Installation of the Lining and Insulation
TASK 52-32-13-400-001-A
Installation of the Lining and Insulation
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Referenced Information
3. Job Set-up
Subtask 52-32-13-860-050-A
Subtask 52-32-13-420-050-E
Subtask 52-32-13-865-052-A
[Rev.10 from 2021]
2026.04.01 01:42:22 UTC
Installation of the Lining and Insulation
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 52-30-00-860-001-A | Open the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump |
| TASK 52-30-00-860-002-A | Close the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump |
Subtask 52-32-13-860-050-A
A. Aircraft Maintenance Configuration
(1) Make sure that the Aft cargo-compartment door (referred to as cargo door) is opened and the actuator safety locks are installed (Ref. AMM TASK 52-30-00-860-001).
(2) Make sure that the ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE is in position below the opened cargo door.
Subtask 52-32-13-865-051-A (1) Make sure that the Aft cargo-compartment door (referred to as cargo door) is opened and the actuator safety locks are installed (Ref. AMM TASK 52-30-00-860-001).
(2) Make sure that the ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE is in position below the opened cargo door.
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/HYD POWER/Y | 3803GX | N30 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/HYD POWER/Y | 3803GX | N31 |
| ** ON A/C ALL | |||
| 122VU | DOORS/CARGO | 1MJ | T12 |
| 123VU | Y HYD/ELEC/PUMP | 3802GX | AB06 |
| 123VU | Y HYD/ELEC/ELEC PUMP/NORM | 3801GX | AB03 |
Subtask 52-32-13-420-050-E
A. Installation of the Protective Lining
(1) Put the protective lining (3) together with the self-adhesive insulation mat in position at the cargo door (1) and engage the VELCRO tapes.
(2) Attach the protective lining (3) with the quick-release fasteners (2) to the cargo door (1).
5. Close-up(1) Put the protective lining (3) together with the self-adhesive insulation mat in position at the cargo door (1) and engage the VELCRO tapes.
(2) Attach the protective lining (3) with the quick-release fasteners (2) to the cargo door (1).
Subtask 52-32-13-865-052-A
A. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 52-32-13-410-050-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/HYD POWER/Y | 3803GX | N30 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/HYD POWER/Y | 3803GX | N31 |
| ** ON A/C ALL | |||
| 122VU | DOORS/CARGO | 1MJ | T12 |
| 123VU | Y HYD/ELEC/PUMP | 3802GX | AB06 |
| 123VU | Y HYD/ELEC/ELEC PUMP/NORM | 3801GX | AB03 |
B. Close Access
(1) Remove the actuator safety locks and close the Aft cargo door (Ref. AMM TASK 52-30-00-860-002).
(2) Remove the access platform(s).
(1) Remove the actuator safety locks and close the Aft cargo door (Ref. AMM TASK 52-30-00-860-002).
(2) Remove the access platform(s).
Lining and Insulation of the Aft Cargo-Compartment Door