W DOC AIRBUS | AMM A320F

Removal of the Lining


TASK 25-45-26-000-001-A
Removal of the Lining


ZONE: 200
1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
200
UPPER HALF FUSELAGE
 B. Referenced Information
REFERENCE
DESIGNATION
TASK 24-42-00-861-001-A
Energize the Ground Service Network from the External Power
TASK 25-45-38-000-001-A
Removal of the Washbasin
3. Job Set-up
Subtask 25-45-26-861-050-A
A. Aircraft Maintenance Configuration
   (1) Energize the ground service network
(Ref. AMM TASK 24-42-00-861-001).
Subtask 25-45-26-010-050-A
B. Get Access
   (1) If the washbasin is installed, remove it (Ref. AMM TASK 25-45-38-000-001) or (Ref. AMM D/O 38-32-43-00).
4. Procedure
Subtask 25-45-26-020-050-B
A. Remove the Lining
   (1) Remove the rollers (5) and the roller bracket (4).
   (2) Remove the screws (2), the washers (3) and the lining (1).