W DOC AIRBUS | MMEL ITEMS A320F

ACT 1 Inlet Valve


28-28-09ACT 1 Inlet Valve
Applicable to: -
28-28-09-B All ACTs empty
Repair intervalNbr installedNbr requiredPlacard
C
13.04.2026
10No
May be inoperative in the closed position provided that there is no fuel in any ACT.

28-28-09-C ACTs fuel not usable
Repair intervalNbr installedNbr requiredPlacard
C
13.04.2026
10No
(o)(m)
May be inoperative in the closed position provided that:

1)
The fuel quantity in the ACTs is considered as not usable and as part of the ZFW and is taken into account for CG determination, and

2)
The ACT transfer valve is secured in the closed position.

28-28-09-D Use of ACT 1 fuel
Repair intervalNbr installedNbr requiredPlacard
C
13.04.2026
10No
(m)
May be inoperative in the open position provided that:

1)
The (If Installed) ACT 2 is empty, and

2)
The ACT transfer valve is checked operative before each flight when the ACT 1 is used.