Preparation of the Rudder Fillet Fairing for Installation
TASK 55-43-19-560-002-A
Preparation of the Rudder Fillet Fairing for Installation
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Consumable Materials
B. Referenced Information
3. Job Set-up
Subtask 55-43-19-010-051-A
Subtask 55-43-19-420-050-A
[Rev.10 from 2021]
2026.04.01 02:06:29 UTC
Preparation of the Rudder Fillet Fairing for Installation
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Consumable Materials
| REFERENCE | DESIGNATION |
|---|---|
| (Material No.06AEA1) | Polysulfide Sealant-Low Adhesion Brushable - |
| REFERENCE | DESIGNATION |
|---|---|
Subtask 55-43-19-010-051-A
A. There is no special job set-up for this task.
4. ProcedureSubtask 55-43-19-420-050-A
A. Prepare the Rudder Filet Fairing for Installation
(1) Make sure that the parts retained from the removed component are clean and in the correct condition.
(2) Examine all related anchor nuts for a good condition.
(3) If you have removed the sealing strips (6) and the plates (3) apply the Polysulfide Sealant-Low Adhesion Brushable - (Material No.06AEA1) to the screws (5).
(4) Install the sealing strips (6), the plates (3), the washers (4) and the screws (5) to the cover (1).
(1) Make sure that the parts retained from the removed component are clean and in the correct condition.
(2) Examine all related anchor nuts for a good condition.
(3) If you have removed the sealing strips (6) and the plates (3) apply the Polysulfide Sealant-Low Adhesion Brushable - (Material No.06AEA1) to the screws (5).
(4) Install the sealing strips (6), the plates (3), the washers (4) and the screws (5) to the cover (1).
Rudder Fillet Fairing