1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
Torque wrench: range to between 0.28 and 0.22 m.daN (24.78 and 19.47 lbf.in ) T
 B. Referenced Information
REFERENCE
DESIGNATION
TASK 24-42-00-861-001-A
Energize the Ground Service Network from the External Power
TASK 24-42-00-862-001-A
De-energize the Ground Service Network Supplied from the External Power
F Latch Assembly - Spacer ** ON A/C NOT FOR ALL
3. Job Set-up
Subtask 25-24-41-860-053-A
A. Aircraft Maintenance Configuration
   (1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
4. Procedure
Subtask 25-24-41-420-064-A ** ON A/C NOT FOR ALL
A. Installation of the Latch Assembly of the Overhead Stowage-Compartment Door.
   (1) Open the overhead bin door (1).
   (2) Put the latch assembly (4) in position.
   (3) Install the washers (3) and the screws (2).
   (4) Close the overhead bin door (1).
Subtask 25-24-41-420-064-B ** ON A/C NOT FOR ALL
A. Installation of the Latch Assembly of the Overhead Stowage-Compartment Door.
   (1) Make sure that the overhead stowage-compartment door (1) is open.
   (2) Put the latch assembly (2) in position.
   (3) Install the washers (3) and the screws (4).
   (4) TORQUE the screws (4) to between 0.28 and 0.22 m.daN (24.78 and 19.47 lbf.in ) T.
   (5) Close the overhead stowage-compartment door (1).
Subtask 25-24-41-420-065-A ** ON A/C NOT FOR ALL
B. Installation of the Latch Assembly of the Spacer.
F Latch Assembly - Spacer ** ON A/C NOT FOR ALL
   (1) Open the door (1).
   (2) Put the bracket in position and install the screws (6) and (7).
   (3) Put the latch assembly (5) and the cover (4) in position.
   (4) Install the washers (3) and screws (2).
   (5) Close the door (1).
5. Close-up
Subtask 25-24-41-862-053-A
A. De-energize the ground service network
(Ref. AMM TASK 24-42-00-862-001).