Removal of the Hinge Assembly
TASK 25-24-41-000-804-A
Removal of the Hinge Assembly
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Referenced Information
3. Job Set-up
Subtask 25-24-41-860-062-A ** ON A/C NOT FOR ALL
Subtask 25-24-41-020-076-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.01 06:09:21 UTC
Removal of the Hinge Assembly
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Referenced Information
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-42-00-861-001-A | Energize the Ground Service Network from the External Power |
| TASK 25-24-41-000-002-A | Removal of the Door of the Overhead Stowage-Compartment |
Subtask 25-24-41-860-062-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
(1) Energize the ground service network
(Ref. AMM TASK 24-42-00-861-001).
4. Procedure(1) Energize the ground service network
(Ref. AMM TASK 24-42-00-861-001).
Subtask 25-24-41-020-076-A ** ON A/C NOT FOR ALL
A. Removal of the Hinge Assembly
(1) Remove the applicable overhead stowage-compartment door (Ref. AMM TASK 25-24-41-000-002).
(2) Hold the hinge assembly (1).
(3) Remove the screws (2) and the washers (3) from the hinge assembly (1).
(4) Carefully remove the hinge assembly (1).
(1) Remove the applicable overhead stowage-compartment door (Ref. AMM TASK 25-24-41-000-002).
(2) Hold the hinge assembly (1).
(3) Remove the screws (2) and the washers (3) from the hinge assembly (1).
(4) Carefully remove the hinge assembly (1).
Hinge Assembly