Visual Check of NLG and MLG Downlock Springs and Attachments
TASK 32-30-00-200-002-A
Visual Check of NLG and MLG Downlock Springs and Attachments
Refer to the MPD TASK: 323000-01
VISUAL CHECK OF NLG AND MLG DOWNLOCK SPRINGS AND ATTACHMENTS.
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 32-30-00-941-056-A
Subtask 32-30-00-210-057-A
Subtask 32-30-00-942-056-A
[Rev.10 from 2021]
2026.04.01 00:43:41 UTC
Visual Check of NLG and MLG Downlock Springs and Attachments
WARNING:
PUT THE SAFETY DEVICES AND THE WARNING NOTICES IN POSITION BEFORE YOU START A TASK ON OR NEAR:
- THE FLIGHT CONTROLS
- THE FLIGHT CONTROL SURFACES
- THE LANDING GEAR AND THE RELATED DOORS
- COMPONENTS THAT MOVE.
WARNING:
MAKE SURE THAT THE GROUND SAFETY-LOCKS ARE IN POSITION ON THE LANDING GEAR. THIS WILL PREVENT UNWANTED MOVEMENT OF THE LANDING GEAR, AND THUS POSSIBLE INJURY TO PERSONS AND DAMAGE TO THE AIRCRAFT AND/OR EQUIPMENT.
1. Reason for the JobRefer to the MPD TASK: 323000-01
VISUAL CHECK OF NLG AND MLG DOWNLOCK SPRINGS AND ATTACHMENTS.
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 2M (6 FT) |
| No specific | 1 | LIGHT SOURCE - TORCH |
| No specific | AR | SAFETY BARRIER(S) |
| No specific | AR | WARNING NOTICE(S) |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 711 | NOSE GEAR |
| 713 | MAIN DOORS |
| 731 | L.H MAIN GEAR |
| 734 | MAIN DOOR |
| 741 | R.H MAIN GEAR |
| 744 | MAIN DOOR |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 32-00-00-481-001-A | Installation of the Safety Devices on the Landing Gears |
Subtask 32-30-00-941-056-A
A. Safety Precautions
(1) As necessary, use the applicable SAFETY BARRIERS, specified by the operator's instructions and your local regulations.
(2) Make sure that the ground safety locks are installed on the landing gears (Ref. AMM TASK 32-00-00-481-001).
(3) On panel 400VU:
Subtask 32-30-00-941-065-A (1) As necessary, use the applicable SAFETY BARRIERS, specified by the operator's instructions and your local regulations.
(2) Make sure that the ground safety locks are installed on the landing gears (Ref. AMM TASK 32-00-00-481-001).
(3) On panel 400VU:
- Make sure that the landing-gear control lever 6GA is in the DOWN position.
- Put the WARNING NOTICE(S) in position to tell persons not to operate the landing gears.
B. Installation of Equipment
(1) Put the ACCESS PLATFORM 2M (6 FT) in position adjacent to the applicable landing gear.
(2) Use the LIGHT SOURCE - TORCH to do the inspection.
4. Procedure(1) Put the ACCESS PLATFORM 2M (6 FT) in position adjacent to the applicable landing gear.
(2) Use the LIGHT SOURCE - TORCH to do the inspection.
Subtask 32-30-00-210-057-A
A. Visual Check of the MLG Downlock Springs and Attachments
(1) Make sure that the downlock springs (1) and (3) are correctly attached to the sidestay and the center joint link (2).
Subtask 32-30-00-210-058-A (1) Make sure that the downlock springs (1) and (3) are correctly attached to the sidestay and the center joint link (2).
B. Visual Check of the NLG Downlock Springs and Attachments
(1) Make sure that the downlock springs (5) and (7) are correctly attached to the upper brackets (8) and the pin (6).
5. Close-up(1) Make sure that the downlock springs (5) and (7) are correctly attached to the upper brackets (8) and the pin (6).
Subtask 32-30-00-942-056-A
A. Removal of Equipment
(1) Remove the access platform(s).
(2) Remove the ground support and maintenance equipment, the special and standard tools and all other items.
(3) Remove the SAFETY BARRIERS.
(4) Remove the WARNING NOTICE(S).
(1) Remove the access platform(s).
(2) Remove the ground support and maintenance equipment, the special and standard tools and all other items.
(3) Remove the SAFETY BARRIERS.
(4) Remove the WARNING NOTICE(S).
MLG Downlock Springs and Attachments