W DOC AIRBUS | TSM A320F

Loss of Phase A of the Windshield Power Supply


TASK 30-42-00-810-802-A
Loss of Phase A of the Windshield Power Supply


1. Possible Causes
  • WHC-1 [2DG1]
  • wiring between pin A/G of the WHC 1 (2DG1) and ground terminal
  • wiring between pin A/A of the WHC 1 (2DG1) and the circuit breaker (1DG1)
  • C/B-ANTI ICE/L/WHSLD [1DG1]
2. Job Set-up Information
 A. Referenced Information
REFERENCE
DESIGNATION
TSM TASK 24-00-00-810-803-A
Circuit Breaker Tripped and/or C/B TRIPPED Warning
AMM 30-42-00-710-001
Operational Test of the Windshield Anti-Icing and Defogging
ASM 304201
AMM 30-42-34-000-001
Removal of the Window Heat Computer (WHC)
AMM 30-42-34-400-001
Installation of the Window Heat Computer (WHC)
3. Fault Confirmation
Subtask 30-42-00-710-052-A
A. Test
   (1) Do the operational test of the windshield anti-icing and defogging AMM 30-42-00-710-001.
4. Fault Isolation
Subtask 30-42-00-865-051-A
A. Table of the circuit breakers used in this procedure:
PANELDESIGNATIONFINLOCATION
** ON A/C ALL
123VUANTI ICE/L/WHSLD1DG1AF10
Subtask 30-42-00-810-051-A
B. If the test gives the maintenance message CHECK WINDSHIELD WHC1 SUPPLY:
  • do a check of the status of the circuit breaker (1DG1).
   (1) If the circuit breaker is closed:
  • do a check for 115VAC at pin A/A of the WHC 1 (2DG1) ASM 304201.
     (a) If there is 115VAC:
     (b) If there is no 115VAC:
  • do a check for a ground signal at pin A/G of the WHC 1 (2DG1).
       1 If there is no ground signal:
no ground signal:
  • repair the wiring between pin A/G of the WHC 1 (2DG1) and ground terminal.
       2 If there is a ground signal:
  • do a check of the wiring between pin A/A of the WHC 1 (2DG1) and the circuit breaker (1DG1).
         a If there is no continuity:
  • repair the above wiring.
         b If there is continuity:
  • Replace the C/B-ANTI ICE/L/WHSLD [1DG1] .
   (2) If the circuit breaker is open:
     (a) If the fault continues:
  • Replace the C/B-ANTI ICE/L/WHSLD [1DG1] .
     (b) If the fault continues:
  • Replace the WHC-1 [2DG1] .
Subtask 30-42-00-710-053-A
C. Do the operational test given in Para. 3.
[Rev.8 from Aug 2018] 2026.04.04 04:29:40 UTC