thin layer of Non Hardening Jointing Putty-Medium Temp. Area - - (Material No.06LCG9) to the bolts (7).
(4) If you cannot install one or more bolts (7) because of the load on the forestay, manually push the NLG wheels forward to release the load.
NOTE: During the removal of the protective cover, one bolt must always stay installed to prevent the movement of the bearing.
(5) Install the protective cover (6), with the three bolts (7). NOTE: The bolt (7) that was installed in the opposite direction is in position.
(6) Through the nose gear compartment, remove the bolt (7) that was installed to prevent the movement of the bearing. (7) Install the remaining bolt (7) through the protective cover (6), and install the washers (3) and nuts (1).
(8) Tighten the nuts (1).
WARNING:
USE PROTECTIVE GOGGLES WHEN YOU REMOVE OR INSTALL A COTTER PIN. EACH TIME YOU REMOVE A COTTER PIN DURING THE TASK, DISCARD IT IMMEDIATELY. A LOOSE COTTER PIN CAN CUT YOU OR MAKE YOU BLIND.
(9) Safety the nuts (1) with the new AIPC 32-21-01-01-010 COTTER PINS (2) or AIPC 32-21-81-01-060 COTTER PINS (2).(10) Do a visual inspection of the swivel bearing from the inside of the nose gear compartment to:
- Make sure that it is correctly installed against the airframe panel, with no space between them.
Subtask 32-21-24-410-055-A
A. Close Access
(1) Lower the aircraft on ground (Ref. AMM TASK 07-11-00-586-001).
(2) Remove the access platform(s).
(3) Close access doors 812 and 822.
(4) Make sure that the work area is clean and clear of tools and other items.
(1) Lower the aircraft on ground (Ref. AMM TASK 07-11-00-586-001).
(2) Remove the access platform(s).
(3) Close access doors 812 and 822.
(4) Make sure that the work area is clean and clear of tools and other items.
Protective Cover of the Forestay Bearing