Detailed Inspection of Disassembled AFT Engine Mount Installation including Mating Surfaces [CFMI]
TASK 71-22-11-210-040-A
Detailed Inspection of Disassembled AFT Engine Mount Installation including Mating Surfaces
Refer to the MPD TASK: 712211-01
DETAILED INSPECTION OF DISASSEMBLED AFT ENGINE MOUNT INSTALLATION INCLUDING MATING SURFACES.
2. Job Set-up Information
A. Work Zones and Access Panels
B. Referenced Information
3. Job Set-up
Subtask 71-22-11-010-056-A ** ON A/C NOT FOR ALL 4. Procedure
Subtask 71-22-11-210-053-A ** ON A/C NOT FOR ALL
Subtask 71-22-11-410-056-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.01 02:22:58 UTC
Detailed Inspection of Disassembled AFT Engine Mount Installation including Mating Surfaces
ZONE: 400
1. Reason for the JobRefer to the MPD TASK: 712211-01
DETAILED INSPECTION OF DISASSEMBLED AFT ENGINE MOUNT INSTALLATION INCLUDING MATING SURFACES.
2. Job Set-up Information
A. Work Zones and Access Panels
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 400 | POWER PLANT, NACELLES AND PYLONS |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 71-22-11-000-040-A | Removal of the Aft Engine Mount |
| TASK 71-22-11-400-040-A | Installation of the Aft Engine Mount |
Subtask 71-22-11-010-056-A ** ON A/C NOT FOR ALL 4. Procedure
Subtask 71-22-11-210-053-A ** ON A/C NOT FOR ALL
A. Do a detailed visual inspection of the aft engine mount as per ROHR CMM 712207 .
5. Close-upNOTE: Inspection is done with engine mount disassembled.
Subtask 71-22-11-410-056-A ** ON A/C NOT FOR ALL