Reactivation of the Flight Control Data Concentrator (FCDC) 2 (FAA only)
TASK 27-95-00-440-801-A
Reactivation of the Flight Control Data Concentrator (FCDC) 2 (FAA only)
1. Reason for the Job
MMEL 27-95-01
FLIGHT CONTROL DATA CONCENTRATORS (FCDC) 2 (FAA ONLY)
2. Job Set-up Information
A. Work Zones and Access Panels
B. Referenced Information
3. Job Set-up
Subtask 27-95-00-861-051-A
Subtask 27-95-00-440-050-A
Subtask 27-95-00-942-051-A
[Rev.10 from 2021]
2026.03.31 23:59:48 UTC
Reactivation of the Flight Control Data Concentrator (FCDC) 2 (FAA only)
1. Reason for the Job
MMEL 27-95-01
FLIGHT CONTROL DATA CONCENTRATORS (FCDC) 2 (FAA ONLY)
2. Job Set-up Information
A. Work Zones and Access Panels
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 210 | CKPT,FWD COMPT BHD TO FLT COMPT BULKHEAD |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-42-00-861-001-A | Energize the Ground Service Network from the External Power |
| TASK 24-42-00-862-001-A | De-energize the Ground Service Network Supplied from the External Power |
Subtask 27-95-00-861-051-A
A. Aircraft Maintenance Configuration
(1) Energize the ground service network
(Ref. AMM TASK 24-42-00-861-001).
Subtask 27-95-00-865-051-A (1) Energize the ground service network
(Ref. AMM TASK 24-42-00-861-001).
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 121VU | FLIGHT CONTROLS/FCDC2/SPLY | 20CE2 | Q20 |
Subtask 27-95-00-440-050-A
A. Reactivation of the FCDC 2
(1) On circuit breaker panel 121VU:
(a) Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
5. Close-up(1) On circuit breaker panel 121VU:
(a) Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
- 20CE2.
Subtask 27-95-00-942-051-A
A. Put the aircraft back to its initial configuration.
(1) De-energize the ground service network
(Ref. AMM TASK 24-42-00-862-001).
(2) Make sure that the work area is clean and clear of tools and other items.
(1) De-energize the ground service network
(Ref. AMM TASK 24-42-00-862-001).
(2) Make sure that the work area is clean and clear of tools and other items.