Installation of the ATC/TCAS Control Unit
TASK 34-52-12-400-001-A
Installation of the ATC/TCAS Control Unit
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
B. Referenced Information
3. Job Set-up
Subtask 34-52-12-865-051-A
Subtask 34-52-12-420-050-A
Subtask 34-52-12-860-050-A
[Rev.10 from 2021]
2026.04.01 06:03:16 UTC
Installation of the ATC/TCAS Control Unit
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 211 | COCKPIT |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 34-52-00-740-004-A | BITE Test of the Air Traffic Control (ATC) |
Subtask 34-52-12-865-051-A
A. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 49VU | COM NAV/ATC/1 | 5SH1 | G11 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | COM NAV/ATC/2 | 5SH2 | K07 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | T/TISS | 2004SG | K07 |
Subtask 34-52-12-420-050-A
A. Installation of the ATC/TCAS Control Unit (3SH)
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Remove the blanking caps from the electrical connectors (3) and (4).
(4) Make sure that the electrical connectors are clean and in the correct condition.
(5) Connect the electrical connectors (4) to the ATC/TCAS Control Unit (2).
(6) Install the ATC/TCAS Control Unit (2) in its housing (5).
(7) Tighten the four quarter-turn fasteners (1).
Subtask 34-52-12-865-052-A NOTE: If the new ATC/TCAS control unit has some inoperative functions/modes, install the INOP labels that were on the removed ATC/TCAS control unit.
(1) Clean the component interfaces and the adjacent area.(2) Do an inspection of the component interfaces and the adjacent area.
(3) Remove the blanking caps from the electrical connectors (3) and (4).
(4) Make sure that the electrical connectors are clean and in the correct condition.
(5) Connect the electrical connectors (4) to the ATC/TCAS Control Unit (2).
(6) Install the ATC/TCAS Control Unit (2) in its housing (5).
(7) Tighten the four quarter-turn fasteners (1).
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 34-52-12-740-050-A 5. Close-up| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 49VU | COM NAV/ATC/1 | 5SH1 | G11 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | COM NAV/ATC/2 | 5SH2 | K07 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | T/TISS | 2004SG | K07 |
Subtask 34-52-12-860-050-A
A. Make sure that the work area is clean and clear of tools and other items.
ATC/TCAS Control Unit