GENERAL VISUAL INSPECTION OF TAIL CONE APU AIR INTAKE AREA (EWIS)
TASK 05-23-10-200-002-A
GENERAL VISUAL INSPECTION OF TAIL CONE APU AIR INTAKE AREA (EWIS)
1. Reason for the Job
Refer to the MPD TASK: ZL-313-01
GENERAL VISUAL INSPECTION OF TAIL CONE APU AIR INTAKE AREA (EWIS)
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 05-23-10-010-051-A
Subtask 05-23-10-210-051-A
Subtask 05-23-10-410-051-A
[Rev.10 from 2021]
2026.03.31 22:49:28 UTC
GENERAL VISUAL INSPECTION OF TAIL CONE APU AIR INTAKE AREA (EWIS)
1. Reason for the Job
Refer to the MPD TASK: ZL-313-01
GENERAL VISUAL INSPECTION OF TAIL CONE APU AIR INTAKE AREA (EWIS)
NOTE: This is an EWIS (Electrical Wiring Interconnection System) procedure. EWIS is defined in ESPM 20-33-11.
2. Job Set-up InformationA. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | AR | ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 313 | TAIL CONE APU AIR INTAKE AREA |
| 314 | TAIL CONE APU AIR INTAKE AREA |
| 314AR |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 52-41-23-010-801-A | Opening of Access Door 314AR |
| TASK 52-41-23-410-801-A | Closing of Access Door 314AR |
Subtask 05-23-10-010-051-A
A. Get Access
(1) Put an ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE in position at the zone 310.
(2) Open the access door 314AR (Ref. AMM TASK 52-41-23-010-801).
4. Procedure(1) Put an ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE in position at the zone 310.
(2) Open the access door 314AR (Ref. AMM TASK 52-41-23-010-801).
Subtask 05-23-10-210-051-A
A. Inspection
(1) Do a general visual inspection of the air intake area of the Auxiliary Power Unit (APU) on the tail cone (Zones 313 and 314).
(2) Make sure that there are no signs of corrosion, cracks or damage.
(3) Make sure that all the installations (wiring, ducting, piping) are attached correctly.
5. Close-up(1) Do a general visual inspection of the air intake area of the Auxiliary Power Unit (APU) on the tail cone (Zones 313 and 314).
(2) Make sure that there are no signs of corrosion, cracks or damage.
(3) Make sure that all the installations (wiring, ducting, piping) are attached correctly.
Subtask 05-23-10-410-051-A
A. Close Access
(1) Close the access door 314AR (Ref. AMM TASK 52-41-23-410-801).
(2) Remove the access platform(s).
(1) Close the access door 314AR (Ref. AMM TASK 52-41-23-410-801).
(2) Remove the access platform(s).
Access Provision of the Aft Fuselage Tail Section