GENERAL VISUAL INSPECTION OF AIR INTAKE LIP (EWIS)
TASK 05-24-30-200-001-A
GENERAL VISUAL INSPECTION OF AIR INTAKE LIP (EWIS)
1. Reason for the Job
Refer to the MPD TASK: ZL-433-01
GENERAL VISUAL INSPECTION OF AIR INTAKE LIP (EWIS)
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 05-24-30-010-050-A ** ON A/C NOT FOR ALL
Subtask 05-24-30-210-050-A ** ON A/C NOT FOR ALL
Subtask 05-24-30-410-050-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.03.31 22:49:52 UTC
GENERAL VISUAL INSPECTION OF AIR INTAKE LIP (EWIS)
1. Reason for the Job
Refer to the MPD TASK: ZL-433-01
GENERAL VISUAL INSPECTION OF AIR INTAKE LIP (EWIS)
NOTE: This is an EWIS (Electrical Wiring Interconnection System) procedure. EWIS is defined in ESPM 20-33-11.
2. Job Set-up InformationA. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | AR | ACCESS PLATFORM 2M (6 FT) |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 433 | AIR INTAKE LIP |
| 434 | AIR INTAKE LIP |
| 443 | AIR INTAKE LIP |
| 444 | AIR INTAKE LIP |
| 434AR, 437AL, 438AR, 444AR, 447AL, 448AR | |
| 433AZ, 433BZ, 434BZ, 443AZ, 443BZ, 444BZ | |
| 434BR, 444BR |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 71-13-00-010-010-A | Opening of the Fan Cowls 437AL(447AL),438AR(448AR) |
| TASK 71-13-00-010-040-A | Opening of the Fan Cowl Doors |
| TASK 71-13-00-010-040-B | Opening of the Fan Cowl Doors |
| TASK 71-13-00-410-010-A | Closing of the Fan Cowls 437AL(447AL),438AR(448AR) |
| TASK 71-13-00-410-040-A | Closing of the Fan Cowl Doors |
| TASK 71-13-00-410-040-B | Closing of the Fan Cowl Doors |
Subtask 05-24-30-010-050-A ** ON A/C NOT FOR ALL
A. Get Access
(1) Put an ACCESS PLATFORM 2M (6 FT) in position at zones 433 and 443.
(2) Open the fan cowl doors:
437AL, 438AR, 447AL and 448AR (Ref. AMM TASK 71-13-00-010-040).
(3) Remove the access panels:
433AZ 433BZ,
434AR 434BZ,
443AZ 443BZ,
444AR 444BZ.
Subtask 05-24-30-010-050-C ** ON A/C NOT FOR ALL (1) Put an ACCESS PLATFORM 2M (6 FT) in position at zones 433 and 443.
(2) Open the fan cowl doors:
437AL, 438AR, 447AL and 448AR (Ref. AMM TASK 71-13-00-010-040).
(3) Remove the access panels:
433AZ 433BZ,
434AR 434BZ,
443AZ 443BZ,
444AR 444BZ.
A. Get Access
(1) Put an ACCESS PLATFORM 2M (6 FT) in position at zones 433 and 443.
(2) Remove the access panels:
434AR 434BR,
444AR 444BR.
(3) Open the fan cowl doors 437AL, 438AR, 447AL and 448AR (Ref. AMM TASK 71-13-00-010-010).
4. Procedure(1) Put an ACCESS PLATFORM 2M (6 FT) in position at zones 433 and 443.
(2) Remove the access panels:
434AR 434BR,
444AR 444BR.
(3) Open the fan cowl doors 437AL, 438AR, 447AL and 448AR (Ref. AMM TASK 71-13-00-010-010).
Subtask 05-24-30-210-050-A ** ON A/C NOT FOR ALL
A. Inspection
(1) Do a general visual inspection of the air intake lip and the inlet cowl.
(2) Make sure that there are no signs of corrosion, cracks or damage.
(3) Make sure that all the installations (wiring, ducting, piping) are correctly attached.
5. Close-up(1) Do a general visual inspection of the air intake lip and the inlet cowl.
(2) Make sure that there are no signs of corrosion, cracks or damage.
(3) Make sure that all the installations (wiring, ducting, piping) are correctly attached.
Subtask 05-24-30-410-050-A ** ON A/C NOT FOR ALL
A. Close Access
(1) Install the access panels:
433AZ 433BZ,
434AR 434BZ,
443AZ 443BZ,
444AR 444BZ.
(2) Close the fan cowl doors 437AL, 438AR, 447AL and 448AR (Ref. AMM TASK 71-13-00-410-040).
(3) Remove the access platform(s).
Subtask 05-24-30-410-050-C ** ON A/C NOT FOR ALL (1) Install the access panels:
433AZ 433BZ,
434AR 434BZ,
443AZ 443BZ,
444AR 444BZ.
(2) Close the fan cowl doors 437AL, 438AR, 447AL and 448AR (Ref. AMM TASK 71-13-00-410-040).
(3) Remove the access platform(s).
Access Doors of the Left Nacelle (Left Side)