1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Consumable Materials
REFERENCE
DESIGNATION
(Material No.06AAB1)
Polysulfide Sealant-General Purpose Fillet -
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
211
COCKPIT
212
COCKPIT
211DW, 211GW, 211PW, 212DW, 212GW, 212PW
 C. Expendable Parts
FIG.ITEM
DESIGNATION
IPC-CSN
25
COTTER PIN
AIPC 56-12-01-01-060
29
COTTER PIN
AIPC 56-12-01-01-060
34
COTTER PIN
AIPC 56-12-01-01-060
36
COTTER PIN
AIPC 56-12-01-01-060
38
COTTER PIN
AIPC 56-12-01-01-060
42
COTTER PIN
AIPC 56-12-01-01-060
55
COTTER PIN
AIPC 56-12-01-01-060
25
COTTER PIN
AIPC 56-12-81-01-010
29
COTTER PIN
AIPC 56-12-81-01-010
34
COTTER PIN
AIPC 56-12-81-01-010
36
COTTER PIN
AIPC 56-12-81-01-010
38
COTTER PIN
AIPC 56-12-81-01-010
42
COTTER PIN
AIPC 56-12-81-01-010
55
COTTER PIN
AIPC 56-12-81-01-010
 D. Referenced Information
REFERENCE
DESIGNATION
3. Job Set-up
Subtask 56-12-12-869-050-A
A. Aircraft Maintenance Configuration
   (1) Make sure that the access platform is in position.
Subtask 56-12-12-865-051-A
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
PANELDESIGNATIONFINLOCATION
** ON A/C ALL
121VUCOM NAV/RADAR/15SQ1K13
** ON A/C NOT FOR ALL
121VUCOM NAV/RADAR/25SQ2K14
** ON A/C ALL
122VUANTI ICE/WINDOWS/R4DG2W14
122VUANTI ICE/WHC/25DG2W13
122VUANTI ICE/WINDOWS/L4DG1X14
122VUANTI ICE/WHC/15DG1X13
123VUANTI ICE/L/WHSLD1DG1AF10
123VUANTI ICE/R/WHSLD1DG2AF03
4. Procedure
Subtask 56-12-12-420-050-A
A. Installation of the Actuating Mechanism
   (1) Installation of the locking lever assembly (44).
     (a) Apply Polysulfide Sealant-General Purpose Fillet - (Material No.06AAB1) to the contact surfaces of the fitting (53).
     (b) Install the trunnion (49) on the fitting (53).
     (c) Install the fitting (53) with the bolts (54) and the nuts (57).
     (d) Install the bolts (59) and (60) and the nuts (52).
     (e) Tighten the nuts (57).
     (f) Tighten the nuts (52).
     (g) Install the slide (47) on the locking lever (44) with the pin (45).
     (h) Put the spring (48) in position.
     (i) Install the slide (47) in the trunnion (49). Install the bolt (58).
     (j) Install the washer (56).
     (k) Install a new AIPC 56-12-01-01-060 COTTER PIN (55) or AIPC 56-12-81-01-010 COTTER PIN (55).
   (2) Installation of the bellcrank (51).
     (a) Put the bellcrank (51) in position. Install the bolt (61).
     (b) Install the washer (26).
     (c) Install a new
AIPC 56-12-01-01-060 COTTER PIN (25) or AIPC 56-12-81-01-010 COTTER PIN (25).
   (3) Installation of the rod (40).
     (a) Put the rod (40) in position. Install the bolts (43) and (46).
     (b) Install the washers (41) and (39).
     (c) Install a new
AIPC 56-12-01-01-060 COTTER PIN (42) or AIPC 56-12-81-01-010 COTTER PIN (42).
     (d) Install a new
AIPC 56-12-01-01-060 COTTER PIN (38) or AIPC 56-12-81-01-010 COTTER PIN (38).
   (4) Installation of the control lever assembly (31).
     (a) Apply Polysulfide Sealant-General Purpose Fillet - (Material No.
06AAB1) to the contact surfaces of the bracket (24).
     (b) Put the bracket (24) in position. Install the bolts (21) and (22) and the nuts (28) and (27).
     (c) Tighten the nuts (28) and (27).
     (d) Put the control lever (31) in position. Install the bolt (23).
     (e) Install the washer (30).
     (f) Install a new AIPC 56-12-01-01-060 COTTER PIN (29) or AIPC 56-12-81-01-010 COTTER PIN (29).
   (5) Installation of the rod (35).
     (a) Put the rod (35) in position. Install the bolts (50) and (32).
     (b) Install the washers (37) and (33).
     (c) Install a new
AIPC 56-12-01-01-060 COTTER PIN (34) or AIPC 56-12-81-01-010 COTTER PIN (34).
     (d) Install a new
AIPC 56-12-01-01-060 COTTER PIN (36) or AIPC 56-12-81-01-010 COTTER PIN (36).
Subtask 56-12-12-720-050-A
B. Testing
   (1) Do a functional test of the mechanism to make sure that it operates correctly :
     (a) Operate the sliding window mechanism.
     (b) Do this procedure two times.
5. Close-up
Subtask 56-12-12-410-050-A
A. Installation of the Access Panels
   (1) Make sure that the sliding window is open.
   (2) Installation of the panel 211PW 212PW.
     (a) Put the panel 211PW 212PW in position.
     (b) Install the washer (16) and the screw (15) and tighten them.
     (c) Tighten the fastener (1).
   (3) Installation of the lining panel 211DW 212DW.
     (a) Put the lining panel 211DW 212DW in position.
     (b) Tighten the fasteners (4)
     (c) Install the washers (2) and (5) and the screws (3) and (6) and tighten them.
     (d) Installation of the lining panel 211GW 212GW.
     (e) Put the electrical cable (13) in position on the lining panel.
     (f) Install the clamp (10), the washer (11) and the screw (12) on the support (14). Tighten the screw (12).
     (g) Put the lining panel 211GW 212GW in position.
     (h) Tighten the fasteners (9).
     (i) Install the washers (7) and the screws (8) and tighten them.
Subtask 56-12-12-865-052-A
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C ALL
121VUCOM NAV/RADAR/15SQ1K13
** ON A/C NOT FOR ALL
121VUCOM NAV/RADAR/25SQ2K14
** ON A/C ALL
122VUANTI ICE/WINDOWS/R4DG2W14
122VUANTI ICE/WHC/25DG2W13
122VUANTI ICE/WINDOWS/L4DG1X14
122VUANTI ICE/WHC/15DG1X13
123VUANTI ICE/L/WHSLD1DG1AF10
123VUANTI ICE/R/WHSLD1DG2AF03
Subtask 56-12-12-942-050-A
C. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.
   (2) Remove the access platform(s).