General Visual Inspection of Vertical Stabilizer Tip (EWIS)
TASK 05-23-20-200-004-A
General Visual Inspection of Vertical Stabilizer Tip (EWIS)
Refer to the MPD TASK: ZL-324-01
GENERAL VISUAL INSPECTION OF VERTICAL STABILIZER TIP (EWIS)
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 05-23-20-010-053-A
Subtask 05-23-20-210-053-A
Subtask 05-23-20-410-053-A
[Rev.10 from 2021]
2026.03.31 22:49:35 UTC
General Visual Inspection of Vertical Stabilizer Tip (EWIS)
ZONE: 324
1. Reason for the JobRefer to the MPD TASK: ZL-324-01
GENERAL VISUAL INSPECTION OF VERTICAL STABILIZER TIP (EWIS)
NOTE: This is an EWIS (Electrical Wiring Interconnection System) procedure. EWIS is defined in ESPM 20-33-11.
2. Job Set-up InformationA. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 12M (40 FT) - ADJUSTABLE |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 324 | VERTICAL STABILIZER TIP |
| 324AT |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 55-34-11-000-001-A | Removal of the Vertical Stabilizer Tip |
| TASK 55-34-11-400-001-A | Installation of the Vertical Stabilizer Tip |
Subtask 05-23-20-010-053-A
A. Get Access
(1) Put the ACCESS PLATFORM 12M (40 FT) - ADJUSTABLE in position at the vertical-stabilizer tip (zone 320).
(2) Remove the vertical stabilizer tip 324AT
(Ref. AMM TASK 55-34-11-000-001).
4. Procedure(1) Put the ACCESS PLATFORM 12M (40 FT) - ADJUSTABLE in position at the vertical-stabilizer tip (zone 320).
(2) Remove the vertical stabilizer tip 324AT
(Ref. AMM TASK 55-34-11-000-001).
Subtask 05-23-20-210-053-A
A. Inspection
(1) Do a general visual inspection of the vertical stabilizer tip (zone 324).
(2) Make sure that there are no signs of corrosion, cracks or damage.
(3) Make sure that all the installations (wiring) are attached correctly.
5. Close-up(1) Do a general visual inspection of the vertical stabilizer tip (zone 324).
(2) Make sure that there are no signs of corrosion, cracks or damage.
(3) Make sure that all the installations (wiring) are attached correctly.
Subtask 05-23-20-410-053-A
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the vertical stabilizer tip 324AT
(Ref. AMM TASK 55-34-11-400-001).
(3) Remove the access platform(s).
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the vertical stabilizer tip 324AT
(Ref. AMM TASK 55-34-11-400-001).
(3) Remove the access platform(s).
Vertical-Stabilizer Tip Area