Remove Offwing Escape Slide Inflation Reservoir for Hydrostatic Test
TASK 25-62-00-750-002-A
Remove Offwing Escape Slide Inflation Reservoir for Hydrostatic Test
Refer to the MPD TASK: 256242-01
REMOVE OFFWING ESCAPE SLIDE INFLATION RESERVOIR FOR HYDROSTATIC TEST
2. Job Set-up Information
A. Work Zones and Access Panels
B. Referenced Information
3. Job Set-up
Subtask 25-62-00-020-053-A ** ON A/C NOT FOR ALL 4. Procedure
Subtask 25-62-00-750-051-A ** ON A/C NOT FOR ALL
Subtask 25-62-00-420-053-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.03.31 23:40:14 UTC
Remove Offwing Escape Slide Inflation Reservoir for Hydrostatic Test
ZONE: 151
ZONE: 152
FIN: 7506MM ** ON A/C NOT FOR ALL
FIN: 7507MM ** ON A/C NOT FOR ALL
FIN: 7685MM ** ON A/C NOT FOR ALL
FIN: 7686MM ** ON A/C NOT FOR ALL
1. Reason for the JobZONE: 152
FIN: 7506MM ** ON A/C NOT FOR ALL
FIN: 7507MM ** ON A/C NOT FOR ALL
FIN: 7685MM ** ON A/C NOT FOR ALL
FIN: 7686MM ** ON A/C NOT FOR ALL
Refer to the MPD TASK: 256242-01
REMOVE OFFWING ESCAPE SLIDE INFLATION RESERVOIR FOR HYDROSTATIC TEST
2. Job Set-up Information
A. Work Zones and Access Panels
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 151 | AFT CARGO COMPARTMENT |
| 152 | AFT CARGO COMPARTMENT |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 25-62-46-000-001-A | Removal of the Inflation Reservoir for the Offwing Escape Slide |
| TASK 25-62-46-400-001-A | Installation of the Inflation Reservoir for the Offwing Escape Slide |
Subtask 25-62-00-020-053-A ** ON A/C NOT FOR ALL 4. Procedure
Subtask 25-62-00-750-051-A ** ON A/C NOT FOR ALL
A. System Test
(1) Send the offwing escape slide inflation reservoir to the workshop to do the hydrostatic test.
5. Close-up(1) Send the offwing escape slide inflation reservoir to the workshop to do the hydrostatic test.
Subtask 25-62-00-420-053-A ** ON A/C NOT FOR ALL