1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Referenced Information
REFERENCE
DESIGNATION
TASK 24-42-00-861-001-A
Energize the Ground Service Network from the External Power
TASK 24-42-00-862-001-A
De-energize the Ground Service Network Supplied from the External Power
3. Job Set-up
Subtask 25-45-33-860-052-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
   (1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
Subtask 25-45-33-865-055-A ** ON A/C NOT FOR ALL
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
2000VULIGHT-LAV1LQJ01
2001VULAVATORY AFT-OCCUPIED11WJB04
4. Procedure
Subtask 25-45-33-210-051-A ** ON A/C NOT FOR ALL
A. Preparation for Installation
   (1) Clean the component interfaces and the adjacent area.
   (2) Do a visual inspection of the component interfaces and the adjacent area.
   (3) Make sure that the parts retained from the removed component are clean and in the correct condition.
Subtask 25-45-33-420-051-A ** ON A/C NOT FOR ALL
B. Installation of the Door Microswitch of the Space Flex Lavatory
   (1) When you connect/install the components, refer to the match marks made during the removal procedure.
   (2) Carefully put the supports (3) together with the door microswitches (2) in position, then install the screws (4).
   (3) Tighten the screws (4).
   (4) Make sure that the work area is clean and clear of tools and other items.
   (5) Close the lavatory doors (1).
Subtask 25-45-33-865-054-A ** ON A/C NOT FOR ALL
C. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
2000VULIGHT-LAV1LQJ01
2001VULAVATORY AFT-OCCUPIED11WJB04
5. Close-up
Subtask 25-45-33-862-051-A ** ON A/C NOT FOR ALL
A. De-energize the ground service network
(Ref. AMM TASK 24-42-00-862-001).