Loss of the Left Aileron Changeover Signal for the ELAC 1
TASK 27-10-00-810-811-A
Loss of the Left Aileron Changeover Signal for the ELAC 1
1. Possible Causes
A. Referenced Information
3. Fault Confirmation
Subtask 27-10-00-860-062-A
Subtask 27-10-00-810-060-A
[Rev.8 from Aug 2018]
2026.04.04 04:27:26 UTC
Loss of the Left Aileron Changeover Signal for the ELAC 1
1. Possible Causes
- ELAC-1 [2CE1]
wiring between the COM part and the MON part of the ELAC 1, from DSO 2 (COM) to DSI 33 (MON) and from DSO 2 (MON) to DSI 33 (COM)
A. Referenced Information
| REFERENCE | DESIGNATION |
|---|---|
| ASM 279236 | |
| AMM 27-93-34-000-001 | Removal of the ELAC |
| AMM 27-93-34-400-001 | Installation of the ELAC |
| AMM 27-96-00-740-001 | BITE Test of the EFCS (Ground Scanning) |
| AMM 29-10-00-863-003 | Pressurize the Blue Hydraulic System with a Hydraulic Ground Power-Cart |
| AMM 29-10-00-864-003 | Depressurize the Blue Hydraulic System |
| AMM 29-23-00-863-001 | Pressurize the Green Hydraulic System from the Yellow Hydraulic System through the PTU with the Electric Pump |
| AMM 29-23-00-864-001 | Depressurize the Green and Yellow Hydraulic Systems after Operation of the PTU |
| AMM 29-24-00-863-001 | Pressurize the Yellow Hydraulic System with the Electric Pump |
| AMM 29-24-00-864-001 | Depressurize the Yellow Hydraulic System |
Subtask 27-10-00-860-062-A
A. Job Set-Up
(1) Pressurize the aircraft hydraulic systems AMM 29-10-00-863-003, AMM 29-23-00-863-001, AMM 29-24-00-863-001.
Subtask 27-10-00-740-052-A Subtask 27-10-00-860-063-A (1) Pressurize the aircraft hydraulic systems AMM 29-10-00-863-003, AMM 29-23-00-863-001, AMM 29-24-00-863-001.
C. Put the aircraft back to its initial configuration.
(1) Depressurize the aircraft hydraulic systems AMM 29-10-00-864-003, AMM 29-23-00-864-001, AMM 29-24-00-864-001.
4. Fault Isolation(1) Depressurize the aircraft hydraulic systems AMM 29-10-00-864-003, AMM 29-23-00-864-001, AMM 29-24-00-864-001.
Subtask 27-10-00-810-060-A
A. If the test gives the maintenance message:
CHECK L AIL CHANGE OVER OF ELAC 1
Subtask 27-10-00-740-053-A CHECK L AIL CHANGE OVER OF ELAC 1
- replace the ELAC-1 [2CE1] , AMM 27-93-34-000-001 and AMM 27-93-34-400-001.
- do a check and repair the
wiring between the COM part and the MON part of the ELAC 1, from DSO 2 (COM) to DSI 33 (MON) and from DSO 2 (MON) to DSI 33 (COM) , ASM 279236.
B. Do the test given in Para. 3.