GENERAL VISUAL INSPECTION OF NOSE GEAR WELL (EWIS)
TASK 05-21-20-200-012-A
GENERAL VISUAL INSPECTION OF NOSE GEAR WELL (EWIS)
1. Reason for the Job
Refer to the MPD TASK: ZL-123-02
GENERAL VISUAL INSPECTION OF NOSE GEAR WELL (EWIS)
A. Work Zones and Access Panels
B. Referenced Information
3. Job Set-up
Subtask 05-21-20-010-062-A 4. Procedure
Subtask 05-21-20-210-061-A
Subtask 05-21-20-410-062-A
[Rev.10 from 2021]
2026.03.31 22:48:34 UTC
GENERAL VISUAL INSPECTION OF NOSE GEAR WELL (EWIS)
1. Reason for the Job
Refer to the MPD TASK: ZL-123-02
GENERAL VISUAL INSPECTION OF NOSE GEAR WELL (EWIS)
NOTE: This is an EWIS (Electrical Wiring Interconnection System) procedure. EWIS is defined in ESPM 20-33-11.
2. Job Set-up InformationA. Work Zones and Access Panels
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 123 | NOSE GEAR WELL |
| 124 | NOSE GEAR WELL |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 32-22-00-010-001-A | Nose Gear Doors - Ground Doors Opening |
| TASK 32-22-00-410-001-A | Nose Gear Doors - Ground Doors Closing |
Subtask 05-21-20-010-062-A 4. Procedure
Subtask 05-21-20-210-061-A
A. Inspection
(1) Do a general visual inspection of the nose gear well (Zones 123 and 124).
(2) Make sure that there are no signs of corrosion, cracks or damage.
(3) Make sure that all the installations (wiring, ducting, piping) are attached correctly.
5. Close-up(1) Do a general visual inspection of the nose gear well (Zones 123 and 124).
(2) Make sure that there are no signs of corrosion, cracks or damage.
(3) Make sure that all the installations (wiring, ducting, piping) are attached correctly.
Subtask 05-21-20-410-062-A